A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Point-of-Interconnection (POI) Support Case Studies

April 29, 2025|Blog

Connecting large-scale generation and storage projects to regional transmission grids demands deep expertise, seamless ISO coordination, and bullet-proof engineering deliverables. Keentel Engineering has supported clients across PJM, ERCOT, WECC and NYISO with end-to-end Point-of-Interconnection (POI) services—from feasibility studies and dynamic modeling to protection scheme design and final energization. Our proven approach minimizes RFIs, accelerates commercial operation dates, and ensures first-time ISO acceptance, making us the go-to partner for renewable, storage, and hybrid projects seeking reliable, compliant transmission access.


Case Study 1: PJM 230 kV POI Interconnection for 250 MW Solar + Storage

Client: Confidential Renewable Developer

Scope: Full POI engineering for a 250 MW solar PV + BESS interconnection to a 230 kV PJM transmission line.

Services Provided:

  • PJM Feasibility, System Impact (SIS) & Facilities studies review
  • PSSE v35 dynamic and short-circuit model development per PJM modeling guide
  • Reactive capability verification at the POI
  • One-line diagrams, relay protection schemes & switching plans
  • Relay setting design for PRC-019, PRC-024 & PRC-025 compliance

Key Challenges:


  • Tight voltage regulation and transient stability criteria from PJM TOs
  • Aggressive coordination schedule with PJM and neighboring utilities

Results:


  • PJM accepted all dynamic & short-circuit models on first submission
  • Facilities Study finalized ahead of plan—mitigating COD risk
  • POI energized & commissioned successfully on first attempt
  • Keentel named preferred POI partner for future PJM projects

Case Study 2: ERCOT 345 kV POI Support for 300 MW Wind Expansion

Client: Confidential Wind Developer

Scope: POI interconnection of a 300 MW wind farm expansion into the ERCOT 345 kV network under the ERCOT Resource Interconnection Handbook (RIN).

Services Provided:

  • PSSE model creation & TSAT dynamic-model validation to ERCOT DWG requirements
  • Steady-state, dynamic stability & short-circuit data packages
  • RFI responses and coordination with ERCOT Planning & TSP
  • Protection package design per ERCOT Nodal Operating Guide Sec. 2
  • ICCP point-mapping for telemetry compliance

Key Challenges:


  • ERCOT’s fast-frequency-response (FFR) validation under evolving grid conditions
  • Integrating legacy and new turbine models in a unified hybrid-code base

Results:


  • Zero RFI follow-ups after initial package review—a rare achievement
  • Dynamic-model certification granted ahead of schedule
  • Client entered ERCOT market on time, with no penalties or delays

Case Study 3: WECC 230 kV POI for 150 MW PV + 75 MW/300 MWh BESS Hybrid

Client: Confidential Renewable Developer

Scope: POI interconnection engineering for a 225 MW hybrid solar + BESS project into WECC’s 230 kV transmission.

Services Provided:

  • Dynamic models (PSSE & PSCAD) per WECC Modeling & Validation Subcommittee (MVWG) standards
  • Harmonic analysis & Sub-Synchronous Resonance (SSR) risk assessment
  • Electromagnetic transient (EMT) studies on inverter switching impacts
  • SCADA/RTU signal list development & point-to-point testing support

Key Challenges:


  • WECC’s rigorous review of IBR models and fast-transient behavior
  • SSR studies necessity due to series-compensated transmission lines

Results:


  • EMT modeling report approved without major comments
  • Achieved full PRC-024, PRC-019 & PRC-027 compliance
  • Preemptive modeling saved client millions in potential cost overruns

Case Study 4: NYISO 138 kV POI Interconnection for 120 MW Wind Farm

Client: Confidential Wind Developer

Scope: End-to-end POI interconnection for a 120 MW wind farm tying into 138 kV NYISO system under the NYISO Generator Interconnection Process (GIP).

Services Provided:

  • PSSE steady-state & dynamic models per NYISO submission requirements
  • Technical appendices for FERC LGIA (Appendix C – Facilities Study)
  • Protection coordination plan aligned with NYISO & TO philosophies
  • Short-circuit contribution review & relay coordination studies

Key Challenges:


  • NYISO’s stringent voltage & frequency ride-through criteria
  • Complex stakeholder coordination among the developer, NYISO, and TO

Results:


  • First-round acceptance of full model submittal—no resubmissions required
  • Finalized Interconnection Agreement terms without material changes
  • Substation build-out and energization completed on original timeline
  • Client engaged Keentel for ongoing O&M engineering support

Discover more about our Generation Interconnection Support Services for ISO-wide POI expertise.

Ready to Accelerate Your POI Connection?

Contact Keentel Engineering today for end-to-end Point-of-Interconnection support—feasibility studies, dynamic modeling, protection design, and final energization.


A bald man with a beard is wearing a suit and a white shirt.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

A group of construction workers are standing next to each other with their arms crossed.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

A bald man with a beard is wearing a suit and a white shirt.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Leave a Comment

Related Posts

Best Practices in Energy-Efficient Data Center Design in 2025
By SANDIP R PATEL July 2, 2025
Learn how to reduce energy use, optimize cooling, and improve efficiency in data centers with the 2024 FEMP & NREL best practices guide.
Explore July 2025 grid reliability trends, IBR registration mandates, and NERC compliance updates. S
By SANDIP R PATEL July 1, 2025
Explore July 2025 grid reliability trends, IBR registration mandates, and NERC compliance updates. Stay ahead with Keentel’s future-ready engineering insights.
Enable seamless Modbus to IEC 61850 integration with the PLX82-MNET-61850 gateway. Achieve NERC comp
By SANDIP R PATEL June 26, 2025
Enable seamless Modbus to IEC 61850 integration with the PLX82-MNET-61850 gateway. Achieve NERC compliance with audit-ready substation communication.
SEL Synchrophasor Technology for Grid Monitoring | Keentel
By SANDIP R PATEL June 20, 2025
Discover how SEL synchrophasor systems, including the SEL-487E PMU, support real-time power grid monitoring and NERC PRC-002-2 compliance. Learn more with Keentel.
Explore NERC PRC-029-1 ride-through requirements for inverter-based resources (IBRs). Learn how it e
By SANDIP R PATEL June 20, 2025
Explore NERC PRC-029-1 ride-through requirements for inverter-based resources (IBRs). Learn how it enhances grid reliability with FERC Order No. 901 support.
Ensure NERC PRC-028 compliance with TESLA 4000 and Keentel Engineering’s expert integration, monitor
By SANDIP R PATEL June 19, 2025
Ensure NERC PRC-028 compliance with TESLA 4000 and Keentel Engineering’s expert integration, monitoring, and audit support services for utilities and GOs.
Ensure your relays don’t trip during stable power swings. Learn how PRC-026 compliance works, what r
By SANDIP R PATEL June 13, 2025
Ensure your relays don’t trip during stable power swings. Learn how PRC-026 compliance works, what relays it applies to, and how to automate your evaluations.
Build winning transmission proposals for PJM with Keentel. Integrated engineering + financial modeli
By SANDIP R PATEL June 9, 2025
Build winning transmission proposals for PJM with Keentel. Integrated engineering + financial modeling to support CapEx, ARR, NPV, and risk analysis.
Explore New York’s 2025 electric grid outlook — aging generation, large loads, renewables, and winte
By SANDIP R PATEL June 9, 2025
Explore NYISO’s ( New York’s) 2025 grid forecast: aging plants, AI-driven demand, winter risks, and interconnection delays plus engineering solutions from Keentel.