A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime

ERCOT NOGRR245 Compliance Services – Meet the September 15, 2025 Deadline with Keentel Engineering

Calendar icon. D

August 6, 2025 | Blog

ERCOT NOGRR245 compliance services with a map of Texas and wind turbines. Deadline is September 15, 2023.

Introduction

The Public Utility Commission of Texas (PUCT) and ERCOT have significantly strengthened Inverter-Based Resource (IBR) ride-through performance requirements. Under the Nodal Operating Guide Revision Request (NOGRR) 245, effective October 1, 2024, all transmission-connected IBRs, Type 1 Wind Generation Resources (WGRs), and Type 2 WGRs must meet strict frequency ride-through and voltage ride-through standards or apply for extensions/exemptions under PUCT Substantive Rule 25.517.

If you are a Resource Entity or Interconnecting Entity that filed for an extension or submitted a notice of intent to request an exemption, the compliance clock is ticking. ERCOT identified that many April 2025 submissions were incomplete, granting all requestors until September 15, 2025 to submit complete and accurate ride-through capability data.

Keentel Engineering specializes in guiding energy developers, asset owners, and operators through the complex NOGRR245 compliance process—ensuring every IFRTCR, IVRTCR, and model submission meets ERCOT’s technical and procedural requirements. Learn more about our NERC compliance engineering services to see how we can help you meet this critical deadline.


Why NOGRR245 Matters

ERCOT’s reliability assessments have identified recurring ride-through failures in inverter-based resources (IBRs)—issues that could threaten Texas grid stability during frequency or voltage disturbances.

NOGRR245 compliance strengthens the Nodal Operating Guides to ensure every resource can ride through specified frequency ride-through and voltage ride-through excursions without tripping offline.

For full ERCOT compliance, each resource must provide:

  • Resource-specific ride-through capability data at the Point of Interconnection (no generic OEM statements)
  • Accurate post-modification models uploaded in RIOO
  • Verified technical limitations via OEM or engineering letters, or notarized attestations
  • Completed IFRTCR (frequency ride-through) and/or IVRTCR (voltage ride-through) forms
  • An official exemption request if unable to comply with the requirements

To understand the technical studies that support ride-through readiness, review our power system studies services.


What ERCOT Found Missing

ERCOT’s review of over 900 NOGRR245 compliance submittals revealed several recurring deficiencies:


  • Missing required ride-through technical data
  • Non-resource-specific, generic ride-through documentation
  • Data not reflecting Point of Interconnection (POI) performance
  • Delays due to pending OEM model updates


Without this information, ERCOT cannot properly assess extension or exemption requests, which could delay interconnection approval and put your project’s operational readiness at risk.


For More Information, visit: ERCOT NOGRR-245 Compliance


What You Must Submit for NOGRR245 Compliance

1. IFRTCR or IVRTCR Forms

  • IFRTCR (Initial Frequency Ride-Through Capability Report) – required for frequency compliance (per Nodal Operating Guide §2.6.2.1)
  • IVRTCR (Initial Voltage Ride-Through Capability Report) – required for voltage compliance (per Nodal Operating Guide §2.9.1.2)


Each form must include:

  • Resource and site details
  • Current capability tables
  • Known technical limitations
  • OEM/engineering letters or notarized attestations
  • Planned software, firmware, or hardware modifications
  • Post-modification capabilities
  • Implementation schedule
  • Limitations that cannot be represented in models

2. Accurate Post-Modification Model

  • Submit through ERCOT’s Resource Integration and Outage Operations (RIOO) system labeled “NOGRR245 Model Submission”
  • Must fully reflect all technical limitations

3. Exemption Requests (PUCT 25.517(c))

If you are seeking an exemption:

  • Complete ERCOT’s official exemption form (to be released in a future market notice)
  • Attach all IFRTCR and/or IVRTCR data with your exemption request
  • Provide supporting OEM/engineering letters or notarized attestations documenting technical limitations
  • Submit all materials by September 15, 2025 — late or incomplete requests will not be accepted

Keentel Engineering’s ERCOT NOGRR245 Compliance Support

Meeting ERCOT NOGRR245 technical and procedural requirements—especially under PUCT 25.517(c)—can be complex and time-sensitive. Keentel Engineering offers turnkey compliance services to help Resource Entities and Interconnecting Entities avoid costly delays or rejections, ensuring all IFRTCR and IVRTCR submissions are complete and error-free before the September 15, 2025 deadline.

Our NOGRR245 Compliance Services Include:

Data Gap Analysis – Review and identify missing or incomplete ride-through data in your current submissions

Capability Table Preparation – Create IFRTCR/IVRTCR ride-through capability tables per Nodal Operating Guide requirements

OEM & Engineering Coordination – Work directly with OEMs and engineering teams to obtain signed technical limitation verification letters

Notarized Attestations – Draft and prepare notarized statements when OEM letters are unavailable

Post-Modification Modeling – Develop and submit accurate post-modification models via the RIOO system

Exemption Request Preparation – Complete all exemption forms in compliance with PUCT 25.517(c)(1)-(9)

Internal Compliance Tracking – Use our proprietary NOGRR245 Excel checklist to track every deliverable

Quality Control Review – Conduct a full compliance audit before ERCOT submission to minimize rejection risk


Risks of Non-Compliance with ERCOT NOGRR245

Failing to meet the September 15, 2025 ERCOT NOGRR245 deadline can result in:

  • Denial of extension or exemption requests under PUCT 25.517
  • Immediate requirement to comply with all ERCOT ride-through performance standards
  • Potential operational restrictions imposed by ERCOT
  • Higher risk of penalties for reliability violations

Why Choose Keentel Engineering for ERCOT Compliance

  • Proven ERCOT Compliance Track Record – Successful delivery on multiple Inverter-Based Resource (IBR), Wind Generation Resource (WGR), and ride-through modeling projects
  • In-Depth Market Knowledge – Experienced with ERCOT market notices, PUCT regulations, and Nodal Operating Guide requirements
  • Integrated Technical & Regulatory Expertise – Engineering, modeling, and compliance support in one service package
  • Fast Turnaround Times – Structured processes to meet urgent ERCOT and NERC compliance deadlines

Action Steps Before September 15, 2025

Identify all resources under extension or exemption requests

Gather complete IFRTCR and IVRTCR capability tables

Obtain OEM/engineering verification letters or prepare notarized attestations

Model post-modification capabilities and ensure accuracy

Submit all required data to ERCOT via   NOGRR245@ercot.com and the RIOO system

File official exemption forms if applying under PUCT 25.517(c)


Contact Keentel Engineering Today

Don’t risk ERCOT rejecting your submission—our team can ensure every document, model, and table meets NOGRR245 standards before the deadline.


Frequently Asked Questions – ERCOT NOGRR245 Compliance

  • 1. What is NOGRR245?

    NOGRR245 is a Nodal Operating Guide Revision Request approved by the Public Utility Commission of Texas (PUCT) that strengthens ERCOT’s ride-through performance requirements for Inverter-Based Resources (IBRs), including frequency ride-through and voltage ride-through capabilities.

  • 2. Who must comply with NOGRR245?

    All transmission-connected IBRs, Type 1 Wind Generation Resources (WGRs), and Type 2 WGRs that have submitted an extension request or exemption request under PUCT 25.517(c) must provide complete, resource-specific ride-through capability data to ERCOT by September 15, 2025.

  • 3. What is the compliance deadline?

    The final deadline is September 15, 2025. Late or incomplete submissions will be rejected by ERCOT, which may result in denial of your extension or exemption request.

  • 4. What forms are required?

    You must submit either:

    • IFRTCR (Initial Frequency Ride-Through Capability Report) for frequency requirements (§2.6.2.1)
    • IVRTCR (Initial Voltage Ride-Through Capability Report) for voltage requirements (§2.9.1.2)


  • 5. Where do I send my completed forms?

    Send completed IFRTCR or IVRTCR forms to NOGRR245@ercot.com.

  • 6. How do I submit models to ERCOT?

    Post-modification models must be submitted via the RIOO system with the label “NOGRR245 Model Submission.”

  • 7. What data must be included in IFRTCR/IVRTCR?

    • Resource entity details (name, DUNS, site name, unit names)
    • Current ride-through capability tables per Nodal OG format
    • All known technical limitations
    • OEM or engineering verification letters / notarized attestations
    • Planned modifications and implementation schedule
    • Post-modification capability tables and models
  • 8. What if my OEM cannot provide a verification letter?

    You must submit a notarized attestation signed by your highest-ranking representative explaining:

    • Efforts taken to obtain the OEM letter
    • Why those efforts were unsuccessful
    • Technical limitations of the resource
  • 9. What deficiencies has ERCOT identified in past submissions?

    • Missing required technical data
    • Generic, non-resource-specific ride-through data
    • Data not reflecting Point of Interconnection performance
    • Delays due to pending OEM model updates without interim dataa
  • 10. Why are ride-through capability tables required?

    These tables document your resource’s ability to ride through frequency or voltage disturbances, ensuring compliance with ERCOT’s Nodal Operating Guides.

  • 11. What is PUCT Substantive Rule 25.517(c)?

    This rule outlines the process for requesting an exemption from ERCOT reliability requirements and specifies the data, models, and documentation that must be provided.

  • 12. Can I request an exemption after September 15, 2025?

    No. ERCOT will not accept any exemption requests after the deadline.

  • 13. What happens if I miss the deadline?

    ERCOT may:

    • Deny your extension or exemption request
    • Require immediate full compliance
    • Impose operational restrictions
  • 14. What’s the difference between IFRTCR and IVRTCR?

    • IFRTCR – Frequency ride-through capability report (§2.6.2.1)
    • IVRTCR – Voltage ride-through capability report (§2.9.1.2)
  • 15. How does Keentel Engineering assist with compliance?

    We provide turnkey ERCOT compliance services, including:

    • Gap analysis of IFRTCR/IVRTCR submissions
    • OEM/engineering letter coordination
    • Notarized attestation preparation
    • Ride-through table creation per Nodal OG
    • Post-modification model preparation and RIOO submissions
    • Full ERCOT & PUCT compliance packages


  • 16. Can I submit generic OEM data?

    No. ERCOT requires resource-specific performance data at the Point of Interconnection.

  • 17. What are the risks of providing incomplete models?

    Incomplete or inaccurate models may lead ERCOT to reject your submission, delaying approval and forcing immediate compliance without extensions or exemptions

  • 18. What must my model include?

    It must reflect post-modification performance and accurately represent all technical limitations.

  • 19. What if my resource is already compliant?

    You must submit a statement confirming that your current ERCOT-submitted model fully represents all technical limitations.

  • 20. How can I get started with Keentel Engineering?


Secure Your ERCOT Compliance Before September 15, 2025

The ERCOT NOGRR245 deadline is fast approaching. Missing it could mean losing your extension or exemption, facing operational restrictions, and being forced into immediate compliance.


📅 Deadline: September 15, 2025


A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Leave a Comment

Related Posts

FERC Order 2023 interconnection process diagram showing power generation
By SANDIP R PATEL May 1, 2026
FERC Order 2023: interconnection reforms, cluster studies & grid impact. Learn key changes fast.
Transmission line design infographic with BIM and power engineering solutions
By SANDIP R PATEL April 27, 2026
Explore advanced transmission line design services with BIM modeling, automated calculations, digital twins, and power engineering solutions by Keentel.
PJM Dynamic Model Guidelines 2026 infographic for utility-scale interconnection,
By SANDIP R PATEL April 27, 2026
Learn PJM dynamic model development, PSS®E model validation, and interconnection compliance requirements. Discover expert strategies for approval.
PJM NextGen application guide for utility-scale energy projects with solar, wind and battery storage
By SANDIP R PATEL April 25, 2026
Master the PJM NextGen application guide for utility-scale projects. Learn interconnection steps, technical data, and avoid delays. Get started today.
DC supply selection schemes improving reliability in HV, MV and LV protection systems
By SANDIP R PATEL April 24, 2026
Learn how DC supply selection schemes improve protection system reliability with dual DC architecture, redundancy, and anti-pumping solutions. Discover more.
Generator protection and control engineering solutions for power system stability
By SANDIP R PATEL April 24, 2026
Learn generator protection control engineering, ANSI 25 synchronization, relay schemes, and power system protection best practices. Discover expert solutions.
Solar capacity and availability testing for utility-scale power systems
By SANDIP R PATEL April 22, 2026
Utility-scale solar capacity testing, solar availability testing, and ASTM E2848 support for bankable performance. Learn more with Keentel.
PSCAD EMT vs RMS simulation infographic for power system stability, load flow, short circuit,
By SANDIP R PATEL April 22, 2026
Compare RMS vs EMT simulation using PSCAD. Learn when to use each for power system studies, inverter modeling, and grid stability. Discover more.
PSCAD power system modeling and simulation services for EMT studies.
By SANDIP R PATEL April 22, 2026
Explore PSCAD modeling, EMT simulation, and grid interconnection studies with expert insights. Learn advanced power system analysis techniques today.