Feature 1 — Permitting Reform Is Not Interconnection Reform
What happened
A bipartisan permitting bill introduced on September 30 by leaders of the Senate Environment and Public Works Committee and the Senate Energy and Natural Resources Committee is drawing new attention after the November midterm elections changed control of both chambers of Congress. The Bipartisan American Affordability and Jobs Act of 2026, known as BAAJA, would amend the core federal review statutes, including the National Environmental Policy Act, the Clean Water Act, the Endangered Species Act and the National Historic Preservation Act, to shorten review timelines and narrow the grounds for delay.
For the power sector, the most significant provisions are:
- Federal backstop siting authority for FERC over significant interstate transmission lines.
- Mandatory long-term transmission planning on a 20-year horizon, with support for grid-enhancing technologies.
- A large-load cost rule requiring high-energy data centers to pay the full cost of their power delivery and grid upgrades, intended to protect residential and commercial ratepayers.
- Litigation limits, including a reported 150-day window to challenge permits, restrictions on broad injunctions and vacatur, and protections against permit revocation once issued.
- Faster water-quality permitting for energy and infrastructure projects.
A solar and storage industry letter supporting the bill was signed by more than 300 companies. Market analysts describe permitting reform as one of the few energy-cost measures with a realistic bipartisan path, while noting that passage is not guaranteed: the congressional calendar is crowded, a new majority may prefer to write its own version next year, and any bill still needs a presidential signature. Environmental and Tribal organizations oppose parts of the bill, particularly its limits on judicial review and consultation.
Source: Energy-Storage.news, November 10, 2026.
Why it matters
The most important engineering point in this story was made by market analysts themselves: faster federal permits will not shorten the interconnection queue. Federal environmental review governs whether a project can be built on a site. The interconnection queue governs whether, when and at what cost the project can connect to the grid. That second process is run by RTOs, ISOs and transmission providers under FERC-approved tariffs, and since FERC Order No. 2023 it has moved to a cluster-study, first-ready, first-served model with significant financial readiness deposits and withdrawal penalties.
For most solar, wind and storage projects we support, the critical path is not NEPA. It is the cluster study, the network upgrades it identifies and the multi-year construction schedules of those upgrades. In recent cluster results we have reviewed, upgrade schedules of five to eight years are common, and allocated costs vary from zero to thousands of dollars per kilowatt depending on location and point-of-interconnection voltage.
Two BAAJA provisions do have direct engineering consequences if they become law:
- The 20-year planning mandate and FERC backstop siting would reinforce the long-term regional planning already required under FERC Order No. 1920, and could accelerate the 345 kV, 500 kV and 765 kV backbone projects that relieve the constraints driving today's network upgrade costs.
- The data center cost rule would make the accuracy of large-load interconnection studies a direct financial issue for the load customer. If the data center pays the full upgrade cost, overstated load forecasts or poorly modeled load behavior translate directly into overbuilt and overcharged facilities.
Keentel's take: what owners should do now
- Do not delay interconnection work waiting for permitting reform. The queue clock and cluster windows will not move because a bill passes.
- Screen points of interconnection with real base cases before each cluster window. Location and voltage class drive upgrade cost more than any other factor.
- Treat model quality as a commercial issue. Accurate PSS®E, PSLF and PSCAD models reduce deficiency notices and avoid unnecessary upgrades.
- Large-load customers should prepare for full cost responsibility now: document realistic ramp schedules, load characteristics and ride-through behavior so studies size upgrades correctly.
- Track state-level action. With federal outcomes uncertain, states such as Texas are expected to play a larger role in data center oversight.
How Keentel can help. Keentel Engineering supports generation, storage and large-load clients through the full interconnection process: POI screening, interconnection request preparation, model building and quality checks, independent replication of cluster studies, upgrade alternatives, surplus interconnection service, and interconnection agreement technical review. Call (813) 389-7871 to discuss your next cluster window.