A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

What Do PRC-002-5 and PRC-028-1 Mean for Generator Owners & Transmission Owners?

Calendar icon. D

May 9, 2025 | Blog

Power lines and transmission towers silhouetted against a cloudy sky with sun flare.

As the power grid evolves with a growing reliance on inverter-based resources (IBRs), so too must the standards that safeguard reliability. At Keentel Engineering, we’re at the forefront of supporting Generator Owners (GOs) and Transmission Owners (TOs) in navigating compliance with the latest NERC reliability standards—PRC-002-5 and PRC-028-1.


These standards redefine how disturbance monitoring and reporting must be implemented for both conventional and inverter-based power systems. This article breaks down what these changes mean, implementation timelines, and how Keentel can help utilities and developers achieve compliance with confidence.


Overview of the Standards

PRC-002-5 – Disturbance Monitoring and Reporting Requirements

This version updates PRC-002-4 and clarifies that it excludes Inverter-Based Resources (IBRs).
Applies to BES Generator Owners and Transmission Owners.
Focuses on traditional synchronous resource disturbance monitoring.

PRC-028-1 – Disturbance Monitoring and Reporting for Inverter-Based Resources

A new standard tailored to BES and non-BES IBRs.
Applies to GOs and TOs with facilities involving IBRs at or above certain thresholds.
Introduces graduated implementation timelines based on commercial operation dates.


Why the Change?

The previous version of PRC-002 was not fully suited for inverter-based technologies. With PRC-028-1, NERC ensures that IBRs—such as solar, wind, and battery storage systems—are properly monitored for system events. This change supports:

  • Better situational awareness during disturbances.
  • Improved system event diagnostics.
  • Harmonization of compliance across legacy and new generation resources.

Key Implementation Timelines

PRC-002-5

  • Effective Date: First day of the first calendar quarter after regulatory approval or NERC Board adoption.
  • No major procurement changes required—focuses on exclusion of IBRs.

PRC-028-1

Implementation is phased and depends on asset type and operational status:

  • For BES IBRs (Bulk Electric System):
  • In operation before effective date: 50% compliance with R1–R7 in 3 years; 100% compliance by Jan 1, 2030.
  • New BES IBRs post-effective date: Compliance required within 15 months or by the commercial operation date (COD), whichever is later.

  • For Non-BES IBRs:
  • Must meet 20 MVA aggregate and be connected at ≥60 kV.
  • In operation before May 2026: 100% compliance by Jan 1, 2030.
  • COD after May 2026: 15 months post-COD or effective date.

  • Requirement R8: Must be met within 9 months (BES) or by April 1, 2027 (non-BES).

What Does This Mean for You?

Many GOs and TOs will need to:

  • Install or upgrade disturbance monitoring equipment (DME).
  • Coordinate outages to complete installations.
  • Prepare for long lead times due to vendor and engineering resource constraints.
  • Stay proactive in planning for the upcoming IBR registration deadline (May 2026).

How Keentel Engineering Can Help

Keentel Engineering offers turnkey solutions to help you comply with PRC-002-5 and PRC-028-1:
✅ Assessment of Existing Infrastructure
✅ Disturbance Monitoring Equipment Specification and Procurement
✅ Engineering Design for Fault, SOE, and Dynamic Recorders
✅ Outage Planning and Project Management
✅ Documentation and Audit-Ready Compliance Packages

Whether you operate legacy gas units, BESS, wind farms, or solar PV systems—our team ensures your monitoring strategy is compliant and future-proof.

Learn more on our Power System Studies page.


FAQs – PRC-002-5 and PRC-028-1 Compliance

  • What’s the difference between PRC-002-5 and PRC-028-1?

    PRC-002-5 applies to synchronous generation; PRC-028-1 is specific to IBRs like solar, wind, and battery systems.

  • Do all IBRs need to comply with PRC-028-1?

    Only BES and qualifying non-BES IBRs above 20 MVA connected at ≥60 kV.

  • What is considered a BES IBR?

    One that meets the NERC definition of Bulk Electric System.

  • Are battery energy storage systems included?

    Yes, if they meet the BES or non-BES capacity and voltage thresholds.

  • What disturbance monitoring equipment is required?

    Typically includes sequence of events recorders (SOER), fault recorders (DFR), and dynamic disturbance recorders (DDR).

  • Do I need to upgrade existing equipment?

    Possibly, if current devices don’t meet the new standard’s requirements.

  • How do I know if I’m a registered GO or TO?

    Your NERC registration status defines your obligations—check with your Regional Entity.

  • What if I can’t meet the deadline?

    You can request a compliance extension with proper justification.

  • Is there a penalty for missing the compliance date?

    Yes, non-compliance may trigger enforcement actions by NERC or your Regional Entity.

  • What is R8 in PRC-028-1?

    It addresses retention and retrieval of DME data; it must be implemented faster than other requirements.

  • What if I have only one BES IBR?

    You still must comply with R1–R7 within 3 years of the standard’s effective date.

  • Can I use third-party engineering firms for compliance support?

    Absolutely—and Keentel Engineering is a trusted NERC compliance partner.

  • How are outages handled for DME upgrades?

    Planned and scheduled as part of implementation; this is factored into the standard’s timeline.

  • What documents do I need to show compliance?

    Engineering drawings, commissioning records, settings, and test data—all of which we help prepare.

  • Who enforces these standards?

    NERC and its delegated Regional Entities (like SERC, WECC, etc.).

  • 📞 Need help preparing your assets for PRC-002-5 and PRC-028-1?

    Describe the item or answer the question so that site visitors who are interested get more information. You can emphasize this text with bullets, italics or bold, and add links.

📞 Need help preparing your assets for PRC-002-5 and PRC-028-1?

Contact us via our contact page or call 813-389-9781 for a free consultation and compliance readiness assessment.



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Leave a Comment

Related Posts

By SANDIP R PATEL August 22, 2026
Learn how NERC's new data center rules affect registration, modeling, protection, compliance, and what computational load operators should do now.
Solar and battery storage shared bus resonance diagram
By SANDIP R PATEL August 20, 2026
Learn how shared 480 V solar and BESS buses create resonance, harmonic, grounding, and transformer issues—and how proper engineering prevents failures.
12.47 kV pole-mounted distribution transformer assembly designed for U.S. IEEE and NESC utility stan
By SANDIP R PATEL August 20, 2026
Learn U.S. pole-mounted transformer design requirements, including IEEE, ANSI, and NESC standards, voltage classes, grounding, protection, and DER considerations.
Neutral grounding resistor sizing guide for HRG and LRG power system grounding applications
By SANDIP R PATEL August 20, 2026
Learn how to size neutral grounding resistors using IEEE and NEC practices, including HRG/LRG selection, fault current calculations, duty ratings, and examples.
PRC-023-6 BESS relay loadability compliance guide
By SANDIP R PATEL August 19, 2026
Understand PRC-023-6 for utility-scale BESS: applicability, the 39-month rule, relay loadability, setting criteria, Category 2 IBRs, and audit evidence.
PRC-029-1 voltage ride-through envelope for inverter-based resources.
By SANDIP R PATEL August 18, 2026
Learn PRC-029-1 compliance requirements for inverter-based resources, including voltage and frequency ride-through, EMT studies, protection settings, and testing.
Solar plant electrical testing and commissioning for utility-scale PV systems
By SANDIP R PATEL August 17, 2026
A technical guide to solar plant electrical testing, commissioning, I-V curves, thermography, insulation testing, cable tests and performance acceptance.
Alt Text: Gas-insulated substation engineering guide covering GIS safety, reliability, VFTO, partial
By SANDIP R PATEL August 16, 2026
Explore GIS substation engineering, including design, SF6 safety, VFTO, grounding, commissioning, testing, GIS vs AIS, and IEEE/IEC standards.
Cable testing before energization engineering guide
By SANDIP R PATEL August 16, 2026
Learn the correct cable testing sequence before energization, including VLF, AC/DC withstand, sheath testing, partial discharge, tan delta, and standards.