A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.
Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime
The three operating regions you have to design to
| Device | Output vs voltage | Response | Best suited to | Main limitations |
|---|---|---|---|---|
| Mechanically switched capacitor or reactor | Proportional to voltage squared | Seconds; discrete steps; limited switching operations per day | Steady-state reactive supply, voltage profile, loss reduction | No dynamic capability; step voltage change on switching; capability collapses when most needed |
| Static var compensator | Capacitive branches proportional to voltage squared | A few cycles; continuously controllable | Continuous control where cost matters and deep voltage support is not the driver | Square-law capability loss; harmonic filters are part of the plant and interact with the network |
| STATCOM | Approximately proportional to voltage — constant current capability | One to two cycles closed loop; converter response faster still | Voltage stability margin, weak interconnections, fast disturbance recovery, flicker and unbalance compensation | Higher capital cost; converter losses; adds a converter and its control dynamics to the network |
| Synchronous condenser | Governed by machine capability and excitation | Excitation response in the hundreds of milliseconds; inherent inertial response instantaneous | System strength and inertia, short-circuit contribution, black start support | Rotating plant with maintenance and losses; slower controlled response than a converter |
| STATCOM with energy storage | Reactive as a STATCOM, plus real power within the storage rating | As STATCOM for reactive; real power limited by storage | Where a real power deficiency is part of the problem | Cost and complexity of the storage; different failure and maintenance profile |
| Service area | What we do for SST campuses | Typical deliverables |
|---|---|---|
| Grid interconnection | Site screening, large-load applications, independent studies, utility and RTO coordination in ERCOT, NYISO, PJM and other markets | Screening reports, application data packages, load flow, contingency and stability studies, study review memos |
| EMT modeling | Model requirements, vendor model review, campus aggregation, ride-through, weak-grid, control interaction and load-oscillation studies | EMT model specifications, model acceptance reports, PSCAD study reports, SCR screening |
| MV/MVDC system studies | AC and DC short-circuit, DC protection philosophy, AC protection, arc flash, grounding, insulation coordination | Study reports, protection philosophy documents, settings files, arc flash labels, interface control documents |
| Power quality | Emission requirements, frequency scans, IEEE 519-2022 compliance, filter sizing, flicker assessment | Harmonic study reports, filter specifications, monitoring plans |
| Substation and transmission design | HV/EHV substations, MV collectors, transmission lines, utility interface protection | Physical and electrical drawing packages, specifications, bills of material, protection and control design |
| NERC compliance | Registration and applicability, ride-through requirements, model validation, monitoring, compliance programs | Applicability assessments, compliance programs, evidence packages, model validation reports |
| Owner's engineer and QA/QC | SST, storage and substation specifications, design reviews, FAT and SAT plans and witnessing, multi-unit QA | Specifications, review comments, test plans, witness reports, due diligence reports |
| Onsite generation and BESS | Role definition and sizing, DC bus control architecture, fire and code compliance coordination, performance testing | Sizing studies, control architecture documents, specifications, test procedures |
Storage and generation
| Term | Meaning |
|---|---|
| AFE | Active front end. The actively switched AC/DC stage of an SST that connects to the MV grid and sets its grid behavior. |
| Aggregated model | A model in which many converters are represented by a smaller number of equivalent converters to make campus-scale simulation practical. |
| Arc flash | The release of energy from an electric arc fault, assessed as incident energy at a working distance to set PPE and safe work practices. |
| BESS | Battery energy storage system. |
| Blocking | Turning off all converter switches so the converter stops feeding current, used to limit DC faults. |
| Composite load model | A positive-sequence load model that combines several load types, such as motors, electronics and static loads. |
| DAB | Dual active bridge. An isolated DC/DC converter topology with active bridges on both sides of a high-frequency transformer. |
| DC-link | The internal DC capacitor bank between converter stages. |
| EMT | Electromagnetic transient simulation. Time-domain simulation with microsecond time steps, used to study fast converter and network behavior. |
| FAT | Factory acceptance test. |
| Grid-forming | A converter control mode that sets its own voltage and frequency reference rather than following the grid's, providing support to weak grids. |
| HIL | Hardware-in-the-loop testing, in which a real controller is tested against a real-time simulation. |
| IBR | Inverter-based resource. Generation or storage connected to the grid through power electronics. |
| Insulation coordination | Matching the insulation strength of equipment to the voltage stresses the system produces, with surge protection where needed. |
| ISC/IL | The ratio of available short-circuit current to maximum demand load current at the point of common coupling, used to set IEEE 519 limits. |
| ISOP | Input-series, output-parallel. A modular converter arrangement that shares a high input voltage across cells in series and combines their outputs in parallel. |
| Large load | A load large enough to affect transmission system reliability. Definitions vary, for example 75 MW and above under Texas SB 6, or loads above 20 MW in the federal rulemaking proposal. |
| LVDC | Low-voltage DC, such as 800 VDC or ±400 VDC rack distribution. |
| MFT | Medium-frequency transformer. The compact isolation transformer inside an SST, operating at kilohertz frequencies. |
| MMC | Modular multilevel converter. A converter built from many submodules with their own capacitors, producing a stepped multilevel waveform. |
| MVDC | Medium-voltage DC distribution, roughly 1 kV to 35 kV DC in common usage. |
| OE | Owner's engineer. An independent engineer representing the owner's technical interests. |
| PCC / POI | Point of common coupling / point of interconnection, where the campus connects to the utility system and where compliance is usually assessed. |
| PLL | Phase-locked loop. The control element that tracks grid voltage phase and frequency. |
| Positive-sequence model | A fundamental-frequency, balanced dynamic model used in PSS®E, PSLF and similar tools. |
| Ride-through | The ability to stay connected and keep operating during and after a grid disturbance within defined limits. |
| SAT | Site acceptance test. |
| SCR | Short-circuit ratio. Available short-circuit power divided by converter rating, a measure of grid strength. |
| SiC | Silicon carbide, a wide-bandgap semiconductor material that allows higher voltage, higher frequency switching. |
| SST | Solid-state transformer. A power electronic converter with a high-frequency isolation stage that replaces a 60 Hz transformer and rectifier chain. |
| Supraharmonics | Emissions in the 2 kHz to 150 kHz range, above the range covered by most harmonic limits. |
| TDD | Total demand distortion. Harmonic current distortion relative to maximum demand current, used in IEEE 519. |
| WSCR | Weighted short-circuit ratio. An SCR screen that accounts for several inverter-based plants sharing a network area. |
Links were current at publication (November 2026). Large-load rules, NERC actions and standards editions are changing quickly, so confirm current versions before relying on them.
Large-load reliability and NERC
- NERC Publishes Incident Review and Guidance on Voltage-Sensitive Large Load Integration, NERC
- Reliability Insights: Large Computational Load Risks Due to Voltage Sensitivity, NERC, September 2026
- NERC Seeks to Address Reliability Impacts from Large Load Integration, NERC presentation to FERC, April 2025
- NERC issues Level 3 Alert to address immediate risks data center loads pose to the grid, Renewable Energy World, May 2026
- NERC Voltage-Sensitive Loads, Keentel Engineering
Federal and state large-load rules
- FERC Docket RM26-4, Interconnection of Large Loads, FERC
- FERC Establishes Proceeding to Consider DOE Directive on Large Load Transmission Interconnection Rulemaking, McGuireWoods, October 2025
- Texas Senate Bill 6 Ushers in Major Overhaul of Large Load Interconnection and Grid Access Rules, Bracewell, July 2025
- Public Utility Commission of Texas Issues Proposed Rules for Large Load Interconnections, Foley & Lardner, March 2026
Solid-state transformers and DC data center power
- Solid State Transformer project, Open Compute Project
- Novel Solid-State Transformer Supports 800-V DC Power in AI Data Centers, Electronic Design
- How SSTs are Reshaping Data Center Infrastructure, Microchip Technology
Standards referenced (consult the publisher for the current edition)
Step 5 — options. Replacing or retrofitting the drives with active-front-end or 18-pulse units at about 5% THDi gives a TDD of about 1.5%. An active harmonic filter sized for the 5th and 7th could achieve a similar result at the facility level. A passive 5th-harmonic tuned filter would also work but must be checked for resonance with the utility system and with any future capacitors.
What this means for you.
The same drives can be compliant on a strong system and non-compliant on a weak one. Ask your utility for the maximum short-circuit current at the PCC early in design. If the ratio is below 50, plan for low-harmonic drives or filtering from the start; it is much cheaper than retrofitting.
9. Inverter-based resources: solar, storage and wind
Solar PV, battery energy storage and full-converter wind turbines use pulse-width-modulated inverters with output filters. They are generally low-distortion sources. IEEE Std 1547-2018 (distribution-connected resources) and IEEE Std 2800-2022 (transmission-connected resources) limit their current distortion — total rated-current distortion (TRD) of 5% with individual limits by order, measured against rated current rather than present output. In practice, quality inverters measure 1–3% at rated output.
Three cautions apply:
- Percentages rise at low output. At 10% of rated output a 2% distortion (of rated current) looks like 20% THD. Limits referenced to rated current, like TDD, avoid this trap.
- Inverters change the system's impedance. Plant collector cables, inverter output filters and capacitor banks add capacitance. They can create resonances near the 5th to 13th harmonics on the 34.5 kV collector or at a 138 kV, 230 kV or 345 kV point of interconnection, amplifying background distortion that the plant did not create.
- Background distortion matters. Inverters can absorb or amplify existing voltage distortion depending on their control design. Utilities increasingly require harmonic impedance studies for new plants, sometimes using electromagnetic transient (EMT) simulation.
Keentel's articles on harmonic resonance and on
weak-grid inverter stability cover these interactions in depth.
10. Data centers and other electronic facilities
Data centers are a special case because almost all their load is electronic. Points to check:
- UPS rectifiers. Double-conversion UPS units with IGBT rectifiers typically draw less than 5% THDi at rated load, rising at low load. Older six-pulse or 12-pulse thyristor UPS rectifiers may need input filters.
- Server and network power supplies. Modern units with active power factor correction have low 3rd harmonic. Legacy equipment does not. Measure a representative panel rather than assuming.
- 208Y/120 V and 415Y/240 V distribution. Check neutral current and transformer K-factor as in Sections 4 and 7.
- Generator operation. Test UPS and generator compatibility at the actual load level. Generator THDv can be three to four times the utility THDv for the same load.
- Cooling plant. Chiller, pump, fan and cooling distribution unit drives often contribute more low-order harmonics than the IT load. Specify low-harmonic drives where the facility is large relative to the utility source.
- Large-load interconnection. Utilities and grid operators now treat large data centers as high-impact loads. Harmonic studies and power quality monitoring are increasingly part of interconnection requirements, alongside ride-through and dynamic studies.
11. How a harmonic study is done
A harmonic study answers four questions: How much harmonic current will the facility inject? What voltage distortion will it cause? Will any resonance amplify it? What is the cheapest reliable fix? Keentel's typical workflow:
- Gather data. Single-line diagram; utility short-circuit data (maximum and minimum) at the PCC; utility background distortion if known; transformer impedances; cable lengths; capacitor banks and filters; drive, UPS and inverter data sheets with harmonic spectra.
- Measure existing conditions. For existing facilities, install class-compliant power quality meters at the PCC and key buses for at least one week, capturing 10-minute and 3-second data up to the 50th harmonic.
- Build the model. Represent sources as harmonic current injections and the network as frequency-dependent impedances, including transformer phase shifts that can cancel 5th and 7th harmonics between delta-delta and delta-wye units.
- Run a frequency scan. Plot driving-point impedance versus frequency at each important bus to find resonances, for all credible system configurations (tie breakers open/closed, capacitor steps in/out, generator versus utility).
- Run harmonic load flow. Calculate harmonic currents and voltages and compare them with IEEE 519 at the PCC and with equipment limits (IEEE 18 for capacitors, C57.110 for transformers) inside the facility.
- Design mitigation. Compare options for performance, cost, losses, footprint and future flexibility.
- Verify. Measure again after installation and document compliance with the statistical criteria.
12. Fixing harmonics: options compared

Joint Load and Generation Interconnection Studies: PJM Fast Energization & MISO LARS
November 24, 2026 | Blog
Part A — Joint Large-Load and Generation Studies at a Glance
For most of the last two decades, transmission planners in the United States studied interconnection requests one at a time. A generator entered the queue, its system impact study tested the grid with that project added to everything ahead of it, and the network upgrades it triggered were assigned to it. The approach was simple to administer and simple to explain. It was also slow, and it hid the interactions between projects that sat electrically close to one another.
Cluster studies changed that. When FERC Order No. 2023 moved every transmission provider to a first-ready, first-served cluster process, it formalized a lesson that regional transmission organizations (RTOs) had already learned: projects that are electrically close interact, and studying them together reveals power flows and overlapping violations that individual studies miss.
The same lesson now applies to something new. Large loads — hyperscale and AI data centers, hydrogen electrolyzers, semiconductor fabs, crypto-mining campuses and electrified industrial plants — are arriving in the same areas as new generation. Developers increasingly pair a 500 MW or 1 GW load with gas turbines, solar, wind or battery energy storage (BESS) in the same zone or behind the same point of interconnection (POI). It is tempting to net the two: 900 MW of load plus 900 MW of new generation equals zero, so the grid sees nothing new.
The grid does not work that way. Whether a load and a generator relieve a constraint or create one depends on where each is connected, how the rest of the system is dispatched, the load level, the network topology, the timing of each project and what happens when an element is lost. A co-located generator that trips while its load stays on can leave the grid carrying the full load through a path that was never studied. A "netted" pairing in the same zone can relieve one flowgate and overload another.
That is why grid operators are now moving to study large loads and generation together. In 2026, PJM filed a Fast Energization proposal at FERC that would study generation and large-load transmission service in one joint process and cut the timeline from roughly two years to roughly one. MISO filed its Large Load Addition Resource Study (LARS), which would study loads above 200 MW together with new generation in the same local resource zone within 120 days. Both responded to a broader push from FERC, which in June 2026 directed every RTO and ISO to justify or reform its large-load integration rules.
Keentel Engineering's view is simple: the real value of a joint study comes from modeling the load and the generation against the same future grid — the same base case, the same queue, the same dispatch assumptions, the same contingency list and the same dynamic models. This guide explains how to do that, why it matters, and what developers, utilities and large-load customers should do now.
Keentel's position. Keentel Engineering is an independent power engineering firm. We perform interconnection, large-load and transmission planning studies — steady-state, short-circuit, stability and EMT — design substations and transmission facilities from 4 kV to 765 kV, and support NERC compliance for utilities, independent power producers, developers and large-load customers. We do not sell generation, storage or data center capacity; our only interest is an accurate answer about what the grid needs.
Who this guide is for
- Data center and large-load developers planning campuses of 100 MW to several gigawatts, with or without on-site or nearby generation.
- Independent power producers and generation developers pairing gas, solar, wind or storage with large-load customers.
- Transmission owners, planners and utilities responding to large-load service requests and new RTO processes.
- Utility and state regulatory staff evaluating cost allocation, reliability and affordability.
- Owner's engineers, lenders and investors who need to understand interconnection risk, schedule and cost.
Key facts at a glance
The large-load landscape is changing month by month. The table below summarizes the developments Keentel tracks most closely. Dates and details are taken from public filings and reporting as of November 2026; always confirm against the current tariff, filing or order.
| Item | What has been reported or filed | Source and date |
|---|---|---|
| FERC large-load show cause orders | Six Section 206 show cause orders directing every RTO/ISO to justify or reform its large-load integration rules; responses due November 16, 2026 | FERC, June 18, 2026 |
| PJM Fast Energization | Joint study of generation and large-load transmission service, targeting roughly one year instead of roughly two | PJM filing at FERC, November 16, 2026 (Docket ER27-531) |
| MISO LARS | Study of loads above 200 MW paired with new generation in the same local resource zone, targeted at 120 days | MISO filing at FERC, reported October 2026 |
| MISO ERAS | Expedited Resource Addition Study for generation tied to urgent resource adequacy needs | Accepted by FERC, July 2025 |
| SPP HILL / HILLGA | High Impact Large Load process and associated generation pathway | Accepted by FERC, January 2026 |
| FERC co-location order | PJM directed to create new transmission service options for co-located load | FERC order, December 2025 |
| DOE directive | DOE invoked Federal Power Act Section 403 to direct FERC to consider large-load interconnection rules | DOE letter, October 2025 |
| PJM Board decision | Critical Issue Fast Path decisional letter on large-load additions | PJM Board, January 16, 2026 |
| ERCOT | Texas Senate Bill 6 (2025); "Batch Zero" batch study process for large loads; large electronic load ride-through rules (NOGRR 282) | Texas Legislature 2025; ERCOT 2026 |
| NERC | Incident review of a roughly 1,500 MW data center load loss in Virginia (July 2024); Level 2 alert on large loads (2025) | NERC, 2025 |
| Large-load transfer event | Several gigawatts of Northern Virginia data center load transferred off the grid within seconds on July 22, 2026 (reported at about 3–4 GW) | PJM and Dominion reviews, 2026 |
The core ideas in one table
| Idea | What it means in practice |
|---|---|
| Projects that are electrically close interact | Cluster studies capture combined flows and shared upgrades that serial studies miss; the same is true of loads and generators. |
| Megawatts cannot simply be netted | A load and a generator only cancel on a flowgate if they have the same distribution factor on it — which in practice means the same bus and both in service. |
| Dispatch and load level change the answer | A pairing that relieves a constraint at summer peak can create one at light load with high renewable output. |
| The generator can trip while the load stays | A joint study must test the load with its co-located generation out of service, not only with it running. |
| Large loads are dynamic devices | Data centers are power-electronic loads that can drop off and return in seconds; ride-through and recovery must be modeled. |
| Deliverability is a separate question from flows | A generator that serves a co-located load may still need to be deliverable to the wider system to count for capacity. |
| Flexibility can buy time | Curtailable or non-firm service can let a load connect before network upgrades are finished, if the curtailment hours are studied honestly. |
| One future grid | Load and generation must be studied against the same base case, queue, dispatch and models, or the results will not agree. |
Fact check: common simplifications
| Common statement | Keentel's engineering check |
|---|---|
| "If the new generation equals the new load, the grid sees nothing." | Only true at the same bus with the generator running. In Keentel's worked example, 900 MW of load and 900 MW of generation at two buses in the same zone still overload two 345 kV lines after single contingencies. |
| "Co-located generation removes the need for network upgrades." | Not if the load stays on when the generator trips or is on maintenance. The network must carry the load for that condition, or the load must be curtailed automatically. |
| "Joint studies are just faster." | Speed is a benefit, but the main value is a more accurate answer: shared upgrades are identified once, and mutual relief is credited only where it is real. |
| "A data center is a constant load." | AI training workloads can swing tens to hundreds of megawatts in seconds, and data centers can transfer to backup power during voltage dips. Both affect planning. |
| "Deliverability studies only matter for generators." | When a load relies on nearby generation to justify its service, the generator's deliverability, accreditation and outage behavior become part of the load's reliability case. |
| "Cluster studies and large-load studies use the same models." | Often not today. Generator queues and load service requests are frequently studied by different teams, in different cases, on different schedules. Joint processes exist to fix that. |
| "Fast-track processes lower the engineering bar." | The schedule is compressed, not the physics. Shorter studies need better data at the start, because there is less time to correct it. |
Eight findings for decision makers
1. Study the pair, not the net. Load and generation in the same area must be modeled at their actual buses, with every realistic dispatch and outage combination.
2. Test the generator-out case. The most common gap in co-location proposals is the condition where the generator trips and the load stays.
3. Light load is as important as peak. New generation creates its worst export flows at light load and high renewable output, exactly when the paired load may be low.
4. Model the load as a dynamic device. Data center ride-through, transfer to backup and recovery behavior can be larger reliability risks than steady-state flows.
5. Short-circuit and system strength change in both directions. Synchronous generation raises fault duty; inverter-based resources and power-electronic loads lower effective system strength.
6. Flexibility is valuable only if it is quantified. Curtailable service should come with an hourly analysis of when and how much curtailment will be needed.
7. Good data is the critical path. Joint processes with 120-day or one-year targets leave little time to correct poor load ramps, models or one-lines.
8. The same future grid is the standard. Keentel builds one study case that holds both queues, both sets of models and one contingency list.
Key terms
- Large load: a load above a defined threshold (for example 75 MW in ERCOT's process, 200 MW for MISO LARS, or 20 MW in the DOE directive) that requires a transmission-level study.
- Co-located load: a load connected at or behind the same POI as a generator, sometimes with no grid service, sometimes with partial or full grid service.
- Distribution factor (DFAX, PTDF): the fraction of a power transfer that flows on a given transmission element.
- Line outage distribution factor (LODF): the fraction of an outaged line's flow that shifts onto another line.
- Flowgate: a monitored element, or element with a contingency, used to measure transfer limits.
- Deliverability: the ability of a generator's output to reach load across the system under stressed conditions, required for capacity accreditation in most RTOs.
- Network integration transmission service (NITS): firm transmission service used to serve network load.
- Non-firm or flexible service: service that may be curtailed under defined conditions, often used as interim service before upgrades are complete.
- ELCC: effective load carrying capability, the capacity accreditation metric now used by most RTOs.
- Ride-through: the ability of a resource or load to stay connected through a voltage or frequency disturbance.
- EMT study: electromagnetic transient simulation, used to model power electronics in detail.
Part B — The Engineering Guide to Studying Large Loads and Generation Together
1. From serial studies to cluster studies
Before the reforms of the last few years, most interconnection queues in the United States worked serially. Each request had a queue position. Its feasibility, system impact and facilities studies were run against a base case that included every higher-queued project, and it was assigned the cost of upgrades its own injection triggered. If a higher-queued project withdrew, lower-queued projects were often restudied, sometimes repeatedly.
That design had three well-known problems:
- Restudy cascades. A single withdrawal could change the upgrades needed by every later project.
- Hidden interactions. Two projects 20 miles apart might each pass when studied alone, while together they overloaded a shared 345 kV line. Under a serial process, the later project carried the whole upgrade, even when the earlier project contributed most of the flow.
- Speculation. Low entry costs encouraged developers to file many requests, inflating queues to several times the installed capacity of the grid.
RTOs began moving to clusters before FERC required it. PJM's reformed process, which FERC accepted in November 2023, replaced serial queues with transition cycles and then annual cycles, each studied as a group. FERC Order No. 2023 then required every public utility transmission provider to adopt a first-ready, first-served cluster process with readiness deposits, site control requirements and withdrawal penalties.
The engineering case for clusters is straightforward. When projects that are electrically close are studied together, the study captures the combined power flows, identifies the shared upgrades once and allocates their costs by each project's contribution. Keentel's guide to cluster interconnection studies shows how much location and POI voltage drive the result: in one transitional cluster we analyzed, allocated costs ranged from zero to about $2,700 per kilowatt depending on where each project connected.
How Keentel Engineering helps here. Keentel replicates cluster study results using the transmission provider's own base cases and methods, so clients can see which upgrades they drive, which they share and which assumptions control their cost. That same capability is the foundation of a joint load and generation study.
2. Why large loads and generation now arrive together
Three trends have pushed loads and generation into the same study.
Load growth has returned at scale. After nearly two decades of flat demand, utilities and grid operators are forecasting rapid growth driven by data centers, manufacturing and electrification. NERC's 2025 Long-Term Reliability Assessment raised its ten-year peak demand forecast sharply, with reporting describing an increase of roughly a quarter over the prior forecast, driven largely by data centers. Individual requests are now routinely in the hundreds of megawatts, and several campuses exceed a gigawatt.
Generation queues are long and the grid is short of capacity. Lawrence Berkeley National Laboratory's Queued Up reports have documented interconnection backlogs measured in thousands of gigawatts, with typical times from request to commercial operation of several years. The 2026 edition reported that the backlog eased somewhat in 2025 amid high withdrawals, but queues remain far larger than the installed fleet. Meanwhile, capacity markets in PJM and MISO have signaled scarcity.
Developers are bringing their own generation. Faced with multi-year waits for network upgrades and capacity, large-load customers increasingly propose to build or contract generation in the same area — gas turbines on site, solar and storage nearby, or an existing nuclear or gas plant co-located with the load. The argument is intuitive: if the load brings its own supply, the grid should need little or nothing.
The intuition is partly right. Generation near load can relieve the transmission system — but only under the right conditions, and those conditions must be studied, not assumed.
3. Why megawatts cannot simply be netted
3.1 Distribution factors
In a meshed transmission network, power does not flow along a contract path. It divides among parallel paths in inverse proportion to their impedance. Planners describe this with distribution factors.
The power transfer distribution factor (PTDF) of a monitored line â„“ for an injection at bus i and withdrawal at a reference bus is the fraction of the transfer that flows on line â„“:

For a transfer from bus i to bus j, the distribution factor is the difference of the two PTDFs:

The line outage distribution factor (LODF) gives the share of an outaged line's flow that moves onto another line k after the outage:

These linear factors come from the DC power flow approximation, in which line flows depend only on bus voltage angles and line reactances. They are accurate enough for screening thermal impacts on a high-voltage network with X/R ratios above about 5, which describes most 115–765 kV systems. Detailed AC power flows are still needed for voltage, reactive power and final thermal results.
3.2 When a load and a generator cancel
A new load of P_L megawatts at bus a and a new generator of P_G megawatts at bus b change the flow on line â„“ by:

The two cancel on every line only if a and b are the same bus (identical PTDFs) and P_G equals P_L at that moment. If the buses differ, the generator and load have different distribution factors on each line, and their effects cancel on some lines, add on others and leave the rest partly offset. If the generator is not running — because it is on maintenance, has tripped, is a solar plant at night or a wind plant in a calm — the load's effect appears in full.
That is the whole argument in one equation: netting works on a flowgate only to the extent that the distribution factors match and both projects are in service at the same output.
3.3 Screening thresholds
RTOs use distribution factor thresholds to decide which projects are responsible for an overload. PJM's generator deliverability procedures, for example, have long used a distribution factor cutoff of about 5% together with megawatt-impact thresholds, and MISO's definitive planning studies apply distribution factor and megawatt-impact criteria to assign upgrades. Thresholds differ by RTO, by study type and over time, so Keentel always confirms the values in the current tariff and business practice manuals before screening.
Thresholds matter for joint studies because a load and a generator may each fall below the threshold on a flowgate while their combined impact does not — or a load may relieve a flowgate that a generator overloads and not be credited for it if the two are studied in separate processes.
Keentel Study Spotlight — Distribution factor screening for paired projects. Keentel computes PTDF, DFAX and LODF matrices for the load bus, each candidate generation bus and every monitored flowgate in the transmission provider's base case. The result is a one-page table that shows, for each flowgate, whether the pairing relieves, aggravates or is neutral — before anyone commits to a site or a generation mix.
Worked example 6 — Distribution factors on a synthetic 345 kV network
To make the ideas concrete, Keentel built a small synthetic 345 kV network with six buses and eight lines (Figure 1). Bus 1 is a West hub with existing generation and serves as the reference bus. Bus 3 is a metropolitan load center. Bus 4 is a new POI where a 900 MW data center wants to connect. Bus 6 is a renewable zone where a developer proposes 900 MW of new generation "to serve the data center."

The distribution factors for a withdrawal at Bus 4 (the data center) and an injection at Bus 6 (the remote generator), each balanced at the West hub, are:
| Line | Load at Bus 4 (DFAX, %) | Generation at Bus 6 (DFAX, %) | Net effect of pairing |
|---|---|---|---|
| L1 West–North | +55.4 | −44.7 | Mostly cancels |
| L2 West–South | +44.6 | −55.3 | Mostly cancels |
| L3 North–Metro | +18.1 | −14.6 | Mostly cancels |
| L4 North–POI | +37.3 | −30.1 | Partly cancels |
| L5 South–POI | +33.2 | −2.7 | Load dominates |
| L6 POI–Metro | −18.1 | +14.6 | Mostly cancels |
| L7 Renewable–POI | +11.4 | +47.4 | Adds |
| L8 Renewable–South | −11.4 | +52.6 | Gen dominates |
On the West-side lines the two projects largely cancel, which is the relief the developer expects. On L5 the load dominates because the generator hardly uses that path, and on L7 the two effects add: the load at Bus 4 pulls more power from the renewable zone along L7, exactly the line the new generator already loads. Netting the megawatts would have missed both.
4. Five scenarios on the same network
Keentel ran the synthetic network through five scenarios using a DC power flow with N-1 contingency analysis of every line. Line ratings are set so that the base case has no N-0 or N-1 overloads. The numbers are illustrative, but the pattern is one Keentel sees repeatedly in real studies.

Figure 1. Keentel worked examples 1–4 on a synthetic six-bus 345 kV network: (A) 900 MW of load alone at Bus 4, (B) the same load paired with 900 MW of generation at Bus 6 in the same zone, and (C) the load with 900 MW of co-located generation at Bus 4 in service. Red lines exceed their rating at N-0 or after the worst single contingency.
Worked example 1 — The load alone
With 900 MW added at Bus 4 and supplied by existing West-hub generation, every line remains within its rating with all lines in service; the heaviest is L1 West–North at 86%. After single contingencies, the picture changes: losing L1 pushes L2 West–South to 140%, losing L2 pushes L1 to 140%, and losing L1 also pushes L5 South–POI to 139%. A load-only study would require upgrades on the West-side corridor and on L5.
Worked example 2 — The generator alone
With 900 MW of new generation at Bus 6 (and no new load), the West-side lines unload, but the export path from the renewable zone fills: L7 Renewable–POI reaches 89% at N-0, and losing either L7 or L8 overloads the other to 150%, and losing L1 or L5 pushes L7 to 110–113%. A generator-only cluster study would assign the generator upgrades on L7 and L8.
Worked example 3 — Netting in the zone: load at Bus 4, generator at Bus 6
The developer's proposal is to pair the two and argue that the zone is "net zero." The joint study gives a mixed answer. The West-side lines now carry only modest increases over the base case (L1 at 66% instead of 86%), which is genuine relief. But L7 Renewable–POI reaches 99% at N-0, and single contingencies still overload it: losing L8 pushes L7 to 150% (and losing L7 pushes L8 to 150%), losing L5 pushes L7 to 138%, losing L1 pushes L7 to 133% and L5 to 118%. The pairing solved the load's West-side problem and kept the generator's export problem, while creating new contingency overloads that neither project caused alone.
Worked example 4 — Co-location at the same bus, and the generator-trip case
With 900 MW of generation at Bus 4 itself, and the generator running at full output, every line flow returns exactly to the base case and there are no N-1 overloads. This is the only case in which netting is exact.
Now trip the generator while the data center stays on. The network sees 900 MW of new load at Bus 4 with no local supply — which is worked example 1. The same 140% contingency overloads reappear. If the load can stay connected when its generator is unavailable, the transmission system must be planned for that condition, or the design must include an automatic scheme that curtails the load when the generator trips, or the service must be explicitly non-firm.
Worked example 5 — Light load and high renewable output
Finally, Keentel tested a light-load hour: metro load reduced to 1,100 MW, existing renewable output 1,400 MW plus the new 900 MW generator, and the data center at full load. Without the data center, the new generator overloads L7 to 119% and L8 to 111% at N-0. With the data center on, L8 improves to 101% but L7 worsens to 129%, because the load pulls renewable output toward Bus 4 along L7. A study that only looked at summer peak would never have seen these overloads.
Figure 2. Keentel worked examples 1–5: worst N-0 or N-1 loading of five flowgates for each scenario. The same 900 MW of load and 900 MW of generation produce very different results depending on location and generator status.
What the five scenarios teach
| Scenario | Worst loading | Lesson |
|---|---|---|
| Base case | 61% | Clean starting point |
| Load alone | 140% (N-1) | Load triggers West-corridor upgrades |
| Generator alone | 150% (N-1) | Generator triggers export-path upgrades |
| Load + generator in same zone | 150% (N-1) | Partial relief; export problem remains; new overloads appear |
| Load + co-located generator, running | 61% | Exact netting only at the same bus with the generator in service |
| Co-located generator tripped | 140% (N-1) | The load must be planned for, curtailed or made non-firm |
How Keentel Engineering helps here. Keentel runs these scenarios on the transmission provider's actual base case, not a synthetic network. We report every flowgate where the pairing helps, hurts or makes no difference, under peak, shoulder and light-load dispatch, with and without the generator — so the client can see the real value of co-location before negotiating service.
5. Dispatch, load level and study cases

A transmission study answers a question about a specific condition: a load level, a generation dispatch, a set of facilities in and out of service and an interchange pattern. Change the condition and the answer can change. For a joint study, the set of conditions must be chosen so that it brackets how the load and the generation will actually operate together.
5.1 The cases Keentel recommends
| Study case | Load assumption | Generation assumption | What it reveals |
|---|---|---|---|
| Summer peak | Large load at full contracted demand; system at peak forecast | Paired generation at expected peak output (solar reduced late in the day; gas at full output) | Load-driven thermal and voltage limits |
| Winter peak | Large load at full demand; winter forecast | Solar near zero at evening peak; wind as accredited; gas derates for cold weather | Evening and cold-weather adequacy; fuel risk |
| Shoulder / light load | System load 40–60% of peak; large load at full or reduced demand | High renewable output; paired generation exporting | Export-driven overloads and high voltage |
| Generator out | Large load at full demand | Paired generator unavailable (maintenance or trip) | Whether the load needs firm grid service |
| Load out | Large load tripped or transferred to backup | Paired generation at full output | Whether the generator becomes stranded or overloads its outlet |
| Ramp and partial build | Load at intermediate phases (for example 25%, 50%, 75%) | Generation at its phased in-service dates | Whether interim service is possible before upgrades |
The last two cases are frequently missed. A data center that transfers to on-site backup power during a disturbance removes hundreds of megawatts in seconds. If co-located generation keeps running, it suddenly exports its full output into the grid through a POI that may never have been studied for that injection. Conversely, if the load ramps in over three to five years while generation comes online in one step, the interim years can look very different from the final build.
5.2 Dispatch assumptions and the "who supplies the load" question
When a study adds a large load, it must decide which generators increase their output to supply it. Common choices are:
- System-wide scaling, in which all dispatchable generators increase in proportion to their headroom.
- Zonal or area scaling, in which only generators in the load's area respond.
- Specific resource pairing, in which the paired project is assumed to supply the load and the rest of the system is unchanged.
Each choice moves flows differently. In the synthetic example, Keentel balanced the new load at the West hub; balancing it across all generators would have spread the impact. For joint studies, Keentel runs the specified pairing and at least one system-wide sensitivity, because the paired resource will not always be the marginal unit in the market.
How Keentel Engineering helps here. Keentel defines a study matrix of load levels, dispatch patterns and outage conditions that brackets real operation, agrees it with the transmission provider early, and documents every assumption so that results can be reproduced and defended.
6. Contingencies and NERC TPL-001 planning events
Joint studies use the same planning events as any other transmission study. NERC Reliability Standard TPL-001-5.1 defines planning events P0 (no contingency) through P7 (common-structure and multiple contingencies), with performance requirements for each. Keentel's TPL-001-5.1 guide covers the standard in detail; the points below are the ones that matter most for paired load and generation.
| TPL-001 event | Example relevant to a load–generation pair | What to check |
|---|---|---|
| P1 single contingency | Loss of the co-located generator, the load's supply transformer or one 345 kV line | Thermal and voltage limits with the load still connected |
| P2 single event (bus section, breaker internal fault) | Loss of a substation bus section carrying both projects | Whether one event removes the generator but not the load |
| P3 generator out, followed by a P1 event | Paired generator on outage, then a line trips | The "generator out" design case for the load |
| P4 stuck breaker | Breaker failure at the shared POI | Whether the scheme separates load and generation unevenly |
| P5 protection system failure | Delayed clearing near a large power-electronic load | Load ride-through and stability |
| P6 two overlapping single contingencies | Line out for maintenance, then the generator trips | Whether curtailment schemes are needed |
| P7 common structure | Double-circuit tower carrying both projects' supply lines | Whether both supplies can be lost at once |
For load-only planning, TPL-001 allows non-consequential load loss under some multiple-contingency events, and interruption of firm demand is constrained for single contingencies. When a large load's service depends on generation, the study must be clear about which load is firm, which is curtailable and which conditions trigger curtailment.
Keentel Study Spotlight — Joint contingency analysis. Keentel builds a contingency list that combines the transmission provider's standard P1–P7 events with project-specific events: generator trip with the load on, load trip with the generator on, POI breaker failure and common-structure outages of the supply lines. Each result is reported against the TPL-001 performance requirement it tests.
7. Short-circuit duty and system strength
Generation and large loads change the short-circuit behavior of a POI in different ways.
- Synchronous generation (gas turbines, reciprocating engines, nuclear) adds substantial fault current. A 900 MVA synchronous unit with a subtransient reactance of 0.20 per unit behind a 12% step-up transformer contributes roughly 2,800 MVA to a three-phase fault at the high-voltage bus.
- Inverter-based resources (solar, wind, BESS) contribute only about 1.0–1.2 per unit of their rated current, and their contribution is controlled by software, so it adds little to system strength in the classical sense.
- Data center loads are predominantly power-electronic. Their rectifiers and UPS systems contribute little or no fault current, and their behavior during faults depends on controls, ride-through settings and transfer logic.
Worked example 7 — Fault current and short-circuit ratio at the POI
Take a 345 kV POI with an existing three-phase short-circuit level of 9,000 MVA, or about 15.1 kA:
Adding a 900 MVA synchronous gas plant raises the short-circuit level by about 2,800 MVA to roughly 11,800 MVA (about 19.8 kA). Breakers at the POI and at neighboring substations must be checked against the higher duty, including asymmetrical and X/R effects under IEEE C37.010.
If the 900 MW paired generation were inverter-based instead, it would add only about 990 MVA of fault contribution, and the short-circuit ratio (SCR) for a 900 MW inverter plant at this POI would be:

That is a strong connection. But SCR is a crude metric when several inverter-based resources and large power-electronic loads share an area. Keentel's guide to system strength metrics explains why weighted and composite metrics — and ultimately EMT studies — are needed when several inverter-based projects and power-electronic loads are electrically close.
How Keentel Engineering helps here. Keentel performs short-circuit studies under IEEE C37.010 and C37.5-based methods, checks breaker duty at the POI and neighboring stations for every pairing option, and screens system strength with SCR, weighted SCR and composite SCR before recommending EMT studies.
8. Voltage and reactive power
Large data center loads are often specified at a power factor near unity at the POI, but their reactive demand is not zero, and it changes with workload, cooling load and the state of on-site equipment. Large loads also depress voltage simply by drawing current through the network impedance.
Worked example 8 — Voltage change from a 900 MW load at 345 kV
For a load of P + jQ at a bus with Thevenin resistance R and reactance X (in per unit on a 100 MVA base), the voltage drop is approximately:

At the 9,000 MVA POI from Example 7 with X/R = 12, the Thevenin impedance is about 0.0111 per unit on 100 MVA. A 900 MW load at 0.98 power factor draws about 183 Mvar. The approximate voltage drop is 2.9%, of which only about 0.8% comes from the real power and 2.0% from the reactive power. Each 100 Mvar changes voltage by about 1.1%.
At a weaker 4,000 MVA POI, the same load depresses voltage by about 6.4%. Holding the drop to 3% would require roughly 137 Mvar of reactive support — capacitor banks, a STATCOM or reactive capability from the paired generation.
This is where pairing can help genuinely: generation or storage at the same POI can supply the reactive power the load needs. It is also where pairing can hurt: if the paired generation trips, the voltage support disappears at the same moment as the active-power supply.
Keentel Study Spotlight — Voltage and reactive power study. Keentel runs P-V and Q-V analyses at the POI with and without the paired resource, sizes static and dynamic reactive devices, and checks that voltage limits are met under the generator-out and load-out cases. Our STATCOM and SVC guides explain the device trade-offs.
9. Dynamics: large-load ride-through, load loss and EMT
9.1 Why large loads are a dynamic problem
Steady-state studies assume loads stay connected. Data centers do not always do so. Their UPS systems are designed to protect servers from voltage disturbances, and when the grid voltage dips below a threshold for long enough, the facility transfers to batteries and then to on-site generators. To the grid, that transfer looks like the sudden loss of hundreds of megawatts of load.
NERC has documented this behavior. Its incident review of a July 2024 event in Virginia described roughly 1,500 MW of data center load lost after a fault on the transmission system, with the load returning over the following period. NERC issued a Level 2 alert on large loads in 2025, and further guidance followed in 2026. On July 22, 2026, a much larger event occurred in Northern Virginia, in which several gigawatts of data center load transferred off the grid within seconds; public reporting put the amount at roughly 3 to 4 GW, and PJM and Dominion Energy reviewed the event. PJM's November 2026 filing at FERC reportedly included ride-through requirements for large loads, and ERCOT developed large electronic load ride-through requirements through NOGRR 282.
For joint studies, these events matter in three ways:
- Frequency. Sudden loss of a gigawatt of load produces an overfrequency event. If co-located generation keeps running, the overfrequency is larger and the generation may also trip on its own protection.
- Voltage. Load loss removes reactive demand and can produce high voltage, especially near capacitor banks or lightly loaded cables. Keentel's guide on temporary and transient overvoltages discusses the consequences.
- Recovery. When the load returns, it may do so in large steps that the grid and the paired generation must follow.
9.2 Model requirements
Planning models for large loads are still developing. Composite load models such as the WECC composite load model represent motors and electronic loads in aggregate, but they were not designed for data centers. NERC, WECC and RTOs are developing guidance and data requirements for large power-electronic loads, and MOD-032-2 adds new data requirements for loads used in planning models. Keentel's MOD-032-2 guide covers those requirements.
Until standard models mature, Keentel recommends:
- A positive-sequence dynamic model of the load that represents ride-through thresholds, transfer to backup and recovery ramp, validated against the facility's design.
- An EMT model of the load's front end (rectifiers, UPS, filters) for weak-grid and harmonic interaction studies.
- Matching models for the paired generation, so that the study captures how the generator and load respond to the same fault.
Keentel Study Spotlight — Large-load ride-through study. Keentel models the facility's UPS and transfer logic, simulates the transmission provider's fault list, and reports which faults cause load loss, how much load is lost, how the paired generation responds and how fast the system recovers. Results feed directly into ride-through settings and the service agreement.
10. Power quality and oscillations
Large power-electronic loads and inverter-based generation share another concern: power quality. Rectifiers inject harmonics; IEEE 519-2022 limits harmonic current at the point of common coupling. When harmonic filters, cable capacitance and network inductance combine, resonances can amplify specific harmonics — the subject of Keentel's harmonic resonance guide.
AI training workloads add a newer concern. Large training jobs can cause synchronized power swings across thousands of GPUs, producing load changes of tens to hundreds of megawatts over seconds, sometimes periodically. Grid operators and NERC have identified forced oscillations and rapid load fluctuations from large computing loads as an emerging risk. Where a large load shares a POI with inverter-based generation, the generation's plant controller and the load's power swings can interact.
Practical mitigations include on-site energy storage to smooth fluctuations, ramp-rate limits in the load's power management system, and oscillation monitoring with phasor measurement units. All of these should be studied, not assumed.
How Keentel Engineering helps here. Keentel performs harmonic studies under IEEE 519, frequency scans for resonance, and time-domain studies of load fluctuations, and specifies smoothing storage and monitoring where they are needed.
11. Deliverability and resource adequacy
11.1 Two different questions
Thermal and voltage studies ask whether the grid can carry the flows. Resource adequacy asks whether enough capacity exists to serve load reliably. In RTO capacity markets, a generator must usually pass a deliverability test — its output must reach load across the system under stressed conditions — before its capacity counts.
For a large load paired with generation, the two questions interact:
- If the paired generator is deliverable and accredited, it adds capacity to the region, which helps offset the load's addition to peak demand.
- If the generator is studied only for energy service (not deliverable), it may not count for capacity, and the load's addition to peak demand still requires capacity from elsewhere.
- If the generator is behind the meter, it may reduce the load's measured demand but not count as a capacity resource at all.
Worked example 10 — How much of a paired portfolio counts for capacity
A developer pairs a 900 MW data center with 600 MW of gas turbines, 400 MW of solar, 300 MW of wind and 300 MW of four-hour battery storage — 1,600 MW of nameplate capacity. With illustrative ELCC accreditation factors (gas 79%, solar 9%, wind 20%, four-hour storage 55%), the accredited capacity is:
| Resource | Nameplate (MW) | Illustrative ELCC | Accredited (MW) |
|---|---|---|---|
| Gas turbines | 600 | 79% | 474 |
| Solar | 400 | 9% | 36 |
| Wind | 300 | 20% | 60 |
| Four-hour BESS | 300 | 55% | 165 |
| Total | 1,600 | 735 |
Against a 900 MW load, the portfolio carries 735 MW of accredited capacity, leaving a 165 MW shortfall — despite 1,600 MW of nameplate. ELCC values vary by RTO, season and year; Keentel uses the current published values for each market. The point stands: nameplate netting overstates what a portfolio contributes to reliability.
Keentel Study Spotlight — Deliverability and accreditation review. Keentel runs the RTO's deliverability methodology for the paired resources and estimates accredited capacity under current ELCC values, so the load customer knows how much of its demand the portfolio actually covers in the capacity market.
12. Firm, non-firm and flexible service
12.1 Why flexibility matters
If network upgrades take five to eight years, as many cluster results show, a large load that insists on firm service may wait years after its building is ready. A load that accepts curtailment during the hours the grid is constrained may connect much sooner. Research by Duke University's Nicholas Institute in 2025 estimated that the US grid could accommodate roughly 76 to 126 GW of new flexible load if that load accepted curtailment of 0.25% to 1% of its annual energy. Keentel's grid flexibility guide covers the economics.
RTOs have moved in this direction. FERC's December 2025 order on co-location in PJM directed new transmission service options, reported to include non-firm options. SPP's High Impact Large Load process includes a provisional path. ERCOT's 2025 legislation addresses curtailment of large loads in emergencies. PJM's Board decision in January 2026 and its later filings were reported to place new large loads that do not bring capacity among the first to be curtailed in emergencies.
12.2 Flexibility must be quantified
The weakness of many flexible-service proposals is that they assume curtailment will be rare without showing it. A joint study should calculate, hour by hour, how often the binding constraint would be exceeded and how much load would need to be curtailed.
Worked example 11 — Curtailment hours on a constrained flowgate

Keentel built a synthetic 8,760-hour loading profile for a 1,000 MW flowgate whose existing flow follows daily and seasonal patterns (average about 600 MW, peaking above 900 MW). A new 900 MW load has a distribution factor of 32% on the flowgate, adding up to 288 MW.
| Result | Value |
|---|---|
| Hours with the flowgate above its limit | 1,010 hours (11.5% of the year) |
| Maximum curtailment needed in any hour | 544 MW |
| Total curtailed energy | about 124,500 MWh |
| Curtailed energy as a share of the load's annual energy | about 1.6% |
The answer is not "rare." The load would need to curtail in more than one hour in nine, sometimes by more than half its demand, though the energy lost is only about 1.6%. Whether that is acceptable depends on the load's ability to shift work, its on-site storage and generation, and its contract. The study has to produce the numbers before anyone signs.
Keentel Study Spotlight — Flexible-service curtailment study. Keentel runs hourly security-constrained analyses of the binding flowgates using RTO base cases and historical or forecast profiles, and reports the number, depth and timing of curtailment hours for each phase of the load's ramp. Clients use the results to size on-site storage, negotiate service terms and decide whether to pay for upgrades.
13. Co-location: what FERC has decided
Co-location — connecting a large load at or behind the POI of an existing or new generator — has been the most contested form of pairing.

- In November 2024, FERC rejected an amended interconnection service agreement that would have expanded co-located load at an existing nuclear plant in PJM, citing concerns that included reliability and cost shifting. The decision made clear that co-location raises transmission service and cost allocation questions, not only interconnection questions.
- In December 2025, after a show cause proceeding, FERC directed PJM to revise its tariff to provide clear transmission service options for co-located loads, including options that do not require full network service. Public summaries of the order describe three new service options and requirements for PJM to address behind-the-meter generation rules.
- In October 2025, the Department of Energy used its authority under Section 403 of the Federal Power Act to direct FERC to consider rules for interconnecting large loads (the directive referenced loads of 20 MW and above) and hybrid facilities to the transmission system.
- In June 2026, FERC issued show cause orders under Section 206 to all six RTOs and ISOs it regulates, directing each to justify its existing large-load integration rules or propose reforms, including measures on cost transparency and customer protection. Responses were due November 16, 2026.
From an engineering point of view, co-location raises four questions a joint study must answer:
| Question | Why it matters |
|---|---|
| Is the load ever served by the grid? | If yes, the grid must be planned for it under the generator-out condition, or the load must be curtailed automatically. |
| Does the generator still sell to the grid? | If yes, its deliverability and the POI's export capability must be studied with the load off. |
| What happens during faults and transfers? | Load ride-through and generator protection must be coordinated so that one does not trip the other unnecessarily. |
| Who pays for what? | Network upgrades, ancillary services and transmission charges depend on the service chosen. |
How Keentel Engineering helps here. Keentel evaluates co-location configurations — full islanding, partial grid service, backup service and full network service — against the transmission provider's criteria, designs the POI substation and protection, and documents the study basis for the service election the client makes.
14. What the new processes say
The processes below were filed, accepted or reported by November 2026. They are summarized for orientation only; Keentel always works from the current tariff and business practice manuals.
| Process | Region | What it does | Status reported |
|---|---|---|---|
| Fast Energization | PJM | Studies generation and large-load transmission service together in one process; targets roughly one year instead of roughly two; reportedly includes cost transparency for states and large-load ride-through requirements | Filed at FERC November 16, 2026 (ER27-531) as part of PJM's response to the show cause order |
| Large Load Addition Resource Study (LARS) | MISO | Studies loads above 200 MW together with new generation in the same local resource zone; 120-day target | Filed at FERC in fall 2026 |
| Expedited Resource Addition Study (ERAS) | MISO, SPP | Fast-tracks generation needed for near-term resource adequacy | MISO's ERAS accepted by FERC July 2025; SPP's also accepted |
| High Impact Large Load (HILL) and HILL generation pathway | SPP | Dedicated process for large loads with a provisional service option and associated generation | Accepted by FERC January 2026 |
| Large-load batch study ("Batch Zero") | ERCOT | Studies large loads in batches rather than one at a time, under Texas SB 6 | Approved by ERCOT in 2026 |
| Co-location service options | PJM | New transmission service choices for co-located load | Directed by FERC December 2025 |
| Critical Issue Fast Path decision | PJM | Board decision on integrating large-load additions | Decisional letter January 16, 2026 |
14.1 PJM Fast Energization
PJM's proposal responds directly to the problem this guide describes. Under the existing approach, a generator seeking interconnection goes through the generation cluster process, while a large load seeking transmission service is studied by the transmission owner and PJM through a separate load-study path. The two are studied on different schedules, against different assumptions. PJM's filing would study them together, so that a generator built to serve a large load can be evaluated with that load in the same case, and it targets roughly one year from start to finish instead of about two.
14.2 MISO LARS
MISO's proposal is narrower and faster. It applies to loads above 200 MW that come with new generation in the same local resource zone, and it targets a 120-day study. The zonal pairing reflects MISO's resource adequacy construct, in which local resource zones must meet local clearing requirements. The 120-day target is aggressive; it is achievable only if the load and generation data, models and one-line diagrams are complete at submission.
14.3 The common thread
Every process listed above, in its own way, accepts the premise of this guide: load and generation that arrive together should be studied together, against the same future grid. The differences lie in eligibility thresholds, schedules, deposits and how flexibility is treated.
Keentel Study Spotlight — Process selection and readiness review. Keentel compares the processes available in the client's RTO, estimates schedule and cost exposure for each path, and prepares the technical data package — load ramp, models, one-lines, protection and ride-through information — so the application is complete on day one.
15. Schedule math
Worked example 9 — What a faster study is worth
A 900 MW data center is ready to energize when its buildings are complete. Every month of grid-related delay has a cost. Using an illustrative delay cost of $15 per kilowatt-month (lost revenue and carrying cost; real values vary widely), the cost of each study path relative to a 120-day joint study is:
| Study path | Months to results | Delay cost vs 120-day path |
|---|---|---|
| Sequential: generation cluster, then load service | 36 | about $432 million |
| Separate studies in parallel (about two years) | 24 | about $270 million |
| Joint study (about one year) | 12 | about $108 million |
| Joint study in the same zone (120 days) | 4 | baseline |

Figure 3. Keentel worked example 9: illustrative study durations for sequential, parallel and joint processes.
The numbers are illustrative, and study time is only part of the schedule — upgrades, equipment lead times and construction often dominate. But the comparison shows why the industry is moving toward joint processes, and why a complete, accurate application is worth the effort.
16. Cost allocation
When a load and a generator share an upgrade, the cost has to be divided. Most RTOs allocate network upgrade costs among cluster participants in proportion to their megawatt impact on the overloaded facility — the product of each project's size and its distribution factor.
Worked example 12 — Sharing a $180 million upgrade
A $180 million 345 kV line upgrade relieves a flowgate that three projects overload together:
| Project | Size (MW) | DFAX on flowgate | MW impact | Share | Allocated cost |
|---|---|---|---|---|---|
| Data center load | 900 | 32% | 288 | 69.6% | $125.2 million |
| Solar plus BESS | 500 | 18% | 90 | 21.7% | $39.1 million |
| Wind | 400 | 9% | 36 | 8.7% | $15.7 million |
Allocation rules differ by RTO and by whether the facility is a load or a generator, and load-driven upgrades may be recovered through transmission rates rather than assigned directly. The FERC show cause orders and proposed federal legislation on data center cost responsibility both point toward larger loads bearing more of the upgrade cost they cause. Joint studies make the allocation more accurate, because each project's real contribution is measured in the same case.
How Keentel Engineering helps here. Keentel replicates cost allocation calculations, tests sensitivity to dispatch and withdrawal of other projects, and identifies lower-cost alternatives — reconductoring, advanced conductors, series compensation or flexible service — before a client accepts an allocation.
17. Modeling both against the same future grid
The most important principle in joint studies is also the easiest to state and the hardest to execute: the load and the generation must be modeled against the same future grid. In practice, that means one study case that contains:
- The same topology, including every planned transmission project with a credible in-service date and every retirement.
- The same generation queue, with higher-priority projects modeled consistently and withdrawals reflected promptly.
- The same large-load queue, including other large loads with signed agreements or credible service requests in the area.
- The same load forecast for the rest of the system, including the RTO's own large-load adjustments.
- The same dispatch rules and interchange assumptions.
- The same contingency and monitored-element lists.
- Compatible dynamic and EMT models for every inverter-based resource and every large power-electronic load.
When generation and load are studied in separate processes, each process builds its own case. The generation cluster case may not include large loads that have not yet signed agreements; the load study may assume generation that later withdraws from the queue. The results disagree, and both can be wrong.
17.1 Model management
Keentel maintains a model management log for every joint study: which base case and revision, which projects were added or removed and why, which models were updated and which assumptions changed. When an RTO issues a new base case or a project withdraws, the log shows which results need to be rerun.
17.2 MOD-032-2 and load data
NERC Reliability Standard MOD-032-2 requires data for power system modeling and analysis, and its revision added expectations for load data that matter directly to large loads. Large-load customers should expect their transmission service provider to request:
- Load ramp schedules by phase, with realistic dates.
- Load composition: IT load, cooling, auxiliary loads and on-site generation.
- Power factor and reactive capability at the POI.
- Ride-through capability and transfer logic.
- Dynamic and EMT models of the load's front end, or data sufficient to build them.
- Harmonic emission data.
Supplying this data early is the single most effective way to shorten a study.
Keentel Study Spotlight — Unified study case. Keentel builds a single study case that combines the RTO's latest base case, both queues, the client's load and generation models and project-specific contingencies, and maintains it through every RTO case update. The same case drives steady-state, short-circuit, stability and EMT work, so every result describes the same future grid.
18. A joint study workflow
Keentel's joint load and generation study follows the steps below. The order matters: earlier steps change the scope of later ones.
| Step | Activity | Output |
|---|---|---|
| 1 | Define the pairing: load ramp, generation mix, POIs, service election | Project description and study scope |
| 2 | Screen distribution factors for candidate POIs and generation sites | PTDF/DFAX table; ranking of sites |
| 3 | Build the unified study case | Case log; model inventory |
| 4 | Steady-state analysis: N-0, N-1 and TPL-001 events for each study case | Thermal and voltage violations by case |
| 5 | Generator-out and load-out cases | Firm vs non-firm service requirements |
| 6 | Short-circuit and breaker duty | Breaker replacements; system strength screen |
| 7 | Dynamic stability including load ride-through | Stability and ride-through results; setting recommendations |
| 8 | EMT studies where screening indicates weak-grid or power-electronic interaction | Control and filter recommendations |
| 9 | Deliverability and accreditation | Accredited capacity; capacity shortfall |
| 10 | Upgrade alternatives and cost allocation | Upgrade list, costs and schedules |
| 11 | Flexible-service and curtailment analysis | Curtailment hours and depth by phase |
| 12 | Report and agreement support | Technical exhibits for service and interconnection agreements |
How Keentel Engineering helps here. Keentel can perform the complete workflow independently, replicate or review a transmission provider's study, or support a client through an RTO process by preparing data, reviewing interim results and responding to deficiency notices.
19. What each party should do now
19.1 Large-load developers and data center owners
- Treat interconnection as a design input, not an afterthought. Choose sites with distribution factor screening before land is committed.
- Prepare a credible load ramp. Overstated early phases trigger unnecessary upgrades; understated phases delay service later.
- Decide early whether you will accept flexible or non-firm service, and quantify what curtailment would cost your operation.
- Design ride-through into the facility. UPS and transfer settings are now a grid reliability issue, and new requirements are arriving in PJM and ERCOT.
- If you plan to pair generation, study the generator-out case before you announce the pairing.
19.2 Generation developers
- Treat a large-load offtaker as part of your interconnection strategy, not only your commercial strategy. Pairing may change your upgrades.
- Confirm whether your project needs deliverability for capacity value, or only energy service.
- Model your plant's behavior during the load's ride-through events; a large load trip can expose your plant to high voltage and overfrequency.
19.3 Transmission owners and utilities
- Build large-load data requirements into your interconnection and service procedures, aligned with MOD-032-2.
- Coordinate generation and load study teams so that both use the same case.
- Require load models that represent ride-through and recovery, and validate them with event data.
19.4 Regulators and policymakers
- Expect joint processes to shorten study time but not construction time. Upgrades with five- to eight-year schedules remain the critical path.
- Insist on transparent assumptions about curtailment and cost allocation, so that flexibility is real and costs land where they are caused.
20. The ten most common mistakes in paired load and generation proposals
1. Netting nameplate megawatts in a zone and assuming the grid sees nothing.
2. Studying only summer peak and ignoring light-load export conditions.
3. Leaving out the generator-out case.
4. Leaving out the load-out case, in which the generator suddenly exports its full output.
5. Assuming a data center is a constant-power load that never trips.
6. Ignoring reactive power and voltage support when the paired generator is offline.
7. Counting nameplate capacity instead of accredited capacity.
8. Assuming flexibility without calculating curtailment hours.
9. Studying load and generation in different cases with different queues.
10. Submitting incomplete data to a fast-track process and losing the schedule advantage to deficiency cycles.
How Keentel Engineering helps here. Keentel's independent review checks a proposal against all ten points before it reaches the transmission provider. Each one caught early saves months later.
21. Phased load ramps and interim service
Large loads rarely arrive all at once. A 1 GW campus may be built in four or five phases over five to seven years, and each phase may itself ramp over months as servers are installed. Generation, by contrast, often comes online in large blocks: a gas plant at its commercial operation date, a solar plant over a few weeks of energization.
The mismatch creates three study questions that load-only or generation-only studies seldom ask:
- Can the early phases connect before upgrades are complete? Often yes. The first 200–300 MW of a campus may fit within existing headroom, with or without flexible service, while later phases wait for upgrades.
- Does generation arriving before the load create a temporary export problem? A paired generator that reaches commercial operation two years before the load it was meant to serve is, for those two years, simply a new generator injecting into the grid.
- Does load arriving before generation create a temporary supply problem? If the generation is delayed by equipment lead times, permitting or a queue restudy, the load may need firm service it had planned to avoid.
Keentel studies each phase as its own case, with the load and generation each at their realistic in-service level for that year. The output is a phase-by-phase table showing which upgrades are needed for each step and which phases can proceed on flexible service.
Worked example 13 — A phased pairing

Using the synthetic network from Section 4, suppose the 900 MW load arrives in three 300 MW phases and the 900 MW co-located generator arrives in one block with phase 2. Keentel ran each phase with the load alone at Bus 4:
| Load at Bus 4 (no generation) | Worst N-0 loading | Worst N-1 loading | Limiting event |
|---|---|---|---|
| 300 MW | 70% | 110% | Loss of L1 overloads L2 West–South |
| 600 MW | 78% | 125% | Loss of L1 overloads L2 West–South |
| 900 MW | 86% | 140% | Loss of L1 overloads L2 West–South |
The worst N-1 loading rises by about 5 percentage points per 100 MW, from roughly 95% with no new load. Firm headroom without upgrades is therefore only about 100 MW. Even phase 1 needs either flexible service (curtailment after the loss of L1), a remedial scheme or an upgrade to L2. Once the co-located generator is in service, phases 2 and 3 are firm only while it runs; for the generator-out condition, the load must again be curtailed or the West corridor upgraded. That conclusion is exactly what a phased joint study should state:
| Phase | Load at Bus 4 | Co-located generation | Service recommendation |
|---|---|---|---|
| 1 | 300 MW | None | About 100 MW firm; remainder flexible (curtail after loss of L1) or upgrade L2 |
| 2 | 600 MW | 900 MW in service | Firm while generator available; curtail or upgrade for generator-out |
| 3 | 900 MW | 900 MW in service | Firm only with upgrades or automatic curtailment on generator trip |
How Keentel Engineering helps here. Keentel produces phase-by-phase service maps that show what each phase can energize, when, and under which conditions — the information clients need to sequence construction, procurement and financing.
22. Protection and substation design at a shared POI
When load and generation share a substation, the physical design must reflect the study results.
22.1 Bus configuration
A breaker-and-a-half or double-breaker double-bus arrangement at 345 kV or 500 kV allows a breaker or bus section to be removed from service without disconnecting either project, and limits the number of single events (TPL-001 P2) that separate load and generation unevenly. A ring bus may be adequate for smaller projects but should be checked for the P2 and P4 events in Section 6. Keentel's guides on substation configurations and on AIS versus GIS discuss the trade-offs.
22.2 Protection coordination
- Transformer and feeder protection for the load side must coordinate with the generator's protection so that a load-side fault does not trip the generator, and vice versa. Keentel's guides to 87T and restricted ground fault protection, and to transformer overcurrent staging, cover the elements involved.
- Reverse power and export limits. If the service is non-export or limited-export, protection or control must enforce it. Keentel's reverse power protection guide covers the options.
- Load curtailment and runback schemes. Automatic schemes that curtail load when the generator trips, or run back generation when the load trips, are remedial action schemes in all but name. Where they affect the bulk electric system, they may need to meet NERC PRC-012 requirements for remedial action schemes and be reviewed by the reliability coordinator.
- Disturbance monitoring. Both the load and the generation should have high-resolution recording at the POI. For inverter-based generation, PRC-028-1 now requires it; for large loads, it is good practice and is increasingly expected by transmission owners.
22.3 Metering and telemetry
Separate revenue metering for the load and the generation, even behind a shared POI, is essential for settlement, accreditation and dispute resolution. Real-time telemetry to the transmission operator should include both, so that operators can see what the net flow hides.
Keentel Study Spotlight — Shared-POI substation design. Keentel designs shared POI substations, protection and control, curtailment and runback schemes and metering from 4 kV to 765 kV, and checks each design against the study conditions that produced it.
23. Operations after energization
A joint study is a planning tool; operating the paired facility is another task.
- Operating procedures. The transmission operator needs procedures that say what happens when the generator is out for maintenance, when a curtailment is called and how the load returns after a transfer to backup.
- Outage coordination. Generator maintenance should be scheduled with the transmission operator in light of the generator-out study results; in some cases, maintenance may be limited to seasons with lower load.
- Model validation. After the first disturbances, recorded data should be compared with the planning models. Keentel's MOD-033 and MOD-026 guides describe how validation works for generators; the same approach applies to large loads.
- NERC registration. Generation above the registration thresholds brings Generator Owner and Generator Operator obligations, including PRC-024 or PRC-029 ride-through, PRC-019 coordination, MOD-025 and MOD-026 testing and PRC-005 maintenance. Keentel's NERC compliance services guide summarizes them. Large-load registration under NERC is under development, and owners should expect new obligations.
How Keentel Engineering helps here. Keentel writes operating procedures for paired facilities, validates models against event data, and supports NERC registration and compliance for the generation side — so that the facility keeps operating the way it was studied.
24. A joint study from start to finish
The sections above describe the pieces. This section walks through how Keentel assembles them into one study for a typical client: a developer proposing a 750 MW data center on a 345 kV transmission line, paired with 500 MW of solar and 250 MW / 1,000 MWh of storage at a site about 15 miles away on a different 345 kV substation, plus 120 MW of on-site reciprocating engines for backup.
24.1 Week 1–2: scope and data
The first task is to pin down what is being studied. Keentel's scope document lists:
- Load ramp: 150 MW in year one, 450 MW in year two, 750 MW in year three, with monthly ramp curves within each year.
- Load characteristics: IT load share, cooling share, power factor at the POI, UPS topology, transfer thresholds, recovery logic and harmonic data.
- Generation: technology, size, in-service dates and reactive capability for the solar, storage and engines; which resources are intended to export to the grid and which are backup only.
- Service election under consideration: firm network service, firm plus flexible, or non-firm with curtailment.
- Study cases: the matrix from Section 5, plus phase-by-phase cases.
Missing data is flagged immediately. The most common gaps are ride-through settings ("the UPS vendor will decide later") and the load ramp ("we will be at full load on day one"), both of which change the answer.
24.2 Week 2–4: screening and case building
Keentel computes distribution factors for the data center bus and the solar and storage bus on every monitored flowgate within the study area. In this example, the screen shows that the solar and storage site relieves three of the five flowgates the data center loads, aggravates one (an export path from the solar site toward a 138 kV network) and is neutral on the fifth. That result changes the conversation: the pairing has real value, but it is not a full offset.
In parallel, Keentel builds the unified case: the RTO's latest summer and light-load base cases, the active generation cluster, other large loads with signed agreements, and the client's facilities with their models.
24.3 Week 4–8: steady-state, short-circuit and voltage
Steady-state contingency analysis runs every study case. The engines are excluded from supply because they are backup only. Results are summarized in a single table of flowgates by case, with the generator-out (solar at night, storage depleted) case clearly separated. In this example:
- At summer peak with solar producing, the pairing keeps all flowgates within limits through phase two; phase three needs one 345 kV line upgrade or flexible service.
- In the evening, with solar output gone and storage discharged after four hours, the data center depends on the grid. That case decides firm service.
- At spring light load, the solar site's export path to the 138 kV network overloads after a single contingency, regardless of the data center, because the data center is on a different substation.
Short-circuit analysis shows modest increases at the solar site and none at the data center. Voltage analysis shows that the data center needs about 120 Mvar of support at full load after the loss of one supply line; the storage inverters, 15 miles away, cannot supply it effectively, so a STATCOM or capacitor banks at the data center substation are recommended.
24.4 Week 8–12: dynamics, EMT and ride-through
Dynamic simulations test the RTO's fault list with the data center's ride-through model. With the original UPS settings, nine of the twenty-four faults studied cause the full facility to transfer to backup. With revised settings that ride through faults cleared in normal time, only one — a close-in fault with delayed clearing — causes transfer. EMT studies at the solar and storage site find no interaction issues at the existing system strength.
24.5 Week 12–14: deliverability, flexibility and results
Deliverability analysis shows that the solar and storage are deliverable except under one light-load condition, which the RTO's methodology addresses through an existing upgrade. Accredited capacity is about 210 MW against a 750 MW load. An hourly flexible-service analysis estimates that, without upgrades, the data center would need curtailment in about 600 hours per year at full build, mostly on summer evenings.
24.6 The deliverable
The final report gives the client four options with costs and schedules: full firm service with upgrades; firm service to 450 MW with flexible service above; firm service to 450 MW with a larger battery at the data center site to cover evening peaks; and full flexible service with on-site generation expanded to cover curtailment hours. The client chooses the third option, which avoids the largest upgrade and shortens energization of phase three by about two years.
Keentel Study Spotlight — Options, not just violations. A study that only lists violations leaves the client to design the solution. Keentel's joint studies end with costed options that combine upgrades, flexible service, storage and reactive support, so the client can choose with the trade-offs in view.
25. Reading a joint study report
Whether a study is performed by an RTO, a transmission owner or a consultant, clients should check a joint study report for the following:
| What to look for | Why it matters |
|---|---|
| Base case name, revision and date | Confirms which future grid was studied |
| List of projects included and excluded, with reasons | Shows whether both queues and other large loads were modeled consistently |
| Dispatch and load scaling method for each case | Explains why flows move as they do |
| Generator-out and load-out results | Determines firm service and export limits |
| Light-load and phased results | Often decides upgrades and interim service |
| Contingency list and TPL-001 events tested | Confirms the scope of reliability testing |
| Short-circuit and breaker duty results | Identifies hidden cost and schedule items |
| Dynamic and EMT results, including load ride-through | Shows whether the facility stays connected and whether interactions exist |
| Upgrade list with cost, schedule and allocation basis | Supports commercial decisions |
| Curtailment hours and depth for flexible service | Quantifies the cost of flexibility |
| Assumptions and limitations | Shows what could change the answer |
If any of these are missing or unclear, ask. Results built on undocumented assumptions are difficult to defend in an agreement negotiation or a regulatory proceeding.
26. Negotiating service with study results in hand
Joint study results are ultimately used to negotiate service agreements and interconnection agreements. Keentel's experience suggests three principles:
- Tie service terms to study conditions. If firm service depends on the generator being available, the agreement should say so, with a defined curtailment obligation when it is not.
- Make curtailment measurable. Flexible service should define the triggering constraint, the notice period, the maximum depth and duration, and how compliance is metered.
- Plan for change. Base cases, queues and rules will change. Agreements should define when a restudy is triggered and how results flow into service terms.
How Keentel Engineering helps here. Keentel prepares technical exhibits for service and interconnection agreements — one-lines, protection and curtailment scheme descriptions, operating limits and study summaries — and supports clients in technical discussions with transmission owners and RTOs.
27. Alternatives to traditional network upgrades
When a joint study identifies overloads, the default remedy is a line rebuild or a new transformer with a multi-year schedule. Before accepting that, Keentel evaluates faster and cheaper alternatives:
| Alternative | How it helps | Typical considerations |
|---|---|---|
| Ambient-adjusted and dynamic line ratings | Raises line ratings when weather allows; FERC Order No. 881 required ambient-adjusted ratings | Gains are largest in cool or windy conditions, not always at the binding hour |
| Reconductoring with advanced conductors | Increases line capacity on existing structures | Structure loading, clearances and outage windows |
| Series compensation or power flow control | Redirects flow away from overloaded paths | Subsynchronous resonance and protection impacts; see Keentel's SSSC guide |
| Topology optimization | Opens or closes circuits to relieve constraints | Operating procedures and reliability coordinator acceptance |
| Remedial action schemes | Automatically curtail load or run back generation after a contingency | PRC-012 requirements; reliability coordinator review |
| On-site storage | Covers generator-out or evening peaks; smooths load swings | Sizing for duration and degradation; NFPA 855 and UL 9540 |
| Flexible or non-firm service | Avoids upgrades for rare constraint hours | Requires hourly curtailment analysis and contractual clarity |
Several of these can be combined. In the PJM case study, a battery, a curtailment scheme and two breaker replacements together replaced a multi-year 230 kV rebuild for the first phases of the campus.
Keentel Study Spotlight — Upgrade alternatives analysis. For each overload identified in a joint study, Keentel evaluates at least two alternatives to a conventional rebuild, with cost, schedule and the operating constraints each one brings. Clients often find that the critical-path upgrade can be deferred or avoided for early phases.
28. Co-location configurations compared

Co-location is not one arrangement. The engineering implications differ for each configuration:
| Configuration | Grid service to the load | Generator sells to grid? | Main study questions |
|---|---|---|---|
| Fully islanded (no grid connection for the load) | None | Possibly, through a separate POI | Load reliability depends entirely on on-site supply; no grid study for the load, but the generator's grid exports still need study |
| Behind the meter, non-export | Backup only, or none | No | What the grid must supply when the generator is out; reverse power and export limiting |
| Behind the meter, partial export | Partial | Yes, above load | Export path with load off; generator-out case |
| Front of meter, same POI | Full or partial network service | Yes | All joint study cases; deliverability; cost allocation |
| Same zone, different POIs | Full network service | Yes | Distribution factors on every flowgate; light-load exports; accreditation |
FERC's December 2025 order on PJM co-location reflects the same idea: the right transmission service depends on how much the load actually relies on the grid. A joint study answers that question with numbers.
29. Joint studies outside the organized markets
Much of the debate about large loads focuses on PJM, MISO, SPP and ERCOT, but a large share of new data center and industrial load is arriving in regions served by vertically integrated utilities in the Southeast and the West, outside RTO markets. The engineering principles are identical; the process differs.
- Integrated resource planning. In non-RTO regions, the utility typically plans generation and transmission together through an integrated resource plan approved by the state commission. A large load is often served by new utility-owned or contracted generation, so the load and its supply are planned jointly by default — but not always studied in the same transmission case on the same schedule.
- Large-load tariffs. Many utilities have adopted or proposed large-load tariffs with minimum contract terms, minimum demand charges, collateral and exit fees, designed to protect existing customers if a large load leaves early or never materializes.
- Transmission service under the OATT. Generators still interconnect under the utility's FERC-approved open access transmission tariff and its Order No. 2023 cluster process. Large loads are usually studied as retail load additions under state jurisdiction. The two processes may use different cases.
- Regional planning. Utilities participate in regional transmission planning under FERC Order No. 1920, and large-load growth is now a major driver of regional needs.
For clients in these regions, Keentel applies the same unified-case approach: the utility's planning case, the utility's generation queue and resource plan, other committed large loads and the client's facility, studied together under the utility's planning criteria.

How Keentel Engineering helps here. Keentel supports large-load customers and utilities in non-RTO regions with joint studies, large-load tariff technical support and integrated resource plan analyses that connect load growth, generation additions and transmission needs.
Part C — Three Anonymous US Case Studies
The three case studies below are composites drawn from the kinds of projects Keentel supports. Names, locations and figures have been changed or combined, and the numbers are illustrative. They show how the principles in this guide play out in practice.
Case study 1 — A PJM data center campus with co-located gas and storage
The situation
A developer planned a 1,200 MW data center campus in the PJM region, to be built in four 300 MW phases over five years. The serving transmission owner's initial load study, performed with the load alone, identified more than $400 million of 230 kV and 500 kV upgrades with estimated in-service dates six to seven years out. To shorten that timeline, the developer proposed to build 800 MW of gas turbines and 400 MW / 1,600 MWh of battery storage at an adjacent site, connected to the same 500 kV substation, and argued that the campus would be "self-supplied."
The developer asked Keentel for an independent assessment before it committed to the generation build.
What Keentel did
Keentel obtained the transmission owner's base case under the appropriate confidentiality arrangements and built a unified study case containing PJM's latest regional model, the active generation queue cycle, other large loads with signed agreements in the area, and the client's phased load and generation. We then ran the study matrix from Section 5:
- Summer and winter peak with all phases of load and all generation in service.
- Light load with high regional renewable output.
- Each gas unit out of service in turn, and the entire gas plant out, with the full load in service.
- The full load out (transfer to backup) with all generation running.
- Interim phases at 300, 600 and 900 MW of load.
What we found
- With all generation running, the pairing removed most of the 500 kV overloads the load-only study had found. That part of the developer's argument was correct.
- With the largest gas unit out, two 230 kV lines still overloaded after single contingencies, by 112% and 118%. The campus was not self-supplied whenever a turbine was on maintenance — which, across four units, would be several weeks each year.
- With the full load out, the gas plant and battery exporting at full output overloaded the 500/230 kV transformer at the shared substation after a single contingency. The project needed either an export limit or a runback scheme.
- Short-circuit duty at the 500 kV substation rose by about 18%, pushing two existing breakers above 95% of their interrupting rating.
- Ride-through. The client's UPS design transferred to batteries when voltage fell below 85% for more than 50 milliseconds — a setting that, in Keentel's dynamic simulations, would have dropped the campus for most nearby 500 kV faults.
What changed
- The client elected a hybrid service: firm network service for the first 600 MW (sized to survive the generator-out case with modest upgrades) and non-firm service for the remainder, backed by an automatic load curtailment scheme armed when gas units are unavailable.
- The battery was sized so that a turbine trip could be covered for long enough for the curtailment scheme to act gracefully, without dropping servers.
- A runback scheme limits export when the campus load is low.
- The two breakers were replaced as part of the project.
- The UPS transfer settings were revised, in coordination with the server equipment supplier, to ride through faults cleared in normal time, and the revised behavior was modeled and submitted to the transmission owner.
The outcome
The client's first 300 MW phase was energized roughly three years earlier than the load-only study had indicated. Network upgrade costs assigned to the campus fell by about 60%. The key was not the pairing itself but the joint study that showed exactly when the pairing worked and when it did not.
Keentel Study Spotlight — Generator-out design case. In this project the generator-out case decided the size of firm service, the size of the battery and the design of the curtailment scheme. Keentel now runs it at the start of every co-location study.
Case study 2 — A 600 MW load paired with wind, solar and storage in one MISO zone
The situation
An industrial developer planned a 600 MW electrolysis and advanced manufacturing complex in a MISO local resource zone with strong wind resources. A partner proposed to build 700 MW of wind, 400 MW of solar and 300 MW of four-hour storage elsewhere in the same zone to supply the complex. The partners wanted to know whether a joint, zone-based study path — of the kind MISO's LARS proposal describes — would favor the project, and what risks a joint study would expose.
What Keentel did
Keentel screened distribution factors for the load bus and six candidate generation sites, then built a unified case using MISO's most recent planning model and the active definitive planning phase cluster. We studied:
- Summer peak, winter peak, spring light load and a high-wind autumn night.
- The load at full output, at half output and tripped.
- Each generation technology out in turn.
- Deliverability under MISO's methodology for the generation.
- Accredited capacity under the zone's seasonal accreditation.
What we found
- Site choice mattered more than portfolio size. Two of the six candidate wind sites had distribution factors of more than 40% on a 345 kV line already near its limit at light load; pairing them with the load made the export problem worse on windy nights when the electrolyzers were at half output. The other four sites relieved the same line when the load was on.
- Light load decided the upgrades. At summer peak, the pairing performed well. On a windy spring night with the load at half output, the portfolio exported more than 900 MW and overloaded two 345 kV lines after single contingencies.
- Accredited capacity was far below nameplate. The 1,400 MW portfolio accredited roughly 470 MW in summer and less in winter, short of the 600 MW load. The complex would still need capacity from the market.
- Voltage. The electrolyzers' rectifiers required significant reactive support; the storage inverters could supply it, but only if they were sized with reactive headroom.\
What changed
- The partners chose the four favorable wind sites and moved the solar closer to the load bus.
- The electrolyzer control system was designed to follow renewable output and to curtail on a signal from the plant controller when a light-load constraint was binding — an operating mode the joint study had quantified at about 400 hours per year.
- Storage inverters were upsized by about 10% for reactive capability.
- The developer contracted additional accredited capacity to cover the gap.
The outcome
A joint study path became viable because the data package was complete: phased load ramps, EMT models for the rectifiers and inverters, a reactive capability curve for the whole complex and an operating philosophy for curtailment. The partners avoided a 345 kV rebuild that the original site selection would have triggered.
Keentel Study Spotlight — Light-load joint analysis. For load paired with wind and solar, Keentel always studies the hours when the generation is high and the load or the system is low. In this case those hours, not summer peak, decided the design.
Case study 3 — A large load and new generation in a weak area of ERCOT
The situation
A computing company planned a 500 MW facility in West Texas, in an area dominated by wind and solar generation with relatively low short-circuit strength. To improve its interconnection prospects and reduce exposure to grid curtailment under Texas's 2025 large-load legislation, the company proposed to add 300 MW of solar and 200 MW / 400 MWh of storage at the same 345 kV substation, plus on-site reciprocating engines for backup.
What Keentel did
Keentel performed a pre-application study using ERCOT's planning cases, then supported the company through the transmission service provider's large-load study:
- Steady-state analysis with the full facility, with and without the solar and storage.
- System strength screening: short-circuit ratio, weighted short-circuit ratio for the cluster of inverter-based resources and composite metrics.
- EMT studies of the facility's front end, the new solar and storage, and two existing wind plants nearby.
- Ride-through simulations against ERCOT's evolving large electronic load requirements.
- An oscillation study of the computing load's workload-driven power swings.
What we found
- Steady state was not the problem. With the solar and storage at the same bus, thermal impacts were modest.
- System strength was. The weighted short-circuit ratio for the area's inverter-based resources, including the new solar and storage, fell to about 1.6. EMT studies showed a poorly damped oscillation of roughly 8 Hz between the new storage inverters and an existing wind plant's controls when the computing load stepped by 100 MW.
- Workload swings. Training workloads produced load changes of up to 150 MW within two seconds. Without smoothing, these swings excited the oscillation and moved the POI voltage by more than 2%.
- Ride-through. The facility's original design transferred to backup on faults that the wider system was designed to ride through, which would have removed 500 MW of load at the worst moment for a weak system.
What changed
- The storage was configured with grid-forming controls and dedicated headroom to smooth workload swings, limiting the facility's net ramp to 20 MW per second at the POI.
- The existing wind plant's owner agreed to a control parameter update, verified in EMT, that removed the oscillation.
- The facility's UPS transfer logic was revised to ride through the voltage profile in ERCOT's requirements.
- The reciprocating engines were configured to support a staged return of load after any transfer, rather than an instantaneous step.
The outcome
The facility connected with flexible service and a curtailment arrangement consistent with Texas requirements. Most importantly, the joint EMT study found an oscillation that neither the load study nor the generation study alone would have revealed, because it required both projects — and an existing neighbor — in the same model.
Keentel Study Spotlight — Joint EMT study. When large power-electronic loads and inverter-based generation share a weak area, Keentel models them together in EMT with their neighbors. The interactions that matter often involve three or more parties.
Part D — 30-Question Technical FAQ
1. What is a joint large-load and generation study?
A joint study evaluates a large load and one or more generation projects in the same study case, at the same time, under the same assumptions. Instead of studying the generator in the interconnection cluster and the load in a separate transmission service study, the planner adds both to one model of the future grid and tests every relevant load level, dispatch and contingency. The study identifies where the two projects relieve each other, where they aggravate each other and where neither matters, and it produces one set of network upgrades and one cost allocation. PJM's Fast Energization proposal and MISO's Large Load Addition Resource Study are two formal versions of this idea, but the engineering approach applies anywhere load and generation arrive in the same area.
2. Why can't I just net the megawatts of my load and my generator?
Because transmission flows depend on where power enters and leaves the network, not on totals. A load and a generator cancel on a given line only if they have the same distribution factor on that line — which in practice means they are at the same bus — and only while both are operating at the same output. In Keentel's worked example, 900 MW of load and 900 MW of generation at two buses in the same zone relieved the West-side lines but still overloaded two 345 kV lines after single contingencies, to 150% of rating. And if a co-located generator trips while the load stays on, the grid sees the full load. Netting is a useful first impression; it is never a study result.
3. What is PJM's Fast Energization proposal?
Fast Energization is PJM's proposal, filed at FERC on November 16, 2026 (Docket ER27-531), to study generation interconnection and large-load transmission service jointly. Under existing practice, generators go through PJM's cluster process and large loads go through a separate load-study path with the transmission owner, on different schedules and assumptions. The proposal would combine them and target roughly one year to results instead of about two. Public reporting indicates the filing also addresses cost transparency for states and ride-through expectations for large loads. Because the filing is new, eligibility details, deposits and timelines may change through FERC review; Keentel recommends confirming the accepted tariff language before planning around it.
4. What is MISO's LARS?
The Large Load Addition Resource Study (LARS) is MISO's proposal to study a large load above 200 MW together with new generation located in the same local resource zone, with a 120-day study target. It builds on MISO's experience with the Expedited Resource Addition Study (ERAS), which FERC accepted in July 2025 to fast-track generation needed for resource adequacy. LARS links load additions directly to the resources that will serve them in the same zone, which fits MISO's zonal resource adequacy construct. A 120-day study is only achievable with complete data at submission: load ramps, models, one-lines and protection details.
5. Why did FERC issue show cause orders on large loads?
In June 2026, FERC issued orders under Section 206 of the Federal Power Act to all six RTOs and ISOs it regulates, directing each to show that its existing rules for integrating large loads are just and reasonable or to propose reforms. Public summaries describe a focus on speeding up integration, enabling flexibility, cost transparency and protecting existing customers from bearing costs caused by new large loads. Responses were due November 16, 2026. The orders followed the Department of Energy's October 2025 directive under Section 403 asking FERC to consider rules for large-load interconnection. The responses — including PJM's Fast Energization filing — will shape large-load processes in 2027.
6. What did FERC decide about co-location in PJM?
In December 2025, FERC directed PJM to revise its tariff to give co-located loads clear transmission service options, rather than requiring every co-located load to take full network service or none. Public summaries describe three new service options, including non-firm options, and requirements to clarify behind-the-meter generation rules. This followed FERC's November 2024 rejection of an amended interconnection agreement that would have expanded co-located load at an existing nuclear plant. The engineering message is that co-location is a transmission service question: the grid must be studied for the conditions under which it actually serves the load.
7. What is the "generator-out" case and why does it matter so much?
It is the study condition in which the paired generator is unavailable — on planned maintenance or after a forced outage — while the large load remains in service. It matters because it is the condition that determines whether the load needs firm grid service. If the transmission system cannot serve the full load with the generator out, the project must choose among upgrades, automatic load curtailment when the generator is out, or non-firm service. In Keentel's experience, it is the case most often left out of co-location proposals, and it frequently decides the size of firm service and of on-site storage.
8. What is the "load-out" case?
The opposite condition: the large load trips or transfers to its backup power while the paired generation keeps running. The generation then exports its full output into the grid through a POI that may have been sized for net-zero flow. Data centers make this case realistic, because they transfer to UPS and on-site generation during voltage disturbances. A joint study should test whether the POI transformer and outlet lines can carry the full export after a contingency, and if not, specify an export limit or an automatic runback scheme.
9. Which load levels and dispatch patterns should a joint study cover?
At minimum: summer peak, winter peak, a shoulder or light-load case with high renewable output, the generator-out case and the load-out case, plus interim phases if the load ramps over several years. Each should be studied with the RTO's standard dispatch and with the specified pairing. Light-load cases are especially important when the generation is wind or solar, because export-driven overloads appear when the grid's own load is low. Keentel's case studies show that the light-load case, not peak, often decides upgrades for renewable-paired loads.
10. What distribution factor thresholds do RTOs use?
Each RTO sets its own. PJM's generator deliverability procedures have long applied a distribution factor cutoff of about 5% together with megawatt-impact thresholds, and MISO applies distribution factor and megawatt-impact criteria in its definitive planning studies. The thresholds differ between generation and load studies and between thermal and deliverability tests, and they are revised from time to time. Keentel confirms the values in the current business practice manuals for every study, because a project just above or below a threshold may gain or lose an upgrade assignment.
11. How do TPL-001 planning events apply to paired projects?
TPL-001-5.1 defines the planning events used in every transmission study, from P0 (system normal) to P7 (common-structure and multiple contingencies). For paired load and generation, the important ones are P1 (loss of the generator, the load transformer or a supply line), P2 and P4 (bus and breaker events at a shared POI), P3 and P6 (overlapping outages, such as generator maintenance followed by a line trip) and P7 (loss of a double-circuit tower carrying both supplies). The study should report each result against the performance requirement it tests, and be explicit about which load is firm and which is curtailable.
12. Does adding generation near a large load increase short-circuit duty?
Synchronous generation does, substantially. In Keentel's example, a 900 MVA gas plant raised the fault level at a 345 kV POI from about 15.1 kA to about 19.8 kA, enough to require breaker checks at the POI and nearby substations. Inverter-based generation adds much less fault current, about 1.0–1.2 per unit of its rating. Data center loads add little or none. A joint study should run short-circuit analysis for every pairing option, because breaker replacements can add cost and schedule.
13. Can co-located generation fix a weak-grid problem?
Synchronous generation and synchronous condensers increase system strength. Inverter-based generation generally does not, in the classical sense, although grid-forming inverters can provide some of the stabilizing behavior weak grids need. Large power-electronic loads add to the challenge. When several inverter-based resources and power-electronic loads share a weak area, simple short-circuit ratios are not enough; weighted or composite metrics and EMT studies are needed. Keentel's system strength guide explains the metrics and when to move to EMT.
14. Why are data center loads a reliability concern?
Because they can disappear and return quickly. Data center UPS systems transfer to batteries and then to on-site generation when grid voltage dips below their thresholds. NERC's incident review of a July 2024 event in Virginia described about 1,500 MW of data center load lost after a transmission fault. In July 2026, a larger event in Northern Virginia, reported at roughly 3 to 4 GW, prompted reviews by PJM and Dominion Energy. Sudden loss of that much load causes overfrequency and high voltage, and the return of the load must be managed. NERC, PJM and ERCOT have moved toward ride-through requirements for large loads.
15. What ride-through requirements apply to large loads?
They are emerging. ERCOT has developed large electronic load ride-through requirements through NOGRR 282. PJM's November 2026 filing reportedly includes ride-through expectations for large loads. NERC has issued alerts on large loads and is developing further guidance. Unlike IEEE 2800 and NERC PRC-029-1 for inverter-based generation, there is not yet a single national standard for large-load ride-through. Keentel recommends designing new facilities to ride through faults cleared in normal time on the transmission system, and documenting the UPS transfer logic and recovery behavior in the planning model.
16. What models does a large load need to provide?
Expect requests for a load ramp by phase, load composition, power factor and reactive capability, harmonic emissions, a positive-sequence dynamic model that represents ride-through, transfer and recovery, and an EMT model or data to build one for weak-grid studies. MOD-032-2 has strengthened the expectation that load data used in planning models be accurate and complete. Standard composite load models were not designed for data centers, so custom or user-written models are often needed until standard models mature.
17. Do AI workloads create oscillations on the grid?
Large AI training jobs can synchronize power consumption across thousands of processors, producing load swings of tens to hundreds of megawatts over seconds, sometimes repeating periodically. Grid operators and NERC have identified rapid fluctuations and forced oscillations from large computing loads as an emerging risk. Where these loads share an area with inverter-based generation, their swings can interact with plant controllers. Mitigations include on-site storage to smooth demand, ramp-rate limits in the load's power management and oscillation monitoring. Keentel's ERCOT case study shows how a joint EMT study can reveal such an interaction.
18. How does deliverability differ from a thermal study?
A thermal study asks whether the network can carry the flows created by a specific condition. A deliverability study asks whether a generator's output can reach load across the system under stressed conditions defined by the RTO, which is a precondition for counting the generator as capacity. A generator studied only for energy service may run and serve its co-located load but not count for capacity. For a large load relying on paired generation, deliverability determines whether the pairing helps meet the region's resource adequacy needs.
19. Why is accredited capacity lower than nameplate?
Because RTOs now accredit capacity using effective load carrying capability (ELCC) or similar methods that reflect each resource's contribution during the hours of greatest risk. Solar contributes little in winter evenings, wind varies, storage is limited by duration and thermal units have forced outages and fuel risks. In Keentel's example, a 1,600 MW portfolio of gas, solar, wind and storage accredited only 735 MW against a 900 MW load. ELCC values vary by market, season and year; always use the current published values.
20. What is flexible or non-firm load service?
Service under which the load agrees to be curtailed under defined conditions — usually when a specific transmission constraint binds or during emergencies — in exchange for earlier connection or lower upgrade costs. FERC's December 2025 co-location order, SPP's High Impact Large Load process and Texas's 2025 legislation all include forms of curtailable or provisional service. The value depends on how often and how deeply curtailment will occur, which must be calculated hour by hour.
21. How often would a flexible load really be curtailed?
It depends entirely on the constraint and the load's distribution factor on it. In Keentel's worked example, a 900 MW load with a 32% distribution factor on a 1,000 MW flowgate would need curtailment in about 1,010 hours per year, up to 544 MW in the worst hour, but only about 1.6% of its annual energy. Industry research has estimated that tens of gigawatts of flexible load could connect with curtailment of well under 1% of annual energy, but individual projects can differ widely. The only reliable answer is an hourly study of the binding constraints.
22. How are shared network upgrade costs allocated between a load and a generator?
Most RTOs allocate shared upgrade costs among cluster participants in proportion to their megawatt impact on the overloaded facility — size multiplied by distribution factor. Load-driven upgrades have historically been recovered more through transmission rates, but the trend, including the FERC show cause orders and proposed federal legislation, is toward large loads bearing more of the costs they cause. Joint studies improve allocation accuracy because every project's contribution is measured in the same case. In Keentel's example, a $180 million upgrade split about 70% to the data center, 22% to solar plus storage and 9% to wind.
23. What does "the same future grid" mean in practice?
One study case containing the same topology, planned projects, retirements, generation queue, large-load queue, load forecast, dispatch rules, contingency list and compatible dynamic and EMT models for every project. When generation and load are studied in different cases, they rest on different assumptions about each other and about the rest of the system, and their results disagree. Keentel maintains a model management log so that every result can be traced to the exact case and assumptions that produced it.
24. How long does a joint study take?
The target timelines in the new proposals range from 120 days (MISO LARS) to about one year (PJM Fast Energization), compared with roughly two years for separate processes today. Independent pre-application studies by a consultant can often be completed in six to twelve weeks once base cases are available. Study time is only part of the schedule: network upgrades often take five to eight years, and long-lead equipment such as large power transformers and high-voltage breakers can take several years to procure.
25. How does ERCOT handle large loads?
ERCOT has a dedicated large-load interconnection process for loads at or above 75 MW. Texas Senate Bill 6, enacted in 2025, added requirements for large loads, including provisions on interconnection standards, cost responsibility and curtailment in emergencies. In 2026 ERCOT approved a batch study approach, often called "Batch Zero," that studies large loads in groups rather than individually, and developed ride-through requirements for large electronic loads. Keentel's ERCOT Batch Zero guide covers the process in more detail.
26. How does SPP handle large loads?
SPP developed a High Impact Large Load (HILL) process and an associated generation pathway, which FERC accepted in January 2026. The process provides a dedicated study path for large loads, including a provisional service option, and recognizes generation paired with large loads. SPP's Expedited Resource Addition Study for generation was also accepted by FERC. As with other RTOs, details are evolving; confirm current tariff provisions before relying on them.
27. What NERC obligations does a paired facility have?
The generation side brings the usual Generator Owner and Generator Operator obligations above NERC's registration thresholds, including ride-through under PRC-024 or PRC-029, coordination under PRC-019, testing under MOD-025 and MOD-026, disturbance monitoring under PRC-028 for inverter-based resources, and protection system maintenance under PRC-005. Automatic schemes that curtail load or run back generation to protect the bulk electric system may need to meet PRC-012 requirements for remedial action schemes. NERC is developing how large loads themselves will be registered and what obligations they will carry. Keentel's NERC compliance services guide summarizes the generation-side requirements.
28. What information should a developer gather before applying?
A credible phased load ramp; site layout and one-line diagram; POI options with distribution factor screening; load composition and power factor; ride-through and transfer settings; harmonic data; positive-sequence and EMT models or the data to build them; the generation mix, technology, size and in-service dates; reactive capability of the combined facility; proposed protection, curtailment and runback schemes; and a decision on firm versus flexible service. Fast-track processes reward complete applications and penalize deficiencies.
29. Can a joint study reduce my network upgrade costs?
Often, yes — but not always, and not by netting. In Keentel's PJM case study, a joint study reduced assigned upgrades by about 60% by crediting relief that was real and pairing it with curtailment for the conditions when it was not. In other cases a joint study reveals overloads, such as light-load export problems or generator-out conditions, that separate studies missed, which can increase costs but avoid unpleasant surprises later. The value of a joint study is an accurate answer, delivered early enough to change the design.
30. How can Keentel Engineering help with a joint load and generation project?
Keentel performs independent joint studies — distribution factor screening, steady-state contingency analysis, short-circuit, stability, EMT, deliverability, accreditation and flexible-service curtailment analysis — using the transmission provider's base cases. We build unified study cases, prepare complete application data packages, review and replicate RTO and transmission owner studies, design shared POI substations, protection and curtailment schemes from 4 kV to 765 kV, and support NERC compliance for the generation side. Contact us at (813) 389-7871, contact\@keentelengineering.com or calendly.com/keentel-engineering/15min.
How Keentel Engineering Helps
Keentel Engineering supports large-load developers, independent power producers, utilities and transmission owners through every stage of joint load and generation interconnection, from site screening to energization and compliance, from 4 kV to 765 kV.
| Service | What Keentel delivers | Outcome |
|---|---|---|
| Site and POI screening | PTDF/DFAX screening of load and generation buses against RTO base cases | Better sites chosen before land and equipment are committed |
| Unified study case | One case with both queues, the latest RTO model, client models and project-specific contingencies | Results that describe the same future grid |
| Steady-state joint studies | N-0, N-1 and TPL-001 P1–P7 analysis across peak, light-load, generator-out, load-out and phased cases | Clear list of upgrades and firm-service limits |
| Short-circuit and breaker duty | Fault studies and breaker evaluation for each pairing option | No surprise breaker replacements |
| System strength and EMT | SCR, weighted and composite metrics; PSCAD EMT studies of loads, inverters and neighbors | Weak-grid and oscillation risks found before energization |
| Dynamic stability and ride-through | Large-load ride-through, transfer and recovery modeling; generator response | Ride-through settings that keep the facility online |
| Voltage and reactive power | P-V and Q-V analysis; STATCOM, SVC and capacitor sizing | Voltage support that survives the generator-out case |
| Deliverability and accreditation | RTO deliverability methods and ELCC-based accreditation estimates | Honest view of capacity value |
| Flexible-service analysis | Hourly curtailment frequency and depth by phase | Data to size storage and negotiate service terms |
| Cost allocation and alternatives | Replication of allocations; reconductoring, advanced conductors, series compensation and flexible alternatives | Lower-cost paths to service |
| Application and data packages | Load ramps, models, one-lines, protection and ride-through data for PJM, MISO, SPP, ERCOT and non-RTO utilities | Complete applications that keep fast-track schedules |
| Study review and replication | Independent review of RTO and transmission owner studies | Errors caught and challenged with engineering evidence |
| Substation and protection design | Shared-POI substations, protection, curtailment and runback schemes, metering | Designs that match the study assumptions |
| NERC compliance | PRC-024, PRC-029, PRC-019, PRC-005, PRC-012, PRC-028, MOD-025, MOD-026, MOD-032 support | A facility that stays compliant after energization |
| Owner's engineer | Technical due diligence, design review, construction oversight and commissioning witness | Confidence for owners, lenders and investors |
Why Clients Choose Keentel
- Load and generation expertise in one team. We study generators, inverter-based resources, data centers and industrial loads, so a joint study does not fall between two specialties.
- Every study type under one roof. Steady-state, short-circuit, stability, EMT, harmonics and deliverability use one case and one team.
- Independent. Keentel does not sell generation, storage, equipment or data center capacity. Our recommendations follow the engineering.
- Practical design experience. We design the substations, protection and schemes our studies call for, from 4 kV to 765 kV.
- US practice. NERC, FERC, IEEE, NESC and RTO tariff requirements are built into every deliverable, across PJM, MISO, SPP, ERCOT, CAISO, NYISO, ISO-NE and non-RTO utilities.
- Licensed professional engineering. Keentel is a Florida-registered engineering firm (Firm Registration No. 36853) with offices in Tampa, Austin, Sacramento and Baltimore, supporting projects nationwide.
- Credentials. NSPE member firm, D-U-N-S registered, IEEE Senior Member leadership and BBB Accredited Business with an A+ rating.
Talk to Keentel Engineering
Planning a data center campus with its own generation, pairing a generation portfolio with a large-load customer, or responding to a large-load request as a transmission owner? Keentel can tell you what the grid really sees — before you commit.
- Phone: (813) 389-7871
- Email: contact@keentelengineering.com
- Book a 15-minute call: calendly.com/keentel-engineering/15min
- Web: keentelengineering.com
References
- FERC, show cause orders under Federal Power Act Section 206 to six RTOs/ISOs on large-load integration, June 18, 2026, and FERC materials on cost transparency and customer protection in those orders.
- PJM Interconnection, filing in response to FERC's large-load show cause order including the Fast Energization proposal, Docket ER27-531-000, November 16, 2026.
- PJM Board of Managers, decisional letter on the Critical Issue Fast Path process for large-load additions, January 16, 2026.
- PJM and Dominion Energy reviews of the July 22, 2026 Northern Virginia large-load transfer event, 2026.
- MISO, Large Load Addition Resource Study (LARS) proposal and Large Load Working Group materials, 2026; filing at FERC, fall 2026.
- FERC, order accepting MISO's Expedited Resource Addition Study (ERAS), Docket ER25-1674, July 2025.
- FERC, order accepting SPP's High Impact Large Load (HILL) tariff revisions, Docket ER26-247, January 2026.
- FERC, order directing PJM to establish transmission service options for co-located load, December 2025.
- FERC, order rejecting an amended interconnection service agreement for expanded co-located load in PJM, November 2024.
- US Department of Energy, letter directing FERC under Federal Power Act Section 403 to consider large-load interconnection rules, October 2025.
- FERC Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements, July 2023.
- NERC, Incident Review: Large Load Loss (July 2024 event), 2025; NERC Level 2 Alert on Large Loads, 2025.
- NERC, 2025 Long-Term Reliability Assessment, December 2025.
- NERC Reliability Standards TPL-001-5.1, MOD-032-2, MOD-026, MOD-033, PRC-005, PRC-012, PRC-019, PRC-024, PRC-028 and PRC-029.
- ERCOT, large-load interconnection process and batch study materials, 2026; NOGRR 282, Large Electronic Load Ride-Through Requirements, 2025–2026.
- Texas Senate Bill 6, 89th Legislature, 2025.
- Lawrence Berkeley National Laboratory, Queued Up: 2025 Edition (December 2025) and Queued Up: 2026 Edition (2026).
- Duke University Nicholas Institute, Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems, February 2025.
- IEEE Std 519-2022, Harmonic Control in Electric Power Systems; IEEE Std 2800-2022; IEEE Std C37.010.
- Wood, A. J., Wollenberg, B. F. and Sheblé, G. B., Power Generation, Operation, and Control, 3rd ed., Wiley, 2014 (distribution factors and DC power flow).
Related Keentel guides
- Cluster Interconnection Studies
- A 1 GW Data Center Explained
- Data Center Load Calculations
- Grid Flexibility, VPPs and Storage
- Resource Adequacy and Transmission Planning
- TPL-001-5.1 Transmission Planning
- MOD-032-2 Modeling Data
- System Strength Metrics
- Temporary vs Transient Overvoltages
- NERC Compliance Services Guide
- ERCOT Batch Zero Guide
Disclaimer
This article is provided by Keentel Engineering for general technical education. It is not legal, regulatory, financial or engineering advice for any specific project. Large-load and interconnection rules are changing rapidly: the filings, orders and processes described here are summarized from public documents and reporting available in November 2026, and several were pending before FERC or subject to change. Always confirm current tariff provisions, business practice manuals and orders before making decisions. Worked examples use a synthetic network and illustrative values; real results depend on the transmission provider's base cases, assumptions and criteria. Case studies are anonymous composites. Keentel Engineering accepts no liability for decisions made on the basis of this article without a project-specific study.
© 2026 Keentel Engineering. All rights reserved. Written by Keentel Engineering.
| Office | Address | Phone |
|---|---|---|
| Head Office — Tampa | 400 N Ashley Dr STE #2600, Tampa FL 33602 | (813) 389-7871 |
| Austin | 5900 Balcones Drive STE 100, Austin TX 78731 | (512) 591-0752 |
| Sacramento | 1401 21st St Ste R, Sacramento CA 95811 | (916) 913-4524 |
| Baltimore | 306 W Redwood St STE 200, Baltimore MD 21201 | (410) 225-2181 |

About the Author:
Sandip "Sonny" R. Patel, P.E.
IEEE Senior Member · Founder & CEO, Keentel Engineering
In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.
For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.
His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.
Services

Let's Discuss Your Project
Let's book a call to discuss your electrical engineering project that we can help you with.

About the Author:
Sandip "Sonny" R. Patel, P.E.
IEEE Senior Member · Founder & CEO, Keentel Engineering
In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.
For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.
Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.
His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.
Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.