A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.
Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime
The three operating regions you have to design to
| Device | Output vs voltage | Response | Best suited to | Main limitations |
|---|---|---|---|---|
| Mechanically switched capacitor or reactor | Proportional to voltage squared | Seconds; discrete steps; limited switching operations per day | Steady-state reactive supply, voltage profile, loss reduction | No dynamic capability; step voltage change on switching; capability collapses when most needed |
| Static var compensator | Capacitive branches proportional to voltage squared | A few cycles; continuously controllable | Continuous control where cost matters and deep voltage support is not the driver | Square-law capability loss; harmonic filters are part of the plant and interact with the network |
| STATCOM | Approximately proportional to voltage — constant current capability | One to two cycles closed loop; converter response faster still | Voltage stability margin, weak interconnections, fast disturbance recovery, flicker and unbalance compensation | Higher capital cost; converter losses; adds a converter and its control dynamics to the network |
| Synchronous condenser | Governed by machine capability and excitation | Excitation response in the hundreds of milliseconds; inherent inertial response instantaneous | System strength and inertia, short-circuit contribution, black start support | Rotating plant with maintenance and losses; slower controlled response than a converter |
| STATCOM with energy storage | Reactive as a STATCOM, plus real power within the storage rating | As STATCOM for reactive; real power limited by storage | Where a real power deficiency is part of the problem | Cost and complexity of the storage; different failure and maintenance profile |
| Service area | What we do for SST campuses | Typical deliverables |
|---|---|---|
| Grid interconnection | Site screening, large-load applications, independent studies, utility and RTO coordination in ERCOT, NYISO, PJM and other markets | Screening reports, application data packages, load flow, contingency and stability studies, study review memos |
| EMT modeling | Model requirements, vendor model review, campus aggregation, ride-through, weak-grid, control interaction and load-oscillation studies | EMT model specifications, model acceptance reports, PSCAD study reports, SCR screening |
| MV/MVDC system studies | AC and DC short-circuit, DC protection philosophy, AC protection, arc flash, grounding, insulation coordination | Study reports, protection philosophy documents, settings files, arc flash labels, interface control documents |
| Power quality | Emission requirements, frequency scans, IEEE 519-2022 compliance, filter sizing, flicker assessment | Harmonic study reports, filter specifications, monitoring plans |
| Substation and transmission design | HV/EHV substations, MV collectors, transmission lines, utility interface protection | Physical and electrical drawing packages, specifications, bills of material, protection and control design |
| NERC compliance | Registration and applicability, ride-through requirements, model validation, monitoring, compliance programs | Applicability assessments, compliance programs, evidence packages, model validation reports |
| Owner's engineer and QA/QC | SST, storage and substation specifications, design reviews, FAT and SAT plans and witnessing, multi-unit QA | Specifications, review comments, test plans, witness reports, due diligence reports |
| Onsite generation and BESS | Role definition and sizing, DC bus control architecture, fire and code compliance coordination, performance testing | Sizing studies, control architecture documents, specifications, test procedures |
Storage and generation
| Term | Meaning |
|---|---|
| AFE | Active front end. The actively switched AC/DC stage of an SST that connects to the MV grid and sets its grid behavior. |
| Aggregated model | A model in which many converters are represented by a smaller number of equivalent converters to make campus-scale simulation practical. |
| Arc flash | The release of energy from an electric arc fault, assessed as incident energy at a working distance to set PPE and safe work practices. |
| BESS | Battery energy storage system. |
| Blocking | Turning off all converter switches so the converter stops feeding current, used to limit DC faults. |
| Composite load model | A positive-sequence load model that combines several load types, such as motors, electronics and static loads. |
| DAB | Dual active bridge. An isolated DC/DC converter topology with active bridges on both sides of a high-frequency transformer. |
| DC-link | The internal DC capacitor bank between converter stages. |
| EMT | Electromagnetic transient simulation. Time-domain simulation with microsecond time steps, used to study fast converter and network behavior. |
| FAT | Factory acceptance test. |
| Grid-forming | A converter control mode that sets its own voltage and frequency reference rather than following the grid's, providing support to weak grids. |
| HIL | Hardware-in-the-loop testing, in which a real controller is tested against a real-time simulation. |
| IBR | Inverter-based resource. Generation or storage connected to the grid through power electronics. |
| Insulation coordination | Matching the insulation strength of equipment to the voltage stresses the system produces, with surge protection where needed. |
| ISC/IL | The ratio of available short-circuit current to maximum demand load current at the point of common coupling, used to set IEEE 519 limits. |
| ISOP | Input-series, output-parallel. A modular converter arrangement that shares a high input voltage across cells in series and combines their outputs in parallel. |
| Large load | A load large enough to affect transmission system reliability. Definitions vary, for example 75 MW and above under Texas SB 6, or loads above 20 MW in the federal rulemaking proposal. |
| LVDC | Low-voltage DC, such as 800 VDC or ±400 VDC rack distribution. |
| MFT | Medium-frequency transformer. The compact isolation transformer inside an SST, operating at kilohertz frequencies. |
| MMC | Modular multilevel converter. A converter built from many submodules with their own capacitors, producing a stepped multilevel waveform. |
| MVDC | Medium-voltage DC distribution, roughly 1 kV to 35 kV DC in common usage. |
| OE | Owner's engineer. An independent engineer representing the owner's technical interests. |
| PCC / POI | Point of common coupling / point of interconnection, where the campus connects to the utility system and where compliance is usually assessed. |
| PLL | Phase-locked loop. The control element that tracks grid voltage phase and frequency. |
| Positive-sequence model | A fundamental-frequency, balanced dynamic model used in PSS®E, PSLF and similar tools. |
| Ride-through | The ability to stay connected and keep operating during and after a grid disturbance within defined limits. |
| SAT | Site acceptance test. |
| SCR | Short-circuit ratio. Available short-circuit power divided by converter rating, a measure of grid strength. |
| SiC | Silicon carbide, a wide-bandgap semiconductor material that allows higher voltage, higher frequency switching. |
| SST | Solid-state transformer. A power electronic converter with a high-frequency isolation stage that replaces a 60 Hz transformer and rectifier chain. |
| Supraharmonics | Emissions in the 2 kHz to 150 kHz range, above the range covered by most harmonic limits. |
| TDD | Total demand distortion. Harmonic current distortion relative to maximum demand current, used in IEEE 519. |
| WSCR | Weighted short-circuit ratio. An SCR screen that accounts for several inverter-based plants sharing a network area. |
Links were current at publication (November 2026). Large-load rules, NERC actions and standards editions are changing quickly, so confirm current versions before relying on them.
Large-load reliability and NERC
- NERC Publishes Incident Review and Guidance on Voltage-Sensitive Large Load Integration, NERC
- Reliability Insights: Large Computational Load Risks Due to Voltage Sensitivity, NERC, September 2026
- NERC Seeks to Address Reliability Impacts from Large Load Integration, NERC presentation to FERC, April 2025
- NERC issues Level 3 Alert to address immediate risks data center loads pose to the grid, Renewable Energy World, May 2026
- NERC Voltage-Sensitive Loads, Keentel Engineering
Federal and state large-load rules
- FERC Docket RM26-4, Interconnection of Large Loads, FERC
- FERC Establishes Proceeding to Consider DOE Directive on Large Load Transmission Interconnection Rulemaking, McGuireWoods, October 2025
- Texas Senate Bill 6 Ushers in Major Overhaul of Large Load Interconnection and Grid Access Rules, Bracewell, July 2025
- Public Utility Commission of Texas Issues Proposed Rules for Large Load Interconnections, Foley & Lardner, March 2026
Solid-state transformers and DC data center power
- Solid State Transformer project, Open Compute Project
- Novel Solid-State Transformer Supports 800-V DC Power in AI Data Centers, Electronic Design
- How SSTs are Reshaping Data Center Infrastructure, Microchip Technology
Standards referenced (consult the publisher for the current edition)
Step 5 — options. Replacing or retrofitting the drives with active-front-end or 18-pulse units at about 5% THDi gives a TDD of about 1.5%. An active harmonic filter sized for the 5th and 7th could achieve a similar result at the facility level. A passive 5th-harmonic tuned filter would also work but must be checked for resonance with the utility system and with any future capacitors.
What this means for you.
The same drives can be compliant on a strong system and non-compliant on a weak one. Ask your utility for the maximum short-circuit current at the PCC early in design. If the ratio is below 50, plan for low-harmonic drives or filtering from the start; it is much cheaper than retrofitting.
9. Inverter-based resources: solar, storage and wind
Solar PV, battery energy storage and full-converter wind turbines use pulse-width-modulated inverters with output filters. They are generally low-distortion sources. IEEE Std 1547-2018 (distribution-connected resources) and IEEE Std 2800-2022 (transmission-connected resources) limit their current distortion — total rated-current distortion (TRD) of 5% with individual limits by order, measured against rated current rather than present output. In practice, quality inverters measure 1–3% at rated output.
Three cautions apply:
- Percentages rise at low output. At 10% of rated output a 2% distortion (of rated current) looks like 20% THD. Limits referenced to rated current, like TDD, avoid this trap.
- Inverters change the system's impedance. Plant collector cables, inverter output filters and capacitor banks add capacitance. They can create resonances near the 5th to 13th harmonics on the 34.5 kV collector or at a 138 kV, 230 kV or 345 kV point of interconnection, amplifying background distortion that the plant did not create.
- Background distortion matters. Inverters can absorb or amplify existing voltage distortion depending on their control design. Utilities increasingly require harmonic impedance studies for new plants, sometimes using electromagnetic transient (EMT) simulation.
Keentel's articles on harmonic resonance and on
weak-grid inverter stability cover these interactions in depth.
10. Data centers and other electronic facilities
Data centers are a special case because almost all their load is electronic. Points to check:
- UPS rectifiers. Double-conversion UPS units with IGBT rectifiers typically draw less than 5% THDi at rated load, rising at low load. Older six-pulse or 12-pulse thyristor UPS rectifiers may need input filters.
- Server and network power supplies. Modern units with active power factor correction have low 3rd harmonic. Legacy equipment does not. Measure a representative panel rather than assuming.
- 208Y/120 V and 415Y/240 V distribution. Check neutral current and transformer K-factor as in Sections 4 and 7.
- Generator operation. Test UPS and generator compatibility at the actual load level. Generator THDv can be three to four times the utility THDv for the same load.
- Cooling plant. Chiller, pump, fan and cooling distribution unit drives often contribute more low-order harmonics than the IT load. Specify low-harmonic drives where the facility is large relative to the utility source.
- Large-load interconnection. Utilities and grid operators now treat large data centers as high-impact loads. Harmonic studies and power quality monitoring are increasingly part of interconnection requirements, alongside ride-through and dynamic studies.
11. How a harmonic study is done
A harmonic study answers four questions: How much harmonic current will the facility inject? What voltage distortion will it cause? Will any resonance amplify it? What is the cheapest reliable fix? Keentel's typical workflow:
- Gather data. Single-line diagram; utility short-circuit data (maximum and minimum) at the PCC; utility background distortion if known; transformer impedances; cable lengths; capacitor banks and filters; drive, UPS and inverter data sheets with harmonic spectra.
- Measure existing conditions. For existing facilities, install class-compliant power quality meters at the PCC and key buses for at least one week, capturing 10-minute and 3-second data up to the 50th harmonic.
- Build the model. Represent sources as harmonic current injections and the network as frequency-dependent impedances, including transformer phase shifts that can cancel 5th and 7th harmonics between delta-delta and delta-wye units.
- Run a frequency scan. Plot driving-point impedance versus frequency at each important bus to find resonances, for all credible system configurations (tie breakers open/closed, capacitor steps in/out, generator versus utility).
- Run harmonic load flow. Calculate harmonic currents and voltages and compare them with IEEE 519 at the PCC and with equipment limits (IEEE 18 for capacitors, C57.110 for transformers) inside the facility.
- Design mitigation. Compare options for performance, cost, losses, footprint and future flexibility.
- Verify. Measure again after installation and document compliance with the statistical criteria.
12. Fixing harmonics: options compared

SCADA Architecture for Power and Process: Components, Protocols, Latency, NERC CIP & OT Security
November 25, 2026 | Blog
Part A — SCADA Architecture at a Glance
Supervisory control and data acquisition (SCADA) is the layer of software, hardware and communications that lets a small team of operators watch and steer equipment spread across a plant, a pipeline, a water system or a power grid. It gathers measurements from the field, presents them on screens, raises alarms when something drifts out of bounds, keeps a record of what happened, and sends commands back out: open this breaker, start that pump, raise this set point.
That short description hides a great deal of engineering. Every value an operator sees has passed through a sensor, a signal standard, a controller, one or more networks, a server and a display, and each step adds delay, error and a point where something can fail or be attacked. In the electric power industry the same chain also carries regulatory obligations: NERC Critical Infrastructure Protection (CIP) standards for cyber security, telemetry requirements from balancing authorities and independent system operators (ISOs), and data obligations that feed system models and event analysis.
This guide is Keentel Engineering's full treatment of SCADA architecture for both process plants and electric power systems. It explains what each component does, how data moves and how long it takes, how alarms, historians and time synchronization should be designed, how SCADA differs from a distributed control system (DCS) and an energy management system (EMS), and how to secure the whole stack against the threats that have already reached industrial control systems. Every number is worked through in fifteen examples, with US standards and US practice throughout.
Keentel's position. Keentel Engineering is an independent power engineering firm. We do not sell SCADA software, controllers or network equipment. We help utilities, independent power producers, solar, wind and battery storage owners, data center developers and industrial plants specify, design, review, test and document SCADA and substation automation systems from 4 kV to 765 kV, and we support the NERC compliance work that comes with them.
Who this guide is for
- Utility engineers and operations managers modernizing substation SCADA, distribution automation or control center systems.
- Solar, wind and battery storage owners and EPC contractors responsible for plant SCADA, plant controllers and ISO telemetry.
- Data center developers and facility engineers integrating electrical power monitoring with building and process systems.
- Industrial and water utility engineers running plant SCADA, PLC and DCS systems.
- Compliance and cyber security staff applying NERC CIP, NIST SP 800-82 and ISA/IEC 62443 to operational technology (OT).
- Owners' engineers, lenders and asset managers who need to judge whether a SCADA design is complete, maintainable and defensible.
Key facts at a glance
| Item | Value or practice | Basis |
|---|---|---|
| What SCADA is | Supervisory monitoring and control of geographically distributed equipment through remote units and a central master | IEEE C37.1-2007 (now inactive-reserved) |
| Typical utility SCADA scan rate | About 2–4 seconds for analog values; faster for status changes reported by exception | Industry practice; ISO telemetry handbooks |
| Common power-sector protocols | DNP3 (IEEE 1815), IEC 61850, Modbus, ICCP/TASE.2 between control centers | IEEE, IEC, ISO practice |
| Signal standard for field transmitters | 4–20 mA analog loop, often with HART digital overlay | Industry practice |
| OT security guide | NIST SP 800-82 Rev. 3, Guide to Operational Technology Security , September 2023 | NIST |
| Zone and conduit model | ISA/IEC 62443 series | ISA, IEC |
| Alarm management standard | ANSI/ISA-18.2-2016, Management of Alarm Systems for the Process Industries | ISA |
| HMI design standard | ANSI/ISA-101.01-2015, Human Machine Interfaces for Process Automation Systems | ISA |
| Substation time synchronization | IEEE C37.238-2017 profile of IEEE 1588 Precision Time Protocol | IEEE |
| IED cyber security capabilities | IEEE 1686-2022 | IEEE |
| NERC internal network monitoring | CIP-015-1 approved by FERC in Order No. 907, June 26, 2025 | FERC Docket RM24-7 |
| BES Cyber System impact rating | CIP-002 Attachment 1 bright-line criteria (high, medium, low) | NERC CIP-002 |
The core ideas in one table
| Idea | What it means in practice |
|---|---|
| SCADA supervises; it rarely does fast control | Closed-loop control runs in PLCs, DCS controllers, relays and plant controllers in milliseconds. SCADA sets targets and watches results on a scale of seconds. |
| Every value has a latency budget | Transducer, scan, poll, network hops and gateways add up. A design that looks fast on paper can miss a 4-second telemetry target once every hop is counted. |
| Polling and report-by-exception are different traffic patterns | A full integrity poll of a 5,000-point substation can be ten times the size of a routine exception report. Size links for the worst case, not the average. |
| Time is data | Without a common, accurate time source, sequence-of-events records cannot be trusted and event analysis becomes guesswork. |
| Alarms are a design product | An alarm system that floods operators during an upset is worse than useless. Rationalization and suppression are engineering tasks, not afterthoughts. |
| Redundancy must be tested | Duplicate servers and rings only help if failover works and common-cause failures are controlled. |
| Security is architecture, not a product | Segmentation, controlled remote access, patch and backup discipline, and monitoring inside the perimeter protect SCADA far better than any single device. |
| Power SCADA carries regulatory weight | NERC CIP, ISO telemetry rules and model data requirements turn design choices into compliance obligations. |
Fact check: common simplifications
Short explanations of SCADA circulate widely. Most get the basics right, but several points are routinely oversimplified.
| Common statement | Keentel's engineering check |
|---|---|
| "SCADA monitors and controls industrial processes in real time." | SCADA works in near-real time on a scale of seconds. The fast, closed-loop control happens in controllers and relays below it. Treating SCADA as the control loop leads to designs that fail when the network is slow or down. |
| "A SCADA system's main components are instruments, PLCs, a DCS, RTUs, a network, a server and HMIs." | A sound list, but it omits items that decide whether the system actually works: time synchronization, communication front-ends and gateways, data historians and their replicas, alarm management, backups, and the security architecture around all of it. |
| "The DCS is one component of SCADA." | A DCS is a separate class of system, built for continuous, plant-wide control within one site. It often sits beside SCADA or feeds data to it. Modern platforms blur the line, but the design priorities differ. |
| "The RTU collects data from remote locations." | True, and modern RTUs also run logic, time-stamp events, and act as gateways to protective relays and meters. In substations the "RTU" is often an automation controller polling dozens of intelligent electronic devices (IEDs). |
| "The engineering station is used for configuration and troubleshooting." | It is also one of the most dangerous assets on the network, because it can change controller logic. It needs the strongest access control and monitoring in the system. |
| "Data flows from field instruments to the operator station." | Data flows both ways. Commands travel down the same path and must be checked, authenticated where possible, and confirmed by the field device (select-before-operate in DNP3 and IEC 61850). |
| "The historian is just for trend screens." | Historians also supply compliance evidence, event reconstruction, model validation and performance testing. Storage, compression settings and time quality determine whether that evidence holds up. |
Eight findings for decision makers
1. Treat SCADA as a system of systems. Instruments, controllers, networks, servers and people each have failure modes. The architecture must be designed end to end, with a written latency, availability and security budget.
2. Separate control from supervision. Keep protection and fast control local so that loss of SCADA communications never removes protection or causes unsafe operation.
3. Design the data path for the worst day. Size links and servers for integrity polls, event floods and storm conditions, not for average traffic.
4. Synchronize time everywhere. A GPS-referenced clock with PTP or IRIG-B to every IED and controller turns event records into evidence.
5. Rationalize alarms before go-live. Every alarm should have a cause, a consequence and an operator action. Target about one alarm per ten minutes per console in steady operation.
6. Segment the network and control remote access. Use a layered architecture with a demilitarized zone (DMZ), firewalls between levels, multi-factor authentication for remote access, and monitoring inside the perimeter.
7. Map regulatory obligations at design time. NERC CIP impact rating, ISO telemetry requirements and data retention rules change the design. Find them before procurement.
8. Test everything twice. Factory acceptance testing (FAT), site acceptance testing (SAT) and point-to-point checks catch most errors. Failover, time sync and alarm behavior need their own tests.
Key terms
- SCADA — supervisory control and data acquisition: centralized monitoring and supervisory control of distributed equipment.
- HMI — human-machine interface: the operator's screens and controls.
- PLC — programmable logic controller: a rugged computer that runs discrete and sequential control logic.
- DCS — distributed control system: a plant-wide control system with distributed controllers, built for continuous processes.
- RTU — remote terminal unit: a field device that gathers data and executes commands at a remote site, often also acting as a protocol gateway.
- IED — intelligent electronic device: a microprocessor-based relay, meter, controller or similar device in a substation.
- EMS — energy management system: the control-center application suite for transmission operation, built on SCADA plus network applications such as state estimation.
- ADMS / DERMS — advanced distribution management system / distributed energy resource management system.
- Historian — a time-series database optimized for storing and retrieving process values.
- DNP3 — Distributed Network Protocol, standardized as IEEE 1815, widely used between control centers, RTUs and IEDs in North America.
- IEC 61850 — an international standard for substation and utility automation communications, including GOOSE messaging and sampled values.
- ICCP / TASE.2 — Inter-Control Center Communications Protocol, used to exchange data between utility control centers and ISOs.
- SOE — sequence of events: a time-stamped record of status changes.
- PTP — Precision Time Protocol (IEEE 1588), with the power profile IEEE C37.238.
- ESP — Electronic Security Perimeter under NERC CIP-005.
- INSM — internal network security monitoring under NERC CIP-015.
Purdue model — a reference architecture that divides industrial systems into levels from the physical process (Level 0) to the enterprise (Levels 4–5).
Part B — SCADA Architecture: The Engineering Guide
1. What SCADA actually does
At its simplest, SCADA answers three questions for an operator: what is the state of my equipment right now, what has changed, and what do I want it to do next. It answers them for equipment that is too spread out, too numerous or too dangerous to watch in person.
The functions fall into five groups:
- Data acquisition. Reading analog measurements (pressure, flow, level, voltage, current, power, temperature), status points (breaker open or closed, pump running or stopped) and counters (energy, operations) from field devices.
- Supervisory control. Sending commands and set points: open or close a breaker, start a pump, change a voltage target, raise or lower a tap changer, adjust a plant's real or reactive power.
- Presentation and alarming. Displaying the system on overview and detail screens, highlighting abnormal conditions, and raising alarms that require operator response.
- Recording. Storing values and events in a historian for trending, reporting, event analysis and compliance evidence.
- Integration. Exchanging data with other systems: business systems, maintenance systems, outage management, market and ISO systems, and neighboring control centers.
What SCADA usually does not do is run fast, closed-loop control. A flow loop that adjusts a valve every 100 milliseconds, a protective relay that trips a breaker in two cycles, or a plant controller that regulates voltage at the point of interconnection all run in local controllers. SCADA sets their targets and watches the results. That separation is deliberate: control and protection must keep working when the supervisory link is slow, congested or lost.
IEEE C37.1 has long served as the North American reference that defines SCADA and automation system functions and requirements for the electric utility industry. The 2007 edition is listed by IEEE as inactive-reserved, which means it is no longer maintained but remains available as a reference. Keentel still finds its functional definitions useful when writing specifications, while relying on current standards for communications and cyber security.
How Keentel Engineering helps here. Keentel starts every SCADA project by writing down what must be supervised, what must be controlled locally, and what must keep working with communications lost. That functional requirements document becomes the basis for the points list, the network design, the cyber security plan and the test plan.
2. A short history of SCADA generations
SCADA architecture has changed in four broad steps, and most real systems contain pieces of more than one.
| Generation | Approximate era | Characteristics | Typical risk today |
|---|---|---|---|
| Monolithic | 1960s–1980s | Single mainframe or minicomputer master; proprietary protocols over leased lines or radio; little or no networking | Obsolete hardware and protocols still in service at some remote sites |
| Distributed | 1980s–1990s | Multiple stations on a local area network sharing functions; still largely proprietary | Unsupported operating systems; undocumented interfaces |
| Networked | 1990s–2010s | Open protocols (DNP3, Modbus TCP, IEC 61850), Ethernet and wide-area IP networks; connection to business networks | Exposure to IT-borne threats; flat networks |
| Connected and cloud-assisted | 2010s–present | Virtualized servers, remote access, cloud historians and analytics, IoT sensors, mobile access | Larger attack surface; dependence on external services |
Each step improved capability and reduced cost. Each also widened the attack surface. Systems designed when networks were isolated were rarely built to resist a capable adversary, and many of them are still running. That history explains why modern SCADA design spends so much effort on segmentation, remote access control and monitoring.
How Keentel Engineering helps here. Keentel inventories mixed-generation SCADA estates, identifies equipment and software that is out of support, and builds a phased replacement plan that keeps operators' visibility intact while removing the riskiest legacy components first.
3. SCADA, DCS, PLC, RTU and EMS: who does what
The terms are often blurred, and vendors' platforms now overlap. The design priorities still differ, and confusing them leads to poor architecture.
| System | Primary job | Typical geography | Typical control speed | Typical users |
|---|---|---|---|---|
| SCADA | Supervisory monitoring and control of distributed assets | Wide area: miles to hundreds of miles | Seconds | Utilities, pipelines, water, renewable fleets |
| DCS | Continuous, plant-wide regulatory control | One plant or campus | Milliseconds to seconds | Refining, chemicals, power plants |
| PLC | Discrete and sequential control of machines and processes | One machine, skid or area | Milliseconds | Manufacturing, packaged equipment, plant balance of plant |
| RTU / substation automation controller | Data gathering, local logic and protocol gateway at a remote site | One substation or remote site | Milliseconds to seconds | Utilities, pipelines, water |
| EMS | Transmission operations: SCADA plus network analysis, generation control and market interfaces | Utility or ISO footprint | Seconds to minutes | Transmission operators, balancing authorities |
| ADMS / DERMS | Distribution operations and distributed energy resource management | Distribution system | Seconds to minutes | Distribution utilities |
A few distinctions matter in practice:
- SCADA versus DCS. A DCS is engineered as one integrated system, with controllers, operator stations and a database designed together, high-speed redundant networks, and tightly managed control strategies. SCADA is engineered around unreliable, slower, long-distance communications, so it emphasizes polling, report-by-exception, store-and-forward and time-stamping at the source. Many power plants run a DCS for the plant and pass data to a utility or fleet SCADA above it.
- PLC versus RTU. Both are rugged controllers. PLCs are optimized for fast local logic and I/O. RTUs are optimized for remote communications, event time-stamping and protocol translation, with wider temperature ranges and lower power use. Modern products from many manufacturers do both, so the choice is now about the job, not the label.
- SCADA versus EMS. An EMS includes SCADA but adds network applications: state estimation, contingency analysis, automatic generation control and interfaces to markets. Transmission and balancing operators run EMS platforms; generation plants, substations and distribution feeders feed data into them.
How Keentel Engineering helps here. When a client inherits a mixed fleet of PLCs, RTUs, a plant DCS and a utility SCADA interface, Keentel maps which system owns each control function, where each value originates, and which device is authoritative. That map removes duplicate control paths and closes gaps before they cause an operating error.
4. The layered architecture
Most SCADA systems, in process plants and in power systems, fit a layered model. Keentel uses the Purdue Enterprise Reference Architecture, adapted for security in ISA/IEC 62443 and NIST SP 800-82, as the common language for design reviews. Figure 1 shows the levels with the components that typically sit at each.

Figure 1. SCADA architecture mapped to Purdue levels, security zones and conduits. Keentel original diagram.
Level 0 — the physical process. Sensors and actuators: pressure, temperature, flow and level transmitters, control valves, motors, current and voltage transformers, breakers, inverters and tanks. These are the only parts of the system that touch the process directly.
Level 1 — basic control. PLCs, DCS controllers, RTUs, protective relays, meters and other IEDs. They read Level 0 signals, run control and protection logic, and drive outputs. A Level 1 device must be able to keep the process safe on its own.
Level 2 — supervisory control. Local HMIs, substation automation controllers, plant power controllers and area operator stations. Level 2 coordinates multiple Level 1 devices and gives local operators a view of an area or site.
Level 3 — site operations. SCADA servers, historians, engineering workstations, alarm servers, time servers, and gateways such as ICCP links to an ISO. In a utility, the control center sits here.
Level 3.5 — industrial demilitarized zone. A buffer network between operations and the enterprise. It hosts replicated historians, patch and antivirus staging servers, file transfer services and jump hosts for remote access. Nothing should pass directly from Level 4 to Level 3; every connection terminates in the DMZ.
Levels 4 and 5 — enterprise. Business systems, email, enterprise resource planning and internet access.
The levels are a reference, not a rule that every site must have six physical networks. A small solar plant might combine Levels 2 and 3 in one cabinet. What must not be lost is the principle behind the levels: each boundary is a place to control and inspect traffic, and the most critical functions sit furthest from the internet.
4.1 The data path, step by step
In the simplest description, data flows from field instruments to controllers, across an industrial network, to a SCADA server and on to the operator. A more complete description for a power-system point looks like this:
1. A current transformer and voltage transformer at a breaker feed a protective relay.
2. The relay calculates real power, reactive power and voltage, time-stamps a breaker status change to within a millisecond, and stores the values in its database.
3. A substation automation controller polls the relay over DNP3 or reads it over IEC 61850, perhaps every 250 milliseconds.
4. The SCADA master at the control center polls the substation controller, or receives unsolicited reports, over a wide-area network.
5. The SCADA server updates its real-time database, checks alarm limits, writes values to the historian, and passes selected values to the EMS and to the ISO over ICCP.
6. The operator's display refreshes.
A command travels back down the same path. In both directions each step adds delay and a potential failure point. Sections 7 and 13 put numbers on that delay.
4.2 What the simple diagrams leave out
The common block diagram — operator stations at the top, a server and historian in the middle, controllers and instruments at the bottom — is a fair starting point. Keentel adds eight elements that a real design must show:
- Communication front-ends and gateways that translate protocols and buffer data.
- Time synchronization: a GPS-referenced master clock and the distribution path to every device.
- Redundancy: duplicate servers, network paths and power supplies, with defined failover behavior.
- The security architecture: zones, conduits, firewalls, DMZ, remote access path and monitoring sensors.
- Data exchange with external parties: ISO, transmission operator, neighboring utility, owner's fleet center.
- Backup control capability: for NERC-registered control centers, the backup functionality required under EOP-008.
- Engineering and maintenance access: how configuration changes reach controllers, and who can make them.
- Power supply: uninterruptible and dc power for every critical component, with known ride-through time.
Keentel Study Spotlight — SCADA architecture review. Keentel reviews an existing or proposed SCADA design against the layered model, documents every data path and trust boundary on one drawing, and produces a gap list ranked by operational and compliance risk. Clients use it to scope upgrades and to brief auditors and insurers.
5. Field instruments and signals
Everything SCADA knows begins with a measurement. In process plants that means transmitters; in power systems it means instrument transformers, transducers and the measuring functions inside relays and meters.
5.1 The 4–20 mA loop
The 4–20 mA current loop remains the workhorse analog signal in process plants and in many power-plant balance-of-plant systems. A two-wire transmitter regulates the loop current between 4 mA (0% of range) and 20 mA (100% of range). Using current rather than voltage makes the signal immune to voltage drop along the cable, and the "live zero" at 4 mA lets the receiver tell a zero reading from a broken wire, which reads near 0 mA. Many transmitters also superimpose a HART digital signal on the loop for configuration and diagnostics.
The scaling is linear:

Worked example 1 — scaling a level transmitter and checking the loop
A tank level transmitter is ranged 0–10 m. The controller reads 12.0 mA.
- PV = 0 + (12 − 4) / 16 × 10 = 5.0 m.
The loop is powered from 24 V dc through a 250 Ω input resistor at the controller, and the cable is 600 m of twisted pair with about 26.5 Ω per kilometer per conductor (53 Ω per kilometer for the loop). The transmitter needs at least 10.5 V across its terminals to operate.
- Cable resistance = 53 × 0.6 = 31.8 Ω.
- Voltage available at the transmitter at 20 mA = 24 − 0.020 × (250 + 31.8) = 18.4 V.
- Margin above the 10.5 V minimum = 7.9 V.
- Maximum total loop resistance at 20 mA = (24 − 10.5) / 0.020 = 675 Ω.
The design works with room to spare. Problems arise when a second receiver, an intrinsic-safety barrier or a long run is added without repeating this check. Many transmitters also drive the loop to about 21–23 mA to signal a fault, so Keentel checks the compliance voltage at the alarm current, not just at 20 mA.
5.2 Resolution and accuracy
The controller's analog-to-digital converter sets the smallest change SCADA can see. Resolution is not accuracy: the transmitter's own error, the loop resistor's tolerance and temperature effects usually dominate.
Worked example 2 — what resolution does the input card give?
Assume the input card digitizes 0–20 mA across its full count range, so the 4–20 mA span uses 80% of the counts. For the 10 m level span:
| Converter | Counts over 0–20 mA | Resolution on a 10 m span |
|---|---|---|
| 12-bit | 4,096 | about 3.1 mm |
| 14-bit | 16,384 | about 0.8 mm |
| 16-bit | 65,536 | about 0.2 mm |
All three are finer than a typical transmitter accuracy of a few millimeters on this range. For tank level, any of them is adequate. For energy revenue metering or high-accuracy flow, resolution and the whole measurement chain need a closer look.
5.3 Power-system measurements
In substations, the "instruments" are current transformers (CTs) and voltage transformers (VTs), and the measurement is usually made by a relay, meter or transducer that calculates root-mean-square values, power and energy. Points to watch:
- Accuracy class. Relaying-class CTs are designed to reproduce fault current, not to measure light load accurately. Use metering-class cores where revenue or performance-test accuracy matters.
- Update rate and filtering. Relays may calculate values every few milliseconds but report them to SCADA with deadbands. A deadband that is too wide hides real changes; too narrow, and it floods the network.
- Sign conventions. Real and reactive power direction, especially at plants that both import and export, must be defined once and applied everywhere. Sign errors are one of the most common telemetry faults Keentel finds.
- Scaling and units. Megawatts versus kilowatts, primary versus secondary values, per-unit versus engineering units: every conversion must be documented in the points list.
How Keentel Engineering helps here. Keentel's points-list reviews check every analog point from CT and VT ratio through relay scaling, protocol scaling and SCADA display units, and flag sign-convention and deadband problems before commissioning.
6. Controllers and IEDs
6.1 PLCs and DCS controllers
PLCs and DCS controllers execute control logic in a repeating scan: read inputs, solve logic, write outputs, then handle communications. Scan times range from a few milliseconds to a few hundred. For SCADA design, three properties matter:
- What the controller does when communications fail. It should hold safe states, continue local control, and alarm the loss. Outputs commanded by SCADA should have defined fallback values.
- How data is time-stamped. If the controller time-stamps changes at the source, the historian receives accurate event times. If the SCADA server stamps them on arrival, the time reflects polling delay, not the event.
- Who can change the logic. Online program changes from an engineering station are powerful and dangerous. Access control, change logging and backups of controller programs belong in the design.
6.2 RTUs and substation automation controllers
In a power substation, the classic RTU with hardwired inputs and outputs has largely been replaced by a substation automation controller that collects data from protective relays, meters and other IEDs over serial or Ethernet links, runs local logic, and presents one consolidated data set to the control center. The controller often performs:
- protocol conversion, for example from IEC 61850 or Modbus inside the substation to DNP3 toward the control center;
- data concentration and calculation, such as summing feeder loads or deriving station totals;
- local automation, such as bus transfer, load shedding, capacitor control or interlocking;
- event collection and time-stamped sequence-of-events recording;
- secure remote engineering access to downstream IEDs.
6.3 Protective relays as data sources
Modern microprocessor relays are among the richest data sources in a substation, providing analogs, breaker status, alarms, fault locations and oscillography. They are also protection devices whose primary job must never be compromised by SCADA traffic. Keentel's practice is to keep protection settings and SCADA data mapping under separate change control, to limit the SCADA command set to what operations truly needs, and to confirm that relay processing time is not affected by polling load.
Keentel Study Spotlight — Controller and IED data mapping. Keentel builds or audits the data map for every relay, meter and controller: register or object, scaling, deadband, class assignment, time-stamp source and command permissions. The result is a single, version-controlled points list that operations, protection and compliance teams all use.
7. Communications and protocols
7.1 The main protocols
| Protocol | Typical use in power and process SCADA | Key features | Security notes |
|---|---|---|---|
| 4–20 mA / HART | Field transmitters to controllers | Analog signal with digital overlay for configuration | Physical access is the main risk |
| Modbus (RTU and TCP) | Controllers, meters, drives, inverters, battery systems | Simple register-based polling; very widely supported | No native authentication or encryption |
| DNP3 (IEEE 1815) | Control center to RTU/IED; substation to plant | Report-by-exception, event classes, time-stamped events, select-before-operate | Secure Authentication available but not universally deployed |
| IEC 61850 | Within substations: MMS client/server, GOOSE peer-to-peer messaging, sampled values | Object-oriented data model, configuration language, fast peer messaging | Security addressed by companion IEC 62351 series |
| ICCP / TASE.2 (IEC 60870-6) | Between control centers and ISOs | Bilateral tables, block transfers, scheduled and event-driven data | Usually carried over dedicated, firewalled links |
| IEC 60870-5-101/104 | International equivalent of DNP3; occasional US use | Event-driven telemetry | Similar considerations to DNP3 |
| IEEE C37.118 | Phasor measurement units to phasor data concentrators | High-rate time-synchronized phasors | Typically on separate networks |
| IEEE 2030.5 | Utility to distributed energy resources and aggregators | Web-based DER management | Built-in transport security |
DNP3 was developed in the early 1990s and later standardized by IEEE as IEEE 1815. IEEE lists the 2012 edition as inactive-reserved; the protocol continues to be maintained and supported through its users' organization and remains the dominant SCADA protocol in North American utilities. IEC 61850 is an international standard that has become common in new US substations, particularly for relay-to-relay messaging.
7.2 Polling, report-by-exception and integrity scans
DNP3 lets a master request a full "integrity" poll of all values (static data) and also lets outstations report only changes (event data), either when polled or unsolicited. A well-designed system uses frequent event polls and occasional integrity polls. Sizing the communications path depends on which pattern dominates.
Worked example 3 — how much data does a substation send?
A substation automation controller presents 2,000 analog points and 3,000 status points to the control center. Assume 5 bytes per analog value with flags, status points packed one bit each, DNP3 link frames carrying up to about 250 user bytes, and roughly 42 bytes of header and cyclic redundancy check per frame.
- Integrity poll payload ≈ 2,000 × 5 + 3,000 / 8 ≈ 10,375 bytes; with framing ≈ 12,100 bytes.
- At one integrity poll every 2 seconds this would be about 48.6 kbit/s.
- Event poll, assuming 5% of analogs and 1% of status points change per 2-second cycle with time-stamped event objects (11 and 8 bytes): ≈ 1,600 bytes, or about 6.4 kbit/s.
- On a 9,600 bit/s serial link, a single integrity poll takes about 12.6 seconds; at 19,200 bit/s, about 6.3 seconds.
The conclusion is the one most experienced SCADA engineers reach by instinct: on serial links, schedule integrity polls rarely (every 15 to 60 minutes) and rely on event reporting. On Ethernet, integrity polls are cheap, but storm conditions — when many points change at once — still need to be checked against link capacity and server processing.

Worked example 4 — serial versus Ethernet polling cycle
A utility polls 40 RTUs on a shared multidrop radio channel at 9,600 bit/s, 600 bytes per RTU per cycle, with about 150 ms of turnaround per RTU.
- Serial cycle ≈ 40 × (600 × 10 / 9,600 + 0.15) ≈ 31 seconds.
- The same polling over a 10 Mbit/s IP network with 20 ms of turnaround per RTU ≈ 0.8 seconds.
A 31-second cycle is acceptable for distribution monitoring but not for transmission telemetry to an ISO. This is often the single biggest reason for a communications upgrade.
How Keentel Engineering helps here. Keentel models polling cycles, event storms and link utilization for each communication path, and recommends class assignments, deadbands, unsolicited reporting and integrity-poll schedules that meet operations and ISO requirements without overloading radios or serial lines.
8. Network design and redundancy
8.1 Topologies
- Star networks are simple but make the central switch a single point of failure.
- Ring networks of managed switches recover from a single link or switch failure, typically in tens of milliseconds with modern ring protocols.
- Parallel Redundancy Protocol (PRP) sends every frame over two independent networks at once, so a failure on one network causes no recovery delay at all. High-availability Seamless Redundancy (HSR) does the same in a ring. Both are defined in IEC 62439-3 and are used in substations where IEC 61850 messaging cannot tolerate interruption.
- Wide-area connections use utility fiber, leased circuits, licensed or unlicensed radio, cellular or satellite. Each has its own latency, availability and security profile.
| Medium | Typical latency | Strengths | Watch for |
|---|---|---|---|
| Utility-owned fiber | Milliseconds | High capacity, immune to interference, owner-controlled | Build cost; route diversity |
| Leased digital circuits | Milliseconds to tens of ms | Predictable performance | Carrier migration away from legacy circuits; dependence on a third party |
| Licensed narrowband radio | Tens to hundreds of ms per poll | Owner-controlled; long range | Low bandwidth; path studies needed |
| Unlicensed spread-spectrum radio | Tens of ms | Low cost; moderate bandwidth | Interference; shorter range |
| Private LTE | Tens of ms | Broadband; utility-controlled spectrum where licensed | Spectrum access; core network security |
| Public cellular | Tens to hundreds of ms, variable | Easy deployment | Variable latency; carrier outages during storms; security of the path |
| Satellite | Hundreds of ms (geostationary) to tens of ms (low-earth orbit) | Reaches remote sites | Latency, weather and cost |
8.2 Server and network availability
Redundant servers and rings raise availability, but only if failover works and common-cause failures — shared power, shared software defects, a single bad configuration push — are controlled.

Worked example 5 — what does a redundant server pair really buy?
A single SCADA server has availability of 99.5% (about 43.8 hours of downtime a year, including maintenance).
- An ideal hot-standby pair with independent failures: unavailability = 0.005² = 0.000025, or about 13 minutes a year.
- Add a common-cause factor of 2% (a shared defect or power problem that takes out both): unavailability ≈ 0.000025 × 0.98 + 0.02 × 0.005 ≈ 0.000125, or about 65 minutes a year.
The common-cause term is four times larger than the independent term. That is why Keentel looks at separate power feeds, staged patching, configuration validation before both servers are updated, and a tested backup control capability.
Worked example 6 — chain versus ring
Six managed switches each have availability of 99.95%.
- In a chain, every switch must work: 0.9995⁶ ≈ 99.70%, or about 26 hours of outage a year for at least one segment.
- In a ring that tolerates any single switch failure: availability ≈ 99.9996%, or about 2 minutes a year of exposure.
Keentel Study Spotlight — Availability and redundancy analysis. Keentel quantifies availability for SCADA servers, networks, communications paths and power supplies, including common-cause effects, and recommends where redundancy pays for itself. The analysis also supports EOP-008 backup control planning for registered control centers.
9. SCADA servers, HMIs and operator displays
9.1 The SCADA server
The SCADA server, often called the master station, holds the real-time database, runs the communication drivers that poll field devices, processes alarms and events, executes supervisory logic, and serves data to operator stations and other systems. In any system where loss of visibility matters, it is deployed as a redundant pair, often with a third, geographically separate backup.
Design questions Keentel asks for every server installation:
- How long does failover take, and what happens to commands in progress during a switchover?
- Is the database synchronized continuously, or only periodically?
- How are configuration changes made and validated before they reach the standby?
- Is the server virtualized, and if so, is the virtual infrastructure itself redundant and secured?
- Can the system be rebuilt from backups, and how long does it take? Has anyone actually done it?
9.2 The operator interface
The HMI is where the system meets the people who run it. Poor displays cause operating errors; good ones help operators spot abnormal situations early.
ANSI/ISA-101.01-2015 sets out a lifecycle for designing, building and maintaining HMIs for process automation. The approach often called "high-performance HMI" follows from it and from human-factors research:
- Muted backgrounds and gray process graphics, so that color is reserved for abnormal conditions and alarms.
- A display hierarchy from an overview of the whole system, to area displays, to detail and diagnostic displays.
- Analog indicators with normal ranges marked, so the operator sees at a glance whether a value is healthy, rather than reading numbers.
- Consistent symbols, navigation and command dialogs across every screen.
- Confirmation steps for commands, especially those that affect safety or many customers.
In power systems, one-line diagrams are the core display. The same principles apply: show breaker state and energization clearly, highlight abnormal states, and avoid clutter.
How Keentel Engineering helps here. Keentel reviews operator displays against ISA-101 principles and utility operating practice, checks every one-line against the as-built electrical design, and verifies that command dialogs, interlocks and tagging work as intended during SAT.
10. The historian
10.1 What a historian is for
A historian stores time-series values and events so that engineers, operators, compliance staff and analysts can look back. For power-sector owners, the historian is often the evidence behind performance tests, ride-through investigations, disturbance reports, reactive capability demonstrations and model validation. If its time stamps are poor or its compression settings discard detail, that evidence is weak.
10.2 Compression and deadbands
Historians typically store a new value only when it changes by more than a set deadband, or when the trend departs from a straight line by more than a tolerance. Compression ratios of 10:1 to 30:1 are common for slowly changing process data. The settings must be chosen per tag: a deadband suitable for tank level would destroy the information in a plant's reactive power response to a fault.
Worked example 7 — historian storage for 20,000 tags
A plant historian collects 20,000 tags at one sample per second. Each stored value uses about 16 bytes (time stamp, value and quality).
- Uncompressed: 20,000 × 1 × 16 × 31.5 million seconds ≈ 10.1 TB per year.
- At 10:1 compression ≈ 1.0 TB per year.
- At 30:1 compression ≈ 0.34 TB per year.
Storage is cheap; lost data is not. Keentel recommends lighter compression for the tags that serve compliance, performance testing and event analysis, heavier compression for slow process tags, and a documented retention policy that meets regulatory and contractual requirements.
10.3 Where the historian sits
The historian collects from Level 3. Users on the business network should read from a replica in the DMZ, not from the operational historian directly. That one design choice removes a common path for attackers and malware to reach the control network.
Keentel Study Spotlight — Historian and data-quality review. Keentel audits historian tags, scan rates, compression settings, time-stamp sources and retention against what compliance, performance testing and event analysis actually need, and identifies gaps before an event or audit exposes them.
11. Alarm management
11.1 Why alarms fail
An alarm exists to tell an operator that something needs a response. When a system produces hundreds of alarms an hour, most of which need no action, operators learn to ignore them, and the one that matters is missed. Alarm floods during plant upsets have contributed to major industrial accidents, which is why alarm management became a formal discipline.
11.2 The standard and the benchmarks
ANSI/ISA-18.2-2016, Management of Alarm Systems for the Process Industries, defines an alarm management lifecycle: philosophy, identification, rationalization, detailed design, implementation, operation, maintenance, monitoring and assessment, management of change, and audit. Widely used performance benchmarks, drawn from ISA-18.2 and the earlier EEMUA 191 guide, include:
| Metric | Commonly used target |
|---|---|
| Average alarm rate per operator console in steady operation | About 6 per hour, or 1 per 10 minutes; about 150 per day is often called very likely acceptable |
| Maximum manageable | About 12 per hour, or about 300 per day |
| Alarm flood | More than 10 alarms in 10 minutes |
| Share of time in flood | Less than about 1% |
| Priority distribution | Roughly 80% low, 15% medium, 5% high |
| Stale alarms (active more than 24 hours) | Fewer than about 5 at any time |
| Chattering alarms | None |
These are commonly cited benchmarks for process plants. Utility control centers and renewable plants often adapt them, and each organization should set its own targets in its alarm philosophy.
Worked example 8 — is this console overloaded?
Three operator consoles record the following daily alarm counts:
| Console | Alarms per day | Average per hour | Average per 10 minutes | Assessment |
|---|---|---|---|---|
| 1 — transmission substations | 620 | 25.8 | 4.3 | Overloaded; well above the ~300/day manageable level |
| 2 — distribution feeders | 410 | 17.1 | 2.8 | Overloaded |
| 3 — generation plants | 150 | 6.3 | 1.0 | At target |
Averages hide floods. Figure 2 shows a week of 10-minute alarm counts for an illustrative console that averages close to the target but has three floods above 20 alarms in 10 minutes, each following a switching event. Rationalization should address both the average and the floods.

Figure 2. Alarm rate in 10-minute bins for one operator console over a week, against common targets. Illustrative data.
11.3 Practical steps
- Write an alarm philosophy that defines what qualifies as an alarm, priorities, response times and suppression rules.
- Rationalize every alarm: cause, consequence, required action, priority and set point.
- Remove or demote "alarms" that are really events or status changes.
- Use state-based and logical suppression: when a breaker is opened for maintenance, its downstream low-voltage alarms should not annunciate.
- Fix chattering alarms with deadbands and on-delay or off-delay timers.
- Monitor performance monthly and act on the worst offenders.
How Keentel Engineering helps here. Keentel runs alarm rationalization workshops for substations, renewable plants and industrial facilities, writes alarm philosophies, and produces before-and-after performance metrics that show operators and managers the improvement.
12. Time synchronization and sequence of events
12.1 Why time matters
When a fault occurs, dozens of relays, breakers and controllers respond within a few cycles. Reconstructing what happened depends on knowing the order of those actions to within a millisecond or better. If one relay's clock is 40 milliseconds off, the event record can show a breaker opening before the fault that caused it.
Time quality also matters for compliance. Disturbance monitoring and event analysis requirements depend on time-synchronized records, and plant performance investigations compare data from multiple devices.
12.2 Methods
| Method | Typical accuracy at the device | Notes |
|---|---|---|
| Network Time Protocol (NTP) | About 1–10 ms on a LAN, worse over WAN | Adequate for SCADA servers and HMIs; not for protection event records |
| IRIG-B (demodulated) | Better than 1 µs to tens of µs, depending on distribution | Requires dedicated wiring from the clock |
| IEEE 1588 PTP with the C37.238 power profile | Sub-microsecond with PTP-aware switches | Carried over the substation Ethernet network |
| GPS receiver at each device | Sub-microsecond | Requires antennas; vulnerable to signal loss or spoofing |
IEEE C37.238-2017 defines a profile of IEEE 1588 Precision Time Protocol for power-system applications. It is the modern way to deliver accurate time over substation networks without dedicated IRIG-B wiring.
Worked example 9 — how accurate does time need to be?
At 60 Hz, one cycle lasts 16.7 ms.
- An error of 1 ms equals 0.06 cycle, or 21.6 electrical degrees. That is enough to misorder events in a fast fault sequence, and far too much for phasor measurements.
- An error of 1 µs equals 0.0216 degrees, which is why synchrophasor standards require microsecond-class time.
For SCADA sequence-of-events records, Keentel specifies 1 ms resolution with source time-stamping and device clocks synchronized to within about 1 ms or better. For phasor measurement units, microsecond accuracy from GPS or PTP is required.
12.3 Resilience
GPS signals can be lost or spoofed. Good designs use clocks with holdover oscillators, monitor time quality, alarm on loss of synchronization, and, where justified, use a second time source such as a terrestrial reference.
Keentel Study Spotlight — Time synchronization design and verification. Keentel designs the clock architecture for substations, plants and data centers, specifies PTP or IRIG-B distribution, and verifies time quality at every IED during commissioning, so that event records will stand up in an investigation.
13. SCADA in the electric power system
Process plants and power systems use the same building blocks, but the power sector adds three things: very wide geography, protection systems that act in milliseconds, and regulatory obligations attached to the data.
13.1 Control centers and EMS
Transmission operators and balancing authorities run energy management systems that combine SCADA with state estimation, contingency analysis, automatic generation control and interfaces to markets. The data they need comes from substations, generating plants and neighboring control centers. Plants and substations deliver it either directly to the operator's SCADA over DNP3, or to a utility or ISO through ICCP links from the owner's control center.
13.2 Telemetry obligations
ISOs and transmission operators set telemetry requirements for generating resources and large loads: which points, at what scan rate, with what accuracy, latency and availability. Common elements include real and reactive power, voltage, breaker status, plant controller set points and status, and for inverter-based plants, available power and meteorological data. Requirements differ by ISO and are updated over time, so each project must work from the operator's current handbook or protocols. Under NERC TOP-003 and IRO-010, transmission and reliability coordinators issue data specifications that registered entities must meet.
Worked example 10 — will the telemetry arrive in time?
A 200 MW solar and battery plant must deliver real power telemetry to its ISO. For illustration, assume a target of 4 seconds from a change at the plant to the value in the operator's system. Figure 3 compares two designs.
| Step | Design A (tuned) | Design B (slow poll, extra hop) |
|---|---|---|
| Transducer or relay measurement | 0.25 s | 0.25 s |
| RTU or IED scan and processing | 0.50 s | 0.50 s |
| Polling delay (average) | 1.00 s | 2.00 s |
| Communications path | 0.30 s | 0.30 s |
| Plant gateway to owner's control center | 0.50 s | 2.00 s |
| ICCP to ISO energy management system | 0.50 s | 0.50 s |
| Total | 3.05 s | 5.55 s |

Figure 3. End-to-end telemetry latency budget for two plant SCADA designs. Illustrative values; actual requirements come from the applicable ISO or transmission operator.
Design B fails the illustrative target even though each step looks reasonable on its own. The fix is usually one of three things: faster polling or unsolicited reporting at the plant, removing an unnecessary hop through the owner's fleet system, or sending data directly from the plant to the ISO.
13.3 Substation automation
A modern substation automation system combines protective relays, a substation automation controller, a local HMI, Ethernet networks (often PRP or rings), time synchronization and a secure remote access path. Under IEC 61850, relays exchange trip and interlock signals as GOOSE messages over Ethernet instead of copper wiring, and some designs carry digitized CT and VT signals as sampled values on a process bus. These designs cut wiring and improve monitoring but move critical protection traffic onto the network, which raises the bar for network design, testing and cyber security.
How Keentel Engineering helps here. Keentel designs IEC 61850 and DNP3 substation automation systems, including GOOSE messaging, PRP or ring networks and test plans that prove protection messages arrive in time under load and during network failures.
13.4 Renewable and storage plants
At solar, wind and battery plants, SCADA ties together inverters or turbines, the plant power controller, the substation, meteorological stations and the battery energy management system. The plant controller regulates voltage, reactive power, real power and frequency response at the point of interconnection, while SCADA provides the operator interface, set-point entry and data for the ISO.
Worked example 11 — who controls reactive power, and how fast?
A 200 MW plant must deliver about ±66 Mvar at the point of interconnection, roughly 0.33 per unit, or 0.95 power factor at rated output. Its plant controller runs voltage control with a 4% droop and updates inverter commands every 100 ms. The transmission operator sends voltage set points through SCADA, which the plant receives every 4 seconds.
- A 1% voltage deviation with a 4% droop calls for 1% / 4% × 66 ≈ 16.5 Mvar.
- The controller completes about 40 update cycles for every SCADA set-point refresh.
SCADA sets the target; the plant controller does the regulating. A design that tries to close the voltage loop through SCADA would be too slow and would lose control whenever communications dropped. Keentel's power plant controller and IEEE 2800 commissioning guides cover these loops in depth.
13.5 Battery energy storage
Battery systems add a battery management system and an energy management system that schedule charge and discharge, enforce state-of-charge and temperature limits, and coordinate with the plant controller. SCADA must expose state of charge, available energy, alarms from thermal and fire detection systems, and the status of auxiliary systems. Data from the battery management system is often the first warning of a developing thermal problem, so its alarms deserve careful rationalization.
13.6 Distribution, DER and DERMS
Distribution utilities use SCADA and ADMS platforms to monitor substations and feeders, operate reclosers and capacitor banks, and increasingly manage distributed energy resources. IEEE 2030.5 is used to communicate with DER and aggregators in several states, notably under California's Rule 21 smart inverter requirements, and OpenADR is used for demand response. These connections extend the utility's supervisory reach to thousands of customer-owned devices, with corresponding security and data-volume challenges.
How Keentel Engineering helps here. Keentel supports distribution utilities and DER developers with telemetry and control design for distributed resources, IEEE 2030.5 and DNP3 integration, and the protection and hosting-capacity studies that come with them.
13.7 Data centers
Large data centers run electrical power monitoring systems (EPMS) and building management systems that behave much like utility SCADA: they monitor medium-voltage switchgear, transformers, UPS systems, generators and power distribution, record sequence-of-events data, and alarm on abnormal conditions. As data center loads grow into the hundreds of megawatts and connect at transmission voltage, they increasingly need utility-grade telemetry to the transmission operator, time-synchronized event records for ride-through investigations, and attention to cyber security. Keentel's data center tiers and large-load guides discuss the electrical side.
13.8 Synchrophasors
Phasor measurement units (PMUs) measure voltage and current phasors time-stamped to GPS or PTP time and stream them at rates up to 60 or more frames per second. They complement SCADA by showing dynamic behavior — oscillations, angle separation, fault-induced voltage dips — that a 2-to-4-second SCADA scan cannot see. IEEE C37.118.1 covers measurement and C37.118.2 the data transfer format.
Worked example 12 — PMU bandwidth
A PMU streams 8 phasors, frequency and rate of change of frequency, 4 analog values and 1 digital word at 60 frames per second using floating-point data.
- Data frame ≈ 2 + 2 + 2 + 4 + 4 + 2 + 8 × 8 + 4 + 4 + 4 × 4 + 2 + 2 = 108 bytes.
- With about 46 bytes of Ethernet, IP and UDP overhead, each PMU uses about 74 kbit/s.
- Ten PMUs need about 0.74 Mbit/s, and each PMU produces about 0.56 GB of raw data per day.
The bandwidth is modest for fiber but significant for radio or cellular backhaul, and the storage adds up quickly. Phasor data is usually carried on a network separate from SCADA.

13.9 Remote sites and radio
Many SCADA sites — pipeline valves, water tanks, distribution reclosers, remote substations — are reached by radio. Licensed narrowband radio, unlicensed spread spectrum, private LTE, public cellular and satellite each have a role. Every radio path needs a link budget with fade margin.

Worked example 13 — a 900 MHz link to a remote RTU
A 15 km path at 900 MHz with a 30 dBm transmitter, 10 dBi antennas at each end, 3 dB of cable and connector loss, and a receiver sensitivity of −100 dBm:
- Free-space path loss ≈ 20 log(15,000) + 20 log(900 × 10⁶) − 147.55 ≈ 115.1 dB.
- Received signal ≈ 30 + 10 + 10 − 3 − 115.1 ≈ −68.1 dBm.
- Fade margin ≈ −68.1 − (−100) ≈ 31.9 dB.
Free-space loss is the best case. Terrain, vegetation and the Fresnel zone usually add losses, so a path study with terrain data is needed before committing. A fade margin of 20–30 dB is a common design aim for SCADA radio.
14. A worked process example: tank level monitoring
The most familiar SCADA teaching example is a level transmitter on a storage tank that reports to a PLC, which passes the value to the SCADA server for display and alarming. Keentel uses it here to show the engineering behind each step.
Worked example 14 — tank fill rate, alarm limits and response time
A 12 m diameter tank is 10 m tall. Inflow is 180 m³/h and outflow 120 m³/h. The level is 6.0 m. Alarm limits are high (H) at 8.5 m and high-high (HH) at 9.0 m, with an independent safety trip above that.
- Cross-section area = π × 12² / 4 ≈ 113.1 m².
- Net inflow = 60 m³/h = 0.0167 m³/s.
- Level rise rate = 0.0167 / 113.1 ≈ 8.8 mm per minute.
- Time from 6.0 m to the H alarm ≈ (8.5 − 6.0) / 0.0088 ≈ 283 minutes.
- Time from H to HH ≈ 0.5 / 0.0088 ≈ 57 minutes.

The operator has nearly an hour between the H and HH alarms to act, which comfortably exceeds a typical required response time. If the inflow were ten times higher, the gap would shrink to under six minutes, and the alarm design — and possibly an automatic interlock — would need to change. A deadband of about 0.1 m on each alarm prevents chattering from surface ripple.
Three further points the simple example leaves out:
- The HH alarm and the safety trip should not depend on SCADA. The trip belongs in a separate safety instrumented function with its own transmitter.
- Measurement validity matters. A frozen or failed transmitter can show a normal level while the tank overflows. Rate-of-change checks, comparison with a second instrument, and bad-quality alarms address this.
- The same logic applies in power systems. Transformer oil and winding temperatures, battery state of charge and capacitor bank voltages all have the same structure: a rate, limits, response time and a protective backstop.
How Keentel Engineering helps here. Keentel designs SCADA and telemetry for substations, renewable and storage plants, data centers and industrial facilities, including ISO telemetry design and testing, plant controller integration, PMU deployment, radio path studies, and alarm and response-time analysis for critical process and electrical limits.
15. Cyber security for SCADA
15.1 Why SCADA is a target
SCADA systems control physical processes, so an intrusion can cause outages, equipment damage, environmental releases or harm to people. Many systems were designed before networks were exposed to capable adversaries, and some still run unsupported software. Public incidents show the range of risk:
- Ukraine, December 2015. Attackers who had gained access to three Ukrainian distribution companies' networks used their SCADA and remote-access tools to open breakers. US government reporting describes outages affecting about 225,000 customers for several hours. The attackers also disabled equipment and wiped workstations to slow recovery.
- Ukraine, December 2016. A malware framework built to speak industrial protocols directly — publicly named Industroyer or CrashOverride — was used against a transmission substation near Kyiv, causing an outage of roughly an hour.
- Florida water treatment plant, February 2021. Public reports described someone using remote-access software on a plant computer to raise the set point for sodium hydroxide far above normal. An operator noticed and reversed the change. Later reporting raised questions about whether the access came from outside, but the case remains a widely cited lesson about unsecured remote access to HMIs.
- US fuel pipeline, May 2021. A ransomware attack on a major fuel pipeline company's business network led the company to shut down pipeline operations for several days as a precaution. The control system was not reported to be directly compromised, but the dependence of operations on business systems caused the shutdown.
- Pre-positioning in US infrastructure, 2024. In February 2024, CISA and partner agencies published a joint advisory (AA24-038A) describing a state-sponsored group, publicly called Volt Typhoon, that had gained and kept access to IT networks of US critical infrastructure organizations, including energy and water, apparently to position for possible disruption.
The pattern is consistent: attackers usually enter through IT networks, remote access or third-party connections, then move toward operational systems. Defenses that assume the control network is isolated do not hold.
15.2 Frameworks
- *NIST SP 800-82 Rev. 3, Guide to Operational Technology Security (September 2023),* gives an overview of OT architectures and threats and a security program approach mapped to the NIST risk management framework and cybersecurity framework.
- The ISA/IEC 62443 series defines security for industrial automation and control systems, including the concepts of zones (groups of assets with common security requirements) and conduits (the controlled communication paths between them), security levels, and requirements for asset owners, integrators and product suppliers.
- IEEE 1686-2022 specifies cyber security capabilities for IEDs, such as user authentication, role-based access, audit logging and firmware integrity, which utilities can require in procurement.
- IEC 62351 addresses security for power-system communication protocols, including IEC 61850 and IEC 60870-5.
- NERC CIP standards are mandatory for owners and operators of the bulk electric system (BES).
15.3 Architecture controls
Keentel's baseline for any SCADA system, regulated or not:
- Segmentation. Separate Levels 0–3 from the enterprise with a DMZ and firewalls; separate safety systems from control systems; separate substations from each other where practical.
- Remote access. Through a jump host in the DMZ, with multi-factor authentication, session recording, time limits and named accounts. No direct remote-desktop tools on HMIs or engineering stations.
- Least privilege. Operators can operate; engineers can configure; few people can do both, and every privileged action is logged.
- Asset inventory and baselines. A current list of every device, firmware version, open port and connection.
- Patching and vulnerability management. Tested and scheduled, with compensating controls when patches cannot be applied.
- Backups. Offline, tested copies of server images, controller programs, relay settings and network configurations.
- Monitoring. Network monitoring inside the control network that understands industrial protocols, with alerts reviewed by someone who knows what normal looks like.
- Incident response. A plan that covers operating manually, restoring systems and reporting.
15.4 NERC CIP for power-sector SCADA
For registered entities, NERC CIP turns many of these practices into requirements. The scope depends on the impact rating of the BES Cyber Systems under CIP-002.
| Standard | Topic |
|---|---|
| CIP-002 | BES Cyber System categorization (high, medium, low impact) |
| CIP-003 | Security management controls, including low-impact requirements |
| CIP-004 | Personnel and training |
| CIP-005 | Electronic Security Perimeters and remote access |
| CIP-006 | Physical security of BES Cyber Systems |
| CIP-007 | System security management: ports, patches, malware, logging, accounts |
| CIP-008 | Incident reporting and response planning |
| CIP-009 | Recovery plans |
| CIP-010 | Configuration change management and vulnerability assessments |
| CIP-011 | Information protection |
| CIP-012 | Protection of real-time data exchanged between control centers |
| CIP-013 | Supply chain risk management |
| CIP-014 | Physical security of critical transmission stations |
| CIP-015 | Internal network security monitoring |
FERC approved CIP-015-1 in Order No. 907, issued June 26, 2025 (Docket RM24-7). The standard requires internal network security monitoring inside the Electronic Security Perimeters of high-impact BES Cyber Systems and medium-impact systems with external routable connectivity. FERC also directed NERC to extend monitoring to certain systems outside the perimeter. Entities should confirm the applicable effective dates in the current implementation plan.
Worked example 15 — how is a substation rated under CIP-002?
CIP-002 Attachment 1 uses "bright-line" criteria. Among the medium-impact criteria are transmission facilities operated at 500 kV or above, and transmission facilities operated between 200 kV and 499 kV at a single station or substation where the aggregate weighted value of connected lines exceeds 3,000. In the weighting table, lines at 200–299 kV count 700 and lines at 300–499 kV count 1,300. Lines below 200 kV are not counted in this criterion. (Confirm against the current version of CIP-002 and its Attachment 1 before relying on these values.)
- Substation A has four 345 kV lines and two 230 kV lines: 4 × 1,300 + 2 × 700 = 6,600, above 3,000. Its BES Cyber Systems are medium impact under this criterion.
- Substation B has two 345 kV lines and several 138 kV lines: 2 × 1,300 = 2,600. Unless another criterion applies, its BES Cyber Systems are low impact.
The difference is large. Medium-impact systems bring Electronic Security Perimeters, access management, patching, logging and, under CIP-015, internal monitoring. Low-impact systems carry the lighter CIP-003 requirements. Getting the rating right at design time shapes the whole SCADA architecture.
Worked example 16 — ranking risks for a plant SCADA system
A simple likelihood-times-consequence score (each 1 to 5) helps prioritize improvements. Illustrative findings from a plant review:
| Finding | Likelihood | Consequence | Score |
|---|---|---|---|
| Remote access to HMI without multi-factor authentication | 4 | 5 | 20 |
| Flat network linking business and control systems | 3 | 5 | 15 |
| Unpatched HMI operating system | 4 | 3 | 12 |
| Shared engineering laptop used at several sites | 3 | 4 | 12 |
| No offline backups of controller programs | 2 | 5 | 10 |
Scores are illustrative and should come from a structured assessment. The ranking still makes the point: fixing remote access and segmentation usually buys the most risk reduction for the least money.
Keentel Study Spotlight — NERC CIP and OT security assessment. Keentel performs CIP-002 categorization, evaluates SCADA and substation automation designs against CIP-005, CIP-007, CIP-010 and CIP-015, assesses non-regulated sites against NIST SP 800-82 and ISA/IEC 62443, and delivers a prioritized remediation plan with drawings and evidence that auditors can follow.
16. Physical design, codes and environment
SCADA hardware lives in substations, plant control rooms, outdoor cabinets and hazardous areas. The physical design matters as much as the software.
- Control panels. Industrial control panels are commonly built and listed to UL 508A, which also gives a method for determining the panel's short-circuit current rating. NEC Article 409 requires that rating to be marked and coordinated with the available fault current.
- Substation environment. Communications equipment in substations should meet the environmental and electromagnetic immunity requirements of the IEEE 1613 family, so that switching surges and fault currents do not disrupt it.
- Hazardous locations. Instruments and enclosures in classified areas must be suitable for the location under NEC Articles 500 through 506, such as Class I, Division 2 equipment where flammable gases may be present under abnormal conditions.
- Power supplies. SCADA equipment should run from station dc batteries or uninterruptible power with enough ride-through to cover generator start or restoration. Loss of SCADA power during a disturbance is a common and avoidable failure.
- Grounding and surge protection. Communication cables entering substations, especially copper, need surge protection and isolation; fiber is preferred across ground-potential-rise zones.
- Fire protection and environment. Control rooms and server rooms need fire detection, appropriate suppression and environmental control.
How Keentel Engineering helps here. Keentel designs SCADA and relay panels, dc and UPS power, grounding, surge protection and communications cabling for substations and plants, and checks short-circuit current ratings and hazardous-area requirements against the NEC.
17. The project lifecycle: from specification to operation
17.1 Specification
A good SCADA specification defines functions, the points list, performance (scan rates, latency, availability), interfaces, security requirements, standards, documentation, training, testing and support. Vague specifications produce systems that meet the letter of the contract and fail in operation.
17.2 Design and configuration
Detailed design produces network drawings, rack and panel layouts, IP address plans, the data map, display designs, alarm settings and security configurations. Every item should be under version control.
17.3 Testing
| Test | Purpose |
|---|---|
| Factory acceptance test (FAT) | Verify software, displays, database, alarms and interfaces with simulated field data before shipment |
| Site acceptance test (SAT) | Verify the installed system end to end, including communications and failover |
| Point-to-point checkout | Confirm every point from the field device to the HMI and historian, with correct scaling, sign and alarm |
| Control checkout | Operate every controllable device from SCADA under safe conditions, including select-before-operate |
| Failover and recovery tests | Switch servers, break network paths, remove power, and restore from backup |
| Time synchronization test | Confirm time quality at every device and the event time-stamp path |
| Telemetry acceptance | Demonstrate ISO or transmission operator telemetry to the receiving party's satisfaction |
| Security acceptance | Confirm ports, accounts, logging, remote access and monitoring match the design |
17.4 Operation and change management
After go-live, the system must be maintained: patches, backups, configuration changes, alarm reviews, performance monitoring, and periodic reassessment. For NERC-registered entities, CIP-010 configuration management and CIP-007 security management make much of this mandatory.
Keentel Study Spotlight — FAT and SAT witnessing. Keentel writes acceptance test procedures, witnesses FAT and SAT on the owner's behalf, and verifies point-to-point checkout, telemetry, failover and time synchronization, producing signed records that support commissioning, ISO acceptance and compliance.
18. SCADA data and NERC obligations beyond CIP
Cyber security gets most of the attention, but SCADA data also carries other NERC obligations. Designing for them at the start avoids expensive retrofits.
- Data specifications (TOP-003 and IRO-010). Transmission operators, balancing authorities and reliability coordinators issue documented specifications for the data they need from registered entities, including content, periodicity, format and delivery method. A plant or substation SCADA design must deliver exactly what the specification asks for, and owners should keep evidence that it does.
- Communications (COM-001 and COM-002). Operating entities must have reliable interpersonal communication and data exchange capabilities, with alternatives when the primary path fails. SCADA communications design and testing support these obligations.
- Backup control (EOP-008). Reliability coordinators, balancing authorities and transmission operators must keep backup functionality to continue operating if their primary control center is lost. That usually means a backup SCADA/EMS site with its own data paths, tested periodically.
- Disturbance monitoring (PRC-002 and PRC-028). Sequence-of-events recording, fault recording and dynamic disturbance recording are governed by PRC-002 for bulk electric system elements and PRC-028 for inverter-based resources. SCADA sequence-of-events data supplements these records but usually cannot replace a dedicated recorder: SCADA analog values are reported every few seconds with deadbands, while disturbance recorders capture waveforms and high-rate data. Keentel's PRC-028 guide covers the recorder requirements in detail.
- Model validation (MOD-026, MOD-027 and MOD-033). Generator and plant model validation and system model validation rely on recorded data from disturbances. Historians with light compression and accurate time stamps on point-of-interconnection values make that evidence usable.
- Event analysis (PRC-004 and PRC-030). Analyzing protection system operations and unexpected changes in inverter-based resource output depends on time-aligned records from relays, plant controllers, SCADA and historians.
Worked example 17 — why SCADA cannot replace a disturbance recorder
A fault on a 345 kV line near a solar plant lasts 4 cycles, about 67 ms. The plant's SCADA scans point-of-interconnection real power every 2 seconds with a 1 MW deadband. A disturbance recorder samples voltage and current at several kilohertz and stores derived quantities at rates up to tens of samples per second.
- Chance that a 2-second SCADA scan lands inside the 67 ms fault ≈ 0.067 / 2 ≈ 3.4%.
- Even if it does, SCADA reports one averaged value, not the waveform, the voltage dip profile, or the plant's reactive current response.
SCADA tells you that something happened and roughly when. The disturbance recorder tells you what happened. Both are needed, and both must share a time reference.
How Keentel Engineering helps here. Keentel maps each NERC data obligation — TOP-003 and IRO-010 specifications, disturbance monitoring, model validation evidence and event analysis — to the SCADA, historian and recorder design, so the plant or substation produces the evidence it will be asked for.
19. Distribution automation
Distribution SCADA has grown from monitoring substation breakers to controlling devices along the feeder: reclosers, switches, capacitor banks, voltage regulators and, increasingly, customer-sited resources. Two applications stand out:
- Fault location, isolation and service restoration (FLISR). Line devices detect a fault, the system isolates the faulted section, and switches restore power to healthy sections from adjacent feeders, often in under a minute. FLISR can be centralized in an ADMS, distributed among peer devices, or run in a substation controller. Each approach has different communications and testing needs.
- Volt/var optimization (VVO). Coordinated control of load tap changers, regulators and capacitor banks, and now smart inverters, to flatten voltage profiles and reduce losses or demand. VVO depends on accurate, timely voltage measurements along the feeder.
Both rely on communications that may run through thousands of field radios or cellular modems, a scale at which device management, firmware updates and security become major tasks. Distribution systems with high levels of rooftop solar and batteries also need DERMS capabilities and protocols such as IEEE 2030.5 to coordinate customer-owned devices.
How Keentel Engineering helps here. Keentel designs and reviews FLISR and volt/var schemes, including the protection coordination checks for each restoration configuration and the communications design for the field devices involved.
20. Virtualization, cloud services and remote monitoring
Modern SCADA servers are often virtual machines on a small cluster of physical hosts. Virtualization makes redundancy, backup and recovery easier, but it concentrates risk: a fault or compromise in the virtualization layer affects every server on it. Keentel looks for redundant hosts on separate power, isolated management networks, and recovery procedures tested at the virtualization layer as well as for individual servers.
Cloud services are increasingly used for historians, analytics, fleet monitoring and remote diagnostics. They bring real benefits, particularly for renewable fleets with many unattended sites. The design questions are:
- Does any control path depend on the cloud service? It should not. Supervisory control should continue if the cloud link is lost.
- Is data sent outward only, through a DMZ, ideally with one-way transfer where the risk justifies it?
- Who can reach the site through the vendor's platform, and how is that access controlled and logged?
- For NERC-registered systems, does the arrangement create interactive remote access or external routable connectivity that brings additional CIP requirements?
How Keentel Engineering helps here. Keentel reviews virtualization, cloud historian and vendor remote-monitoring arrangements for operational dependence, data-flow direction and CIP implications, and recommends designs that keep supervision local and send data outward safely.
21. Migrating legacy SCADA
Most SCADA work is not greenfield. Owners replace masters, RTUs and communications while keeping the lights on. A migration plan should cover:
- Inventory and discovery. Every point, device, protocol, link and undocumented interface. Legacy systems almost always contain points nobody remembers.
- Parallel operation. Running old and new masters side by side, with the new system in monitor-only mode until its data matches.
- Cutover sequence. Moving sites one at a time, with rollback plans and operations staffed for each cutover.
- Database conversion. Translating point definitions, alarm limits and displays, followed by full point-to-point checkout, not just spot checks.
- Training. Operators need time on the new displays before cutover, especially when moving to high-performance HMI styles.
- Retirement. Removing old equipment, accounts and communication paths, which otherwise remain as forgotten entry points.
Keentel Study Spotlight — SCADA migration planning. Keentel inventories legacy systems, designs the target architecture, writes the cutover and test plan, and supports each site cutover, so that operators never lose visibility during the transition.
22. The ten most common SCADA mistakes Keentel finds
1. Sign and scaling errors in real and reactive power, often discovered only when an ISO questions the data.
2. Time stamps applied by the server on arrival instead of at the source, making event records unreliable.
3. Integrity polls that swamp serial or radio links, causing slow updates during storms.
4. Alarm floods after switching events because nothing was rationalized or suppressed.
5. Remote access through tools installed directly on HMIs without multi-factor authentication.
6. Flat networks with business and control traffic on the same segments.
7. Redundant servers that have never been failed over under realistic conditions.
8. No offline backups of controller programs and relay settings.
9. Undocumented gateways and hops that add latency nobody accounted for.
10. SCADA equipment without battery-backed power, so that visibility is lost during the very events operators most need to see.
How Keentel Engineering helps here. Each of these mistakes appears on Keentel's review checklist, so they are caught on paper or at FAT rather than in operation or in an audit.
23. A design review checklist
| Area | Questions to answer |
|---|---|
| Functions | Which functions are supervisory and which are local? What happens on loss of communications? |
| Points list | Is every point defined with source, scaling, sign, deadband, class, alarm limits and owner? |
| Performance | What are the scan, latency and availability targets, and has the budget been calculated end to end? |
| Communications | Are links sized for integrity polls and event storms? Is there a radio path study? |
| Redundancy | Which components are redundant, how is failover triggered, and what are the common-cause risks? |
| Time | What is the time source, the distribution method and the verified accuracy at each device? |
| Alarms | Is there an alarm philosophy, rationalized database and performance target? |
| HMI | Do displays follow a consistent hierarchy and ISA-101 principles? |
| Historian | Are compression, retention and time quality suitable for compliance and event analysis? |
| Security | Are zones, conduits, DMZ, remote access, monitoring, backups and patching defined? |
| Compliance | What CIP impact rating applies? What ISO telemetry and data specifications apply? |
| Physical | Are panels, power supplies, grounding, surge protection and hazardous-area ratings correct? |
| Testing | Are FAT, SAT, failover, time sync and telemetry tests defined with acceptance criteria? |
Part C — Three Anonymous US Case Studies
The three case studies below are composites drawn from the kinds of projects Keentel supports. Names, locations and identifying details are omitted or changed, and the numbers are illustrative. They show how the principles in this guide play out on real projects.
Case study 1 — Modernizing substation SCADA at a municipal utility
The situation
A municipal electric utility in the Southeast serves about 40,000 customers from eleven distribution substations fed at 69 kV and 115 kV, with 12.47 kV distribution. Its SCADA master was nearly twenty years old. Most substations were polled over a shared licensed radio channel at 9,600 bit/s using DNP3, and several older sites still used hardwired RTUs with a handful of analog transducers.
Operators had three complaints. Breaker status sometimes took more than half a minute to update after a trip. During storms the alarm list scrolled faster than anyone could read it. And the utility's new tie with a neighboring transmission owner had created questions about NERC registration and CIP obligations that nobody in the small engineering group could answer with confidence.
What Keentel found
Keentel began with a functional and architectural review. The main findings were:
- Polling cycle. With about 40 RTUs and IEDs on the radio channel and integrity polls every cycle, the full polling loop took about 30 seconds, consistent with Worked example 4. Status changes were not reported by exception at all, so a breaker trip waited for the next poll of that site.
- Data quality. At two substations, feeder real power was displayed with the wrong sign, and three transformers showed megavars that did not match the relays because of a scaling error introduced during an earlier relay replacement.
- Alarms. The busiest console averaged about 600 alarms a day, more than double the commonly used manageable level. A single feeder lockout typically produced 30 to 50 alarms, including undervoltage alarms from every downstream device.
- Time. Only two substations had GPS clocks. Elsewhere, relay clocks drifted by seconds, so sequence-of-events records could not be merged.
- Security. The SCADA server and the utility's business network shared a flat network. Vendors used a remote-desktop tool installed directly on the SCADA server for support.
- Compliance. Applying the CIP-002 criteria, the utility's BES Cyber Systems were low impact. That carried CIP-003 obligations for security awareness, physical and electronic access controls, transient cyber asset controls and incident response, which had not been formally addressed.
What changed
Keentel developed a three-phase program that the utility could fund over two budget years.
Phase 1: quick wins (three months). The DNP3 configuration was changed to unsolicited reporting of event data for status points, with integrity polls moved to every 30 minutes. The polling loop for analogs fell to about 12 seconds on the existing radio, and breaker status updates now arrived in two to three seconds. The scaling and sign errors were corrected after a point-by-point check against relay settings. Keentel facilitated two alarm rationalization workshops with operators, removed or demoted about 40% of the alarm database, and added state-based suppression so that downstream undervoltage alarms were blocked when an upstream breaker opened. Average alarms on the busiest console fell to about 180 a day.
Phase 2: communications and time (one year). The utility's fiber build-out reached seven of eleven substations. Keentel designed an Ethernet ring for those sites with managed switches and moved them to DNP3 over IP, leaving the remaining four on an upgraded radio system with a path study confirming 25 to 30 dB of fade margin. GPS clocks with holdover were installed at every substation, distributing IRIG-B to existing relays and PTP to new devices. New substation automation controllers took over from the old RTUs, collecting data directly from relays.
Phase 3: security and compliance (in parallel). The SCADA network was separated from the business network with a firewall and a small DMZ hosting a historian replica and a jump host with multi-factor authentication. The vendor remote-desktop tool was removed from the server. Keentel wrote the utility's CIP-003 low-impact program documents: cyber security policy, security awareness, physical security controls, electronic access controls for routable connections, transient cyber asset and removable media procedures, and the incident response plan, and trained staff to maintain them.
Results
| Measure | Before | After |
|---|---|---|
| Breaker status update time | Up to ~30 s | 2–3 s (radio), under 1 s (fiber) |
| Alarms per day, busiest console | ~600 | ~180 after Phase 1; ~140 after Phase 2 |
| Substations with synchronized time | 2 of 11 | 11 of 11 |
| Telemetry sign or scaling errors | 5 found | 0 after point-to-point checkout |
| Business and SCADA networks | Shared | Segmented with DMZ |
| CIP-003 low-impact program | Not documented | Documented and trained |
Timeline
| Month | Activity |
|---|---|
| 0–1 | Functional review, points-list audit, alarm statistics, CIP-002 categorization |
| 2–3 | DNP3 reconfiguration, scaling and sign corrections, two alarm rationalization workshops |
| 4–9 | Fiber ring design and installation at seven substations; radio path study and radio upgrade at four |
| 6–12 | GPS clocks, IRIG-B and PTP distribution; substation automation controllers replace legacy RTUs |
| 3–12 | Network segmentation, DMZ, jump host; CIP-003 program documents and training |
| 12–15 | Site acceptance testing, point-to-point checkout and failover tests at every substation |
Questions the utility now asks of every project
- Does this change add points, and are they in the version-controlled points list with source, scaling and sign?
- Does it add a communication path, and has the latency and security of that path been reviewed?
- Does it add alarms, and have they been rationalized against the alarm philosophy?
- Does it change the CIP-002 categorization of any substation?
Lessons
The biggest operational improvement — fast status updates — came from configuration, not new hardware. Alarm rationalization delivered visible benefits within weeks. And because the utility determined its CIP impact rating early, the security work could be scoped correctly and folded into the communications upgrade rather than retrofitted later.
Case study 2 — Fixing ISO telemetry at a 200 MW solar and storage plant
The situation
A 200 MW solar plant with a 100 MW, four-hour battery system in the south-central US reached commercial operation on schedule, but within weeks the ISO notified the owner that several telemetered values were failing its quality checks. Real power at the point of interconnection occasionally lagged the ISO's own measurements by several seconds, reactive power had the wrong sign when the plant absorbed vars, battery state of charge sometimes froze for minutes, and the plant controller's status flags did not match observed behavior. The ISO asked for a corrective plan.
What Keentel found
Keentel was engaged as owner's engineer and traced the data path from each measuring device to the ISO's system.
- Path and latency. Values went from the substation revenue meter and relays to the plant SCADA controller, then to the owner's fleet operations center over a cellular link, and from there to the ISO over ICCP. The plant controller polled some devices every 2 seconds, the fleet system collected data every 2 seconds and batched it for ICCP, and the cellular link added variable delay. The worst-case path resembled Design B in Worked example 10: more than 5 seconds.
- Sign convention. The plant controller used a generator convention for reactive power, the relay used a load convention, and the mapping to ICCP had been built from the relay. When the plant absorbed vars, the ISO saw them as injection.
- Battery data. State of charge came from the battery energy management system over Modbus. When that system was busy with dispatch updates, it occasionally failed to respond, and the plant controller held the last good value without marking it suspect. The ISO saw a frozen value with good quality.
- Status flags. Several plant controller status flags were mapped to the wrong bits after a firmware update, and nobody had rechecked them.
- Time stamps. The fleet system applied its own time stamps on arrival, so plant event records and ISO data could not be aligned during a voltage disturbance the ISO was investigating.
What changed
- A direct path. Working with the owner and the ISO, Keentel designed a direct, redundant telemetry path from the plant to the ISO using dedicated communication circuits, with the fleet center receiving a copy rather than sitting in the critical path. Measured end-to-end latency fell to about 2.5 seconds.
- One sign convention. Keentel documented a single sign convention for every real and reactive power point, aligned with the ISO's requirements, and corrected the mappings in the plant controller, SCADA and ICCP tables.
- Data quality flags. The Modbus link to the battery system was reconfigured with a dedicated polling task and timeouts, and the plant controller was set to mark values suspect or invalid after a defined number of missed polls. Quality flags were carried through to the ISO.
- Status mapping. Every status flag was checked against the controller documentation and tested by forcing each condition during a planned outage.
- Time. A GPS clock with PTP distribution was added to the plant network, and all devices were set to time-stamp at the source. The historian was configured with lighter compression for point-of-interconnection values, so future event reviews would have full detail.
- Testing and evidence. Keentel wrote and witnessed a telemetry acceptance test with the ISO, documenting each point's source, scaling, sign and latency.
Key numbers
| Measure | Before | After |
|---|---|---|
| End-to-end real power latency to ISO | Up to ~5.5 s | ~2.5 s |
| Reactive power sign errors | Present for absorbing vars | Corrected and documented |
| Frozen battery state-of-charge values reported as good | Several per week | None; stale data flagged |
| Status flags verified against documentation | Not checked after firmware update | All tested by forcing conditions |
| Devices time-stamping at source | Few | All, with PTP from a GPS clock |
Timeline
| Week | Activity |
|---|---|
| 1–2 | Data-path trace from each device to the ISO; latency measurements |
| 3–4 | Sign convention memo; mapping corrections; status flag verification during a planned outage |
| 5–10 | Direct telemetry circuits installed and configured with the ISO |
| 6–8 | GPS clock and PTP distribution; historian compression changes |
| 11–12 | Telemetry acceptance test witnessed with the ISO; issue closed |
Results
The ISO closed the issue after the acceptance test. The plant's data later supported a ride-through investigation in which the time-aligned records showed the plant had behaved as designed, avoiding a disputed performance finding. The owner adopted the telemetry checklist for its other plants.
Lessons
Telemetry failures at renewable plants are rarely about one bad device. They come from long data paths, inconsistent conventions and quality flags that hide stale data. A single, documented data map from measuring device to ISO — with a latency budget, a sign convention and an acceptance test — prevents most of them. Plants subject to newer IBR performance and disturbance-monitoring requirements gain even more from accurate, time-aligned data.
Case study 3 — Integrating EPMS and utility SCADA at a data center substation
The situation
A data center campus in the Mid-Atlantic was building its own 13.8 kV distribution system fed from a customer-owned substation stepping down from 138 kV. The design included two 138/13.8 kV transformers, medium-voltage switchgear with main-tie-main arrangements, UPS systems, diesel generators and an electrical power monitoring system (EPMS). The serving utility required telemetry and breaker status from the 138 kV interface and transfer-trip signals. The owner also wanted time-aligned event records across the utility interface, the 13.8 kV system and the UPS systems, after a previous campus had suffered an unexplained load transfer during a grid disturbance.
What Keentel found during design review
- Two systems, no common time. The EPMS, the substation relays and the UPS controllers each kept their own clocks. Event records from an earlier site could not be put in order.
- Mixed protocols. The substation relays spoke IEC 61850 and DNP3, the switchgear meters Modbus TCP, and the UPS and generator controllers a mix of Modbus and proprietary protocols through gateways.
- Control authority unclear. Both the EPMS and a local substation HMI could operate 13.8 kV breakers, with no interlocking between them and no defined hierarchy.
- Utility interface. The utility required DNP3 telemetry to its SCADA with specific scan, latency and security requirements, and expected the customer to keep its systems isolated from the utility's network apart from a defined interface.
- Security. The EPMS was on the same network as the building management system, which in turn had a remote-access connection for its service provider.
What changed
- A single time architecture. Keentel specified a GPS master clock with holdover in the substation, distributing PTP under the IEEE C37.238 profile over the substation network and NTP to the EPMS servers. UPS and generator controllers that could not accept PTP received time through gateways, and their time quality was documented.
- Sequence-of-events design. Every breaker, transfer switch and UPS mode change was assigned an event point time-stamped at the source with 1 ms resolution, collected by the substation automation controller and the EPMS, and stored in a historian with no compression on event points.
- Defined control authority. The substation HMI was made the local authority for 138 kV and 13.8 kV switching, with the EPMS limited to monitoring and to commands enabled only by a local-remote selector. Interlocks were implemented in the relays, not in software.
- A clean utility interface. The utility's DNP3 link terminated on a dedicated port of the substation automation controller behind a firewall, with a point list agreed in writing and tested end to end.
- Segmentation. The EPMS and substation automation network were separated from the building management system. Service provider access went through a jump host with multi-factor authentication and session recording.
- Testing. Keentel wrote and witnessed FAT and SAT procedures that included breaker operations, transfer sequences and a simulated utility disturbance using relay test sets. Each test confirmed that event records from the relays, switchgear and UPS systems appeared in the correct order within a few milliseconds.
Key numbers
| Item | Design value |
|---|---|
| Utility interface | 138 kV, two transformers to 13.8 kV main-tie-main switchgear |
| Event points time-stamped at source | About 1,200 across relays, switchgear, transfer switches and UPS systems |
| Event time-stamp resolution | 1 ms |
| Verified time alignment across devices at SAT | Within a few milliseconds, including gateway-connected UPS controllers |
| Utility DNP3 point list | Agreed in writing; tested end to end before energization |
| Remote access path | Jump host with multi-factor authentication and session recording |
What the owner changed in its campus standard
- Every new building's electrical systems connect to the same time architecture.
- Control authority for medium-voltage switching is defined in a single document and enforced by relay interlocks.
- The utility interface point list and test procedure are reused, with site-specific values.
- Building management and electrical monitoring networks are always separate, with vendor access only through the jump host.
Results
During the first summer of operation, a fault on the utility's 138 kV system caused a brief voltage sag at the campus. The time-aligned records showed the sequence clearly: the sag, the UPS systems transferring to battery, the 13.8 kV loads riding through, and the UPS returning to normal operation. The investigation took hours instead of weeks, and the owner could show the utility exactly how its load behaved.
Lessons
Data centers are now large enough to matter to the grid, and their electrical events increasingly need utility-grade records. Common time, source time-stamping, clear control authority and a clean, documented utility interface turn an EPMS into a reliable engineering tool. The same principles apply to any large load connecting at transmission voltage.
Part D — Technical FAQ
1. What does SCADA stand for, and what does it do?
SCADA stands for supervisory control and data acquisition. It collects measurements and status from equipment spread over a wide area, presents them to operators, raises alarms when something is abnormal, records history, and lets operators send commands and set points back to the field. The word "supervisory" is important: SCADA sets targets and oversees equipment, while fast control and protection run in local controllers and relays.
2. What are the main components of a SCADA system?
Field instruments and sensors; controllers such as PLCs, DCS controllers, RTUs and IEDs; communications networks and protocol gateways; SCADA servers holding the real-time database; operator stations and HMIs; a historian; an engineering workstation; a time source; and the security infrastructure around them, such as firewalls, a DMZ, remote access servers and monitoring sensors. In power systems, add ICCP links to other control centers and, often, phasor measurement units.
3. How is SCADA different from a DCS?
A DCS is a tightly integrated control system for a single plant or campus, designed for continuous, closed-loop control with fast, redundant networks. SCADA is designed to supervise assets spread over large areas with slower, less reliable communications, so it emphasizes polling, event reporting and time-stamping at the source. Many plants run a DCS internally and connect it to a utility or fleet SCADA above it. Modern products overlap, but the design priorities still differ.
4. How is a PLC different from an RTU?
Both are rugged industrial computers. A PLC is optimized for fast local control logic and input/output. An RTU is optimized for remote communications, event time-stamping, low power use and harsh environments, and often acts as a protocol gateway. Many current products do both. In substations, the RTU role is now usually filled by a substation automation controller that collects data from relays and meters.
5. Is SCADA "real time"?
Near-real time. Utility SCADA typically refreshes analog values every 2 to 4 seconds and reports status changes by exception within a few seconds. That is fast enough for supervision but far too slow for protection or closed-loop control, which run in milliseconds in local devices. A design that depends on SCADA for fast control will fail when communications slow down.
6. What protocols are used in power-system SCADA?
In North America, DNP3 (IEEE 1815) dominates between control centers, RTUs and IEDs. IEC 61850 is widely used inside new substations, including GOOSE messaging between relays. Modbus remains common for meters, inverters, battery systems and drives. ICCP, also called TASE.2 (IEC 60870-6), links utility control centers and ISOs. IEEE C37.118 is used for synchrophasors, and IEEE 2030.5 and OpenADR for distributed energy resources and demand response.
7. What is the difference between polling and report-by-exception?
With polling, the master asks each device for its data on a schedule. With report-by-exception, the device sends only values that have changed, either when polled for events or unsolicited. Exception reporting saves bandwidth and speeds up status changes. A sound design combines frequent event polls or unsolicited reports with occasional integrity polls that refresh every value. Worked example 3 shows an integrity poll of a 5,000-point substation is about seven times larger than a typical event report.
8. How do I size communications for a substation or plant?
Count the points, estimate bytes per point for integrity and event data, add protocol overhead, and calculate the time each transfer takes at the link's speed. Then check the worst case: an event storm after a fault, when many points change at once. On slow serial or radio links, schedule integrity polls infrequently and rely on event reporting. Keentel models these cases before selecting radios or circuits.
9. How fast must telemetry reach an ISO?
It depends on the ISO and the type of resource. Requirements typically specify the points to be sent, scan rate, accuracy, latency, availability and quality flags. Owners should work from the receiving party's current telemetry requirements and calculate an end-to-end latency budget, as in Worked example 10, rather than assume a design meets them.
10. What is a historian, and how much storage does it need?
A historian is a time-series database that stores process values and events for trending, reporting, analysis and compliance evidence. Storage depends on tag count, sample rate, bytes per value and compression. Worked example 7 shows 20,000 tags at one sample per second need about 10 TB per year uncompressed, or roughly 0.3–1 TB with typical compression. Compression should be lighter for compliance and event-analysis tags.
11. Should business users connect directly to the operations historian?
No. Business users should read from a replica in the industrial DMZ. Direct connections from the enterprise network to the operations historian create a path for attackers and malware into the control network and are one of the most common architectural weaknesses Keentel finds.
12. What is the Purdue model?
The Purdue Enterprise Reference Architecture divides industrial systems into levels: Level 0 is the physical process, Level 1 basic control, Level 2 supervisory control, Level 3 site operations, Level 3.5 an industrial DMZ, and Levels 4 and 5 the enterprise. It is widely used, with security refinements from ISA/IEC 62443 and NIST SP 800-82, to decide where systems belong and where traffic should be controlled.
13. What are zones and conduits?
In the ISA/IEC 62443 series, a zone is a group of assets that share security requirements, and a conduit is a controlled communication path between zones. Designing with zones and conduits forces the designer to decide which systems may talk to which, through what path, and with what protection.
14. Which NERC CIP standards apply to SCADA?
For owners and operators of the bulk electric system, CIP-002 determines whether BES Cyber Systems are high, medium or low impact, and that rating sets which requirements apply. CIP-003 through CIP-011 cover security management, personnel, electronic perimeters and remote access, physical security, system security, incident response, recovery, configuration management and information protection. CIP-012 protects real-time data between control centers, CIP-013 covers supply chain risk, CIP-014 physical security of critical transmission stations, and CIP-015 internal network security monitoring.
15. What is CIP-015?
CIP-015-1 requires internal network security monitoring inside the Electronic Security Perimeters of high-impact BES Cyber Systems and medium-impact systems with external routable connectivity. The purpose is to detect malicious activity that has already passed the perimeter. FERC approved it in Order No. 907 on June 26, 2025, and directed NERC to extend monitoring to certain systems outside the perimeter. Entities should check the current implementation plan for effective dates.
16. How do I know if my substation is medium or low impact under CIP-002?
Apply the bright-line criteria in CIP-002 Attachment 1. For transmission, facilities at 500 kV and above, and certain stations between 200 kV and 499 kV whose connected lines exceed an aggregate weighted value of 3,000, are among the medium-impact criteria. Other criteria cover generation, control centers, special protection schemes and more. Worked example 15 shows the weighting calculation. Always confirm against the current version of the standard, because criteria have been revised over time.
17. Why does time synchronization matter so much?
Because events in a power system happen within milliseconds, and reconstructing them requires knowing their order. At 60 Hz, a 1 ms time error equals about 21.6 electrical degrees. Without a common time source, sequence-of-events records from different devices cannot be merged with confidence. Time quality also underpins disturbance analysis, ride-through investigations and synchrophasor applications.
18. Should I use PTP, IRIG-B or NTP?
NTP is adequate for SCADA servers, HMIs and historians, where millisecond accuracy is enough. IRIG-B from a GPS clock provides microsecond-class accuracy over dedicated wiring and is common in existing substations. IEEE 1588 PTP with the IEEE C37.238 power profile delivers sub-microsecond accuracy over Ethernet with PTP-aware switches and is the preferred choice for new substation networks.
19. What alarm rate is acceptable for an operator?
Commonly used benchmarks drawn from ISA-18.2 and EEMUA 191 suggest an average of about one alarm per 10 minutes per operator console in steady operation, about 300 per day as the maximum manageable, and fewer than 1% of time in flood, where a flood is more than 10 alarms in 10 minutes. Each organization should set its own targets in an alarm philosophy and measure against them.
20. What is alarm rationalization?
It is a structured review of every configured alarm to confirm that it indicates an abnormal condition, has a defined consequence and operator action, and has the right priority and set point. Alarms that fail the test are removed, demoted to events, or redesigned. State-based suppression, deadbands and delay timers fix floods and chattering. Rationalization is the core activity of the ISA-18.2 lifecycle.
21. What is a high-performance HMI?
It is an approach to operator display design, consistent with ANSI/ISA-101.01-2015, that uses muted backgrounds and gray graphics so that color stands out only for abnormal conditions, a clear display hierarchy from overview to detail, analog indicators with normal ranges, and consistent navigation and commands. The aim is to help operators recognize abnormal situations early.
22. How should remote access to SCADA be handled?
Through a jump host in the DMZ, with multi-factor authentication, named accounts, least privilege, session recording, time-limited access and monitoring. Remote-access tools should never be installed directly on HMIs, SCADA servers or engineering workstations. For NERC-registered medium- and high-impact systems, CIP-005 sets specific requirements for interactive remote access.
23. What lessons do real incidents teach?
The 2015 attack on Ukrainian distribution companies showed that attackers who reach SCADA and remote-access tools can open breakers and slow recovery by disabling equipment. The 2016 attack showed malware that speaks industrial protocols directly. The 2021 Florida water treatment case highlighted the danger of remote-access software on HMIs. The 2021 pipeline ransomware case showed how dependence on business systems can stop operations even without a control system compromise. The 2024 joint advisory on state-sponsored pre-positioning showed that attackers are targeting energy and water networks to prepare for possible disruption.
24. How should SCADA servers be made redundant?
Use a hot-standby pair with continuous database synchronization, separate power feeds, staged patching and validated configuration changes, plus a tested backup control capability. Worked example 5 shows that common-cause failures can dominate the unavailability of a redundant pair, so they deserve as much attention as the redundancy itself. Test failover under realistic load, not just at commissioning.
25. What are PRP and HSR?
They are redundancy protocols defined in IEC 62439-3. Parallel Redundancy Protocol sends every frame over two independent networks, so loss of one network causes no interruption. High-availability Seamless Redundancy does the same within a ring. They are used where IEC 61850 protection messaging cannot tolerate the recovery time of conventional ring protocols.
26. How does SCADA interact with a plant power controller at a solar or battery plant?
SCADA provides the operator interface, receives set points from the transmission operator or ISO, and sends telemetry outward. The plant controller does the fast regulation of voltage, reactive power, real power and frequency response at the point of interconnection, updating inverter commands many times per second. Worked example 11 shows the controller completing about 40 cycles for each SCADA set-point refresh.
27. Do data centers need utility-style SCADA?
Large data centers already run electrical power monitoring systems that work like SCADA. As campuses grow and connect at transmission voltage, they increasingly need utility-grade telemetry to the transmission operator, time-synchronized sequence-of-events records for disturbance investigations, clear control authority between monitoring and substation control systems, and strong segmentation from building systems with third-party remote access.
28. What codes apply to SCADA panels and field equipment?
Industrial control panels are commonly built and listed to UL 508A, which provides a method for determining short-circuit current rating; NEC Article 409 requires the rating to be marked. Equipment in hazardous locations must meet NEC Articles 500 through 506. Substation communications equipment should meet the IEEE 1613 environmental and immunity requirements. Power supplies, grounding and surge protection should follow utility practice and the NEC.
29. What testing should a new SCADA system receive?
Factory acceptance testing with simulated data, site acceptance testing of the installed system, point-to-point checkout of every point, control checkout of every controllable device, failover and recovery tests, time-synchronization verification, telemetry acceptance with the receiving ISO or transmission operator, and security acceptance against the design. Each test should have written procedures and acceptance criteria.
30. How can Keentel Engineering help with SCADA?
Keentel provides SCADA and substation automation design, points-list and data-map development, communications and latency studies, radio path studies, time synchronization design, alarm rationalization, historian and data-quality reviews, ISO telemetry design and acceptance testing, NERC CIP categorization and program development, OT security assessments against NIST SP 800-82 and ISA/IEC 62443, FAT and SAT witnessing, and owner's engineer services for utilities, renewable and storage plants, data centers and industrial facilities from 4 kV to 765 kV.
How Keentel Engineering Helps
Keentel Engineering supports SCADA, substation automation and telemetry projects from the first requirements meeting through commissioning and compliance, as an independent designer, studies provider and owner's engineer. We do not sell SCADA software or hardware.
| Service | What Keentel delivers | Outcome |
|---|---|---|
| Study basis and specification | Standards map, criteria, contingency list and deliverables agreed before modeling | No rework over criteria after results are in |
| Generator data audit | IEEE 115 / IEEE 1110 parameter review, inertia and base checks, typical-data flags | A dynamic database reviewers can trust |
| Excitation and PSS work | IEEE 421.2-style tests, IEEE 421.5 model validation, PSS tuning, limiter review under PRC-019-2 | Damped oscillations and coordinated limiters |
| Turbine-governor modeling | Manufacturer data translated into WECC-approved models; frequency response checks | Realistic frequency and island behavior |
| Clearing time inventory | Terminal-by-terminal relay, channel, breaker and breaker failure times from settings and nameplates | Accurate normal and delayed clearing margins |
| Critical clearing time studies | Normal and delayed clearing, fault type and location sensitivities | Clear breaker, protection and operating requirements |
| TPL-001-5.1 dynamic assessments | P1–P7 and extreme events, voltage, damping and frequency criteria, corrective action plans | Compliant planning assessments |
| Interconnection stability studies | Replication and review of transmission provider studies; mitigation alternatives | Fewer upgrades and remedial action schemes |
| Industrial islanding and load shedding | Separation detection, fast load shedding, motor reacceleration, resynchronization | Plants that survive utility disturbances |
| Protection in dynamics | Generator 78, 40, 21, 81, 24, 27/59 settings and line relay trajectories; PRC-026 evaluations | Protection that trips only when it should |
| IBR studies and compliance | IEEE 2800 / 2800.2 conformity, PRC-029-1 ride-through, generic model benchmarking, EMT in PSCAD | IBR plants that ride through and recover as modeled |
| Model verification | MOD-025, MOD-026, MOD-027 and MOD-026-2 testing and reports; MOD-032-2 data submittals | Audit-ready evidence and accurate planning models |
| Synchronous condensers and dynamic reactive | Sizing and specification of synchronous condensers, STATCOMs and grid-forming storage | Voltage recovery and system strength restored |
| Large loads and data centers | Ride-through, load-loss and islanding studies with UPS and on-site generation | Facilities that stay online and grids that stay stable |
| Owner's engineer | Design review, specification, witness testing and commissioning support | Confidence for owners, lenders and insurers |
Why Clients Choose Keentel
- Independent advice. We do not sell SCADA platforms or controllers, so our recommendations serve the owner.
- Power systems and automation together. Our engineers work on protection, substations, studies and NERC compliance, so we connect SCADA design to what the grid, the ISO and the auditor require.
- Calculations you can check. Every recommendation comes with its basis and arithmetic, as in the worked examples in this guide.
- Full voltage range. From 4 kV industrial and data center systems to 765 kV transmission.
- Compliance built in. NERC CIP categorization, ISO telemetry obligations and evidence are planned from the start, not retrofitted.
- Credentials. Florida registered engineering firm (Firm Registration No. 36853), NSPE, D-U-N-S registered, IEEE Senior Member leadership and BBB Accredited Business with an A+ rating, with offices in Tampa, Austin, Sacramento and Baltimore.
-
Talk to Keentel Engineering
Is your SCADA fast enough for the ISO, quiet enough for your operators, and segmented enough for today's threats? Keentel can tell you, with numbers.
- Phone: (813) 389-7871
- Email: contact@keentelengineering.com
- Book a 15-minute call: calendly.com/keentel-engineering/15min
- Web: keentelengineering.com
References
All facts drawn from these sources are paraphrased. Status of standards was checked against publisher listings in November 2026; confirm the current edition before relying on any requirement.
Standards and definitions
- IEEE C37.1-2007, IEEE Standard for SCADA and Automation Systems. IEEE lists this standard as inactive-reserved. https://standards.ieee.org/standard/C37_1-2007.html
- IEEE 1815-2012, IEEE Standard for Electric Power Systems Communications — Distributed Network Protocol (DNP3). IEEE lists the 2012 edition as inactive-reserved. https://standards.ieee.org/standard/1815-2012.html
- IEEE 1686-2022, IEEE Standard for Intelligent Electronic Devices Cybersecurity Capabilities, active standard, with a corrigendum. https://standards.ieee.org/ieee/1686/7207
- IEEE C37.238-2017, IEEE Standard Profile for Use of IEEE 1588 Precision Time Protocol in Power System Applications, active standard. https://standards.ieee.org/ieee/C37.238/6650
- IEEE C37.118.2, IEEE Standard for Synchrophasor Data Transfer for Power Systems. The 2011 edition is listed as inactive-reserved; check the current edition. https://standards.ieee.org/ieee/C37.118.2/4921/
- IEEE 2030.5, Smart Energy Profile Application Protocol, IEEE P2030.5 Working Group. https://sagroups.ieee.org/2030-5/
- IEEE 1613 family, environmental and testing requirements for communications networking devices in electric power substations (confirm current editions with IEEE).
- ANSI/ISA-18.2-2016, Management of Alarm Systems for the Process Industries. https://webstore.ansi.org/standards/isa/ansiisa182016 ; ISA InTech, "ISA18 alarm management standard updated," 2016. https://www.isa.org/intech-home/2016/may-june/departments/isa18-alarm-management-standard-updated
- ANSI/ISA-101.01-2015, Human Machine Interfaces for Process Automation Systems. https://webstore.ansi.org/standards/isa/ansiisa101012015 ; ISA InTech overview, 2020. https://www.isa.org/intech/2020/september-october/isa-101-01-human-machine-interfaces-for-process-au
- ISA/IEC 62443 series, Security for Industrial Automation and Control Systems; ISA-62443-3-2 preview (zones and conduits). https://www.isa.org/getmedia/661c718f-8e64-446d-acf9-2c6286db1b33/isa-62443-3-2-preview.pdf
- IEC 62439-3:2021, Industrial communication networks — High availability automation networks — Part 3: PRP and HSR. https://webstore.iec.ch/publication/64423
- IEC 61850 series, Communication networks and systems for power utility automation; IEC 62351 series on security; IEC 60870-6 (TASE.2/ICCP); IEC 60870-5 series (consult IEC for current editions).
- UL 508A, Industrial Control Panels; NFPA 70, National Electrical Code, Articles 409 and 500–506 (consult current editions adopted by the authority having jurisdiction).
- EEMUA Publication 191, Alarm Systems: A Guide to Design, Management and Procurement (benchmarks cited as commonly used values).
Government and regulatory sources
- NIST SP 800-82 Rev. 3, Guide to Operational Technology (OT) Security, September 2023. https://csrc.nist.gov/pubs/sp/800/82/r3/final ; NIST news release. https://www.nist.gov/news-events/news/2023/09/guide-operational-technology-ot-security-nist-publishes-sp-800-82-revision
- FERC, Order No. 907, Critical Infrastructure Protection Reliability Standard CIP-015-1 — Cyber Security — Internal Network Security Monitoring, Docket RM24-7-000, June 26, 2025. https://www.ferc.gov/sites/default/files/2025-06/RM24-7-000.pdf ; Federal Register, July 2, 2025. https://www.govinfo.gov/content/pkg/FR-2025-07-02/html/2025-12309.htm ; FERC June 2025 meeting summaries. https://ferc.gov/news-events/news/summaries-june-2025-commission-meeting
- NERC, CIP-002 Cyber Security — BES Cyber System Categorization, including Attachment 1 (versions 5.1a, 7 and 8). https://www.nerc.com/pa/Stand/Reliability%20Standards/CIP-002-8.pdf ; https://www.nerc.com/pa/Stand/Reliability Standards/CIP-002-5.1a.pdf ; CIP-002-5.1 Standard Application Guide. https://www.nerc.com/pa/comp/guidance/EROEndorsedImplementationGuidance/CIP-002-5.1_Standard_Application_Guide.pdf
- NERC Reliability Standards CIP-003 through CIP-015, TOP-003, IRO-010, EOP-008, COM-001 and COM-002. https://www.nerc.com
- CISA, ICS Alert IR-ALERT-H-16-056-01, Cyber-Attack Against Ukrainian Critical Infrastructure, 2016. https://cisa.gov/news-events/ics-alerts/ir-alert-h-16-056-01
- MITRE ATT&CK, 2016 Ukraine Electric Power Attack (campaign C0025). https://attack.mitre.org/campaigns/C0025/
- CISA and partners, Joint Cybersecurity Advisory AA24-038A, PRC State-Sponsored Actors Compromise and Maintain Persistent Access to U.S. Critical Infrastructure, February 7, 2024. https://cisa.gov/news-events/cybersecurity-advisories/aa24-038a ; https://www.cisa.gov/sites/default/files/2024-02/aa24-038a-jcsa-prc-state-sponsored-actors-compromise-us-critical-infrastructure_1.pdf
- Idaho National Laboratory, CyOTE case study on the 2021 pipeline ransomware incident. https://cyote.inl.gov/content/uploads/24/2025/12/CyOTE-Case-Study_Colonial-Pipeline.pdf
- NPR, "FBI called in after hacker tries to poison Tampa-area city's water with lye," February 9, 2021. https://www.npr.org/2021/02/09/965791252/fbi-called-in-after-hacker-tries-to-poison-tampa-area-citys-water-with-lye ; ASCE Civil Engineering magazine, March 2021. https://www.asce.org/publications-and-news/civil-engineering-source/civil-engineering-magazine/article/2021/03/cyberattack-on-florida-water-treatment-facility-should-prompt-security-assessments
- Council on Foreign Relations, Cyber Operations Tracker, Compromise of a power grid in eastern Ukraine. https://www.cfr.org/cyber-operations/compromise-of-a-power-grid-in-eastern-ukraine
- California Public Utilities Commission, Smart Inverter Working Group materials (Rule 21 and IEEE 2030.5). https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/rule21/smart-inverter-working-group/siwg_phase_2.pdf
- ERCOT, telemetry standards and ICCP communication handbook documents (consult the current ERCOT Nodal Operating Guides). https://www.ercot.com/files/docs/2014/08/27/11._telemetry_standards_approved_tac_050213.doc
- US Department of Energy, synchrophasor standards presentation. https://www.energy.gov/sites/default/files/%237%20Martin%20DOE_DC_SynchrophasorStandards_KM_061112.pdf
Background
- Purdue Enterprise Reference Architecture (overview). https://en.wikipedia.org/wiki/Purdue_Enterprise_Reference_Architecture
- Parallel Redundancy Protocol (overview). https://en.wikipedia.org/wiki/Parallel_Redundancy_Protocol
Related Keentel guides
- Power Plant Controller Compliance
- PRC-029-1 and IEEE 2800: Settings to Closed Loop
- PRC-028-1 IBR Disturbance Monitoring
- PRC-030-1 IBR Event Mitigation
- NERC Compliance Services Guide
- AI-Driven Monitoring for Resilient Clean-Energy Grids
- Data Center Tiers I–IV for MEP Engineers
- Protection Relay SAT for MV Switchgear
- MOD-032-2 Modeling Data
Disclaimer
This article is provided by Keentel Engineering for general technical education. It is not engineering, legal or regulatory advice for any specific facility, system or compliance program. Standards, NERC requirements, ISO telemetry rules and their effective dates change; confirm the current edition and the requirements of your Regional Entity, ISO, transmission operator and authority having jurisdiction before relying on any value here. Worked examples use illustrative inputs. Case studies are composites with identifying details removed or changed. Descriptions of public incidents summarize published reports and do not attribute responsibility beyond those reports. Keentel Engineering accepts no liability for decisions made on the basis of this article without a project-specific review.
Copyright and trademarks
© 2026 Keentel Engineering. All rights reserved. Written by Keentel Engineering. All text, worked examples, tables and figures in this article are original works of Keentel Engineering; no part may be reproduced, distributed or adapted without written permission. Short quotations with attribution are permitted for review and commentary. Facts drawn from third-party sources are cited in the references and are paraphrased, not reproduced. IEEE and the names of IEEE standards are trademarks of the Institute of Electrical and Electronics Engineers, Inc. ISA and the names of ISA standards are trademarks of the International Society of Automation. IEC is a trademark of the International Electrotechnical Commission. NFPA 70, National Electrical Code and NEC are registered trademarks of the National Fire Protection Association. UL is a trademark of UL LLC. NERC is a registered trademark of the North American Electric Reliability Corporation. Other names are the property of their respective owners.
| Office | Address | Phone |
|---|---|---|
| Head Office — Tampa | 400 N Ashley Dr STE #2600, Tampa FL 33602 | (813) 389-7871 |
| Austin | 5900 Balcones Drive STE 100, Austin TX 78731 | (512) 591-0752 |
| Sacramento | 1401 21st St Ste R, Sacramento CA 95811 | (916) 913-4524 |
| Baltimore | 306 W Redwood St STE 200, Baltimore MD 21201 | (410) 225-2181 |

About the Author:
Sandip "Sonny" R. Patel, P.E.
IEEE Senior Member · Founder & CEO, Keentel Engineering
In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.
For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.
His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.
Services

Let's Discuss Your Project
Let's book a call to discuss your electrical engineering project that we can help you with.

About the Author:
Sandip "Sonny" R. Patel, P.E.
IEEE Senior Member · Founder & CEO, Keentel Engineering
In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.
For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.
Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.
His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.
Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.
Leave a Comment
We will get back to you as soon as possible.
Please try again later.
















