Case Study 1: Dynamic Load Balancing with 2-Level UPFC in a Transmission Corridor

A black icon of a calendar showing a grid of dates.

May 27, 2025 | Blog

Diagram of power plant to infinite bus transmission showing load balancing via UPFC, with 75 MW in and 45 MW out.

Client: Confidential

Location: Southeastern USA

System Configuration: Single-machine to infinite bus system with parallel lines

Objective: Prevent line overload during rapid generation shifts

Background:

A power plant in the southeastern U.S. experienced overloading on its secondary transmission line (Line 1B) whenever active generation ramped up beyond 120 MW due to seasonal peak demand. The primary line (Line 1) was underutilized due to a lack of dynamic flow control.



This scenario highlights the importance of unified power flow controller (UPFC) solutions for effective power flow control in transmission lines under dynamic operating conditions.

Solution Implemented:

Keentel Engineering deployed a 2-level Unified Power Flow Controller (UPFC) on Line 1, as modeled in the referenced IEEE study. The UPFC’s series compensator regulated active power while the shunt branch maintained DC bus and voltage stability.


The implementation enabled dynamic load balancing in the power system by actively controlling line loading and redistributing power flow.

Technical Highlights:

  • Initial Generation: 75 MW (25 MW via Line 1, 50 MW via Line 1B)
  • Ramped Generation: 140 MW post 100ms demand spike
  • Power Re-routing: UPFC dynamically rerouted power to Line 1, reducing Line 1B stress
  • Control Strategy: Block diagram-based d-q rotating frame control as shown on page 2, Fig. 3

Results:

  • Maintained power flow within the 80 MW thermal limit of Line 1B
  • Enabled flexible generation ramping without reconfiguration
  • Improved system stability and minimized reactive power losses


To implement similar solutions, explore our power system studies services


Case Study 2: Voltage Support in Urban Substation Using Shunt Compensation

Client: Confidential

Location: Midwest USA

System Configuration: 400 kV ring bus with dual supply and dynamic RL load

Objective: Mitigate voltage sag at critical urban bus under fluctuating load

Background:

A major metropolitan area in the Midwest observed voltage dips at a distribution bus (Bus 2) when reactive-heavy RL industrial loads were introduced. The instability risked tripping protection relays and violating utility voltage criteria.


Voltage stability in power systems becomes critical under reactive load conditions, especially in urban substations with fluctuating demand.

Solution Implemented:

Keentel Engineering integrated a 2-level UPFC at Bus 2 using the configuration described in page 3, Fig. 9. The shunt branch regulated reactive power injection, while the series branch maintained power flow balance across Line 1.


The UPFC provided fast voltage support by injecting reactive power, helping maintain stable bus voltage during transient disturbances.

System Parameters:

  • Base Load: 80 MW
  • Disturbance Load: 5 MW + 75 MVAr RL load added at 0.02 sec
  • Control Mechanism: Reactive power control via d-q frame (equation 9, page 2)

Results:

  • Voltage sag was reduced by 12% compared to the non-UPFC case (Fig. 10, page 3)
  • Reactive power injected adaptively, peaking at 0.8 pu during maximum load
  • Voltage restored to nominal value within 50ms of disturbance

A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.

Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Leave a Comment

Related Posts

Power Swing Blocking, Out-of-Step Tripping and NERC PRC-026: How Distance Relays Tell Swings from Fa
By SANDIP R PATEL • November 14, 2026
Learn power swing blocking, out-of-step tripping, distance relay settings and NERC PRC-026 compliance with Keentel Engineering's technical guide.
NEC 2026 Field Guide showing electrical code changes for load calculations, grounding, energy manage
By SANDIP R PATEL • November 14, 2026
Explore NEC 2026 changes to load calculations, grounding, ampacity, wiring, solar, ESS and EV systems with Keentel Engineering's practical field guide. Copy
Data Center Tiers I–IV comparison showing redundancy, concurrent maintainability and fault tolerance
By SANDIP R PATEL • November 14, 2026
Explore Data Center Tiers I–IV, N+1 vs. 2N redundancy, concurrent maintainability, fault tolerance, and MEP design requirements with Keentel Engineering.
NERC compliance engineering standards covering PRC, MOD, TPL, FAC, VAR, EOP and CIP.
By SANDIP R PATEL • November 14, 2026
Explore NERC compliance engineering for generator and transmission owners, IBRs and large loads, covering PRC, MOD, TPL standards, audits and modeling.
LVRT to HVRT transition in weak grids showing post-fault overvoltage and inverter voltage response.
By SANDIP R PATEL • November 14, 2026
Learn why LVRT becomes HVRT in weak grids, how post-fault overvoltage trips solar, wind and BESS plants, and how Keentel Engineering uses EMT studies.
STATCOM V-I characteristic graph showing voltage regulation, current limits and short-term overload.
By SANDIP R PATEL • November 14, 2026
Explore STATCOM V-I characteristics, voltage control slope, current limits, short-term overload ratings, reactive power and low-voltage grid performance.
Ground distance protection R-X diagram showing mho and quadrilateral relay settings for a 230 kV lin
By SANDIP R PATEL • November 12, 2026
Learn ground distance protection settings for transmission lines: k0 compensation, mho and quadrilateral relays, mutual coupling and NERC compliance.
800 VDC vs. 1,500 VDC AI data center power distribution chart comparing rack current and conductor l
By SANDIP R PATEL • November 12, 2026
Compare 800 VDC vs. 1500 VDC for AI data centers. Explore efficiency, copper savings, DC protection, safety and power distribution with Keentel Engineering.
Transformer overcurrent protection 51/50 time-current coordination curves showing relay settings and
By SANDIP R PATEL • November 12, 2026
Learn transformer overcurrent protection using 50/51 relay stages, inverse-time curves, inrush checks, fault coordination and arc-flash mitigation.