A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

PJM Dynamic Modeling & Interconnection Case Studies

Calendar icon. D

May 9, 2025 | Blog

Control room with people monitoring screens, a large display, and power lines in the background.

At Keentel Engineering, our proven dynamic modeling and interconnection expertise has supported utility-scale solar, battery energy storage systems (BESS), hybrid Solar + BESS facilities, and synchronous generator repowering projects across PJM’s footprint. Leveraging Siemens PSS®E and PSCAD simulations, user-defined model (UDM) development, and strict adherence to NERC and PJM criteria, we deliver audit-ready submissions that eliminate resubmittals, accelerate queue approvals, and ensure Bulk Electric System reliability. Explore how our tailored solutions—from PSS®E flat-start studies to hybrid inverter coordination—have achieved first‐pass acceptance and on-time energization for our clients.


Case Study 1

Dynamic Modeling for a 150 MW Solar PV Plant (Confidential Project A – New Jersey)

Challenge

A utility-scale solar developer submitted a 150 MW New Service Request to PJM with an aggressive timeline to secure queue placement. They faced a challenge in preparing dynamic models that complied with PJM’s strict inverter‐based resource (IBR) modeling criteria, particularly regarding momentary cessation and power factor control.

Keentel Engineering Solution

  • Developed compliant  .idv  and  .dyr  files using REGCA1, REECA1, and REPCA1 models tailored to the specific inverter type.
  • Conducted full flat start, VRT, and primary frequency response simulations using Siemens PSS®E v35.3.2.
  • Eliminated momentary cessation per Section 7.5 and validated Qmax/Qmin from PQ curves at 95 °F ambient temperature.

Outcome

PJM accepted the submission without any data deficiency flags. The developer avoided resubmission delays, and Keentel’s documentation package met all deliverables under Section 8 of the guidelines.


Case Study 2

As-Built Model Resubmission with UDM for a 50 MW BESS (Confidential Project B – Pennsylvania)

Challenge

A 50 MW standalone battery storage project had commissioned with a proprietary inverter model not covered by PJM’s approved library models. The developer faced rejection of their As-Built submission due to lack of a validated user-defined model (UDM).

Keentel Engineering Solution

  • Worked with inverter OEM to extract control logic, DLLs, and source code for the BESS inverter dynamic behavior.
  • Created and tested UDMs with REECC1 and REGCBU1 modules to represent grid-charging behavior per REECC guidelines.
  • Generated a complete UDM documentation packet including block diagrams, parameter explanations, and test logs.

Outcome

The As-Built submission passed PJM review. The FAT report, required under Section 8 for main power transformers, was integrated into the submission. Project achieved interconnection compliance within 30 days of re-submission.


Case Study 3

Multi-Inverter Model for Hybrid Solar + BESS Facility (Confidential Project C – Maryland)

Challenge

A hybrid facility with 120 MW solar and 40 MW BESS had different inverter types and control logics. PJM required a detailed model that accurately represented both technologies using multi-generator equivalents, and plant-level coordination via PLNTBU1.

Keentel Engineering Solution:

  • Developed separate REGC and REEC modules for each inverter type and integrated PLNTBU1 for coordinated control.
  • Modeled PQ curves with inverter-specific data for accurate Qmax/Qmin limits.
  • Included VTGTPAT and FRQTPAT relay models with protection curves compliant with NERC PRC-024-3.

Outcome

The hybrid project submission was approved in the first cycle with no supplemental data requests. The model was lauded for clearly representing shared POI behavior and frequency ride‐through settings, making it a PJM internal example for hybrid configurations.


Case Study 4

Repowering of Existing Synchronous Generator (Confidential Project D – West Virginia)

Challenge

An older 100 MW coal-fired synchronous unit was being upgraded with new excitation and governor systems. The repowered unit required an updated dynamic model that matched current operating characteristics and included necessary power factor and saturation curve validation.

Keentel Engineering Solution:

  • Replaced legacy GENCLS and SEXS models with GENSAL and EXST1 for detailed generator behavior.
  • Integrated PSS (Power System Stabilizer) and AVR limiter models to enhance transient stability representation.
  • Completed MFO and power factor assessments per Section 7.1 and 7.2, including summer and winter operating conditions.

Outcome

The updated model allowed the facility to be requalified under its interconnection agreement. PJM approved the repowering study without requiring a PSCAD model, accelerating re-energization approvals.


Want to learn more? Check out our Power System Studies and POI Interconnection Engineering Support services for details on our dynamic and interconnection capabilities.



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.

Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Leave a Comment

Related Posts

NERC and ERCOT compliance guide for natural gas power plants showing power system diagram and grid c
By SANDIP R PATEL • September 30, 2026
Learn NERC and ERCOT compliance requirements for natural gas power plants, including GO/GOP obligations, O&P standards, GADS reporting, and audits.
Data center and high-voltage transmission grid illustrating a large-load interconnection application
By SANDIP R PATEL • September 26, 2026
Learn how to prepare a MISO large-load interconnection package, including PSS®E models, BESS smoothing, harmonic data and transmission-owner requirements.
800 VDC AI data center storage architecture with battery systems, DC power distribution, and electri
By SANDIP R PATEL • September 26, 2026
Learn where storage belongs in an 800 VDC AI data center, including capacitors, flywheels, BESS, fault current, protection, grounding, and EMT design.
SPP HILL and HILLGA framework for large-load developers
By SANDIP R PATEL • September 26, 2026
Learn how SPP’s HILL and HILLGA framework works for large-load projects, including studies, BTM generation, modeling, EMT requirements, and firm service.
IBR time synchronization and IEEE 2800 compliance for disturbance monitoring systems
By SANDIP R PATEL • September 25, 2026
Learn how IBR time synchronization, IEEE 2800, IRIG-B verification, and PTP solutions help meet disturbance monitoring compliance requirements.
Power engineering technical training and professional development for electrical engineers
By SANDIP R PATEL • September 24, 2026
Learn why continuing technical training matters in power engineering, including standards, software skills, PDH requirements, and career growth.
ERCOT new generator commissioning checklist parts 1, 2 and 3
By SANDIP R PATEL • September 22, 2026
2026 ERCOT commissioning guide covering the Commissioning Plan, Checklist Parts 1–3, BESS requirements, TSP/QSE coordination, field testing and COD.
PRC-030-1 NERC IBR compliance guide showing 20 MW event detection threshold and R1 monitoring timeli
By SANDIP R PATEL • September 22, 2026
Learn PRC-030-1 R1 event detection requirements for inverter-based resources, SEL platforms, disturbance monitoring, and audit-ready compliance.
PSS®E and PSCAD™ plant model update workflow showing modified plant testing, benchmark validation, a
By SANDIP R PATEL • September 22, 2026
Learn how PSS®E and PSCAD™ model updates support plant augmentations, repowering, equipment changes, testing, benchmarking, and grid compliance.