Connecting large-scale generation and storage projects to regional transmission grids demands deep expertise, seamless ISO coordination, and bullet-proof engineering deliverables. Keentel Engineering has supported clients across PJM, ERCOT, WECC and NYISO with end-to-end Point-of-Interconnection (POI) services—from feasibility studies and dynamic modeling to protection scheme design and final energization. Our proven approach minimizes RFIs, accelerates commercial operation dates, and ensures first-time ISO acceptance, making us the go-to partner for renewable, storage, and hybrid projects seeking reliable, compliant transmission access.

Case Study 1: PJM 230 kV POI Interconnection for 250 MW Solar + Storage

Client: Confidential Renewable Developer
Scope: Full POI engineering for a 250 MW solar PV + BESS interconnection to a 230 kV PJM transmission line.

Services Provided:

  • PJM Feasibility, System Impact (SIS) & Facilities studies review
  • PSSE v35 dynamic and short-circuit model development per PJM modeling guide
  • Reactive capability verification at the POI
  • One-line diagrams, relay protection schemes & switching plans
  • Relay setting design for PRC-019, PRC-024 & PRC-025 compliance

Key Challenges:

  • Tight voltage regulation and transient stability criteria from PJM TOs
  • Aggressive coordination schedule with PJM and neighboring utilities

Results:

  • PJM accepted all dynamic & short-circuit models on first submission
  • Facilities Study finalized ahead of plan—mitigating COD risk
  • POI energized & commissioned successfully on first attempt
  • Keentel named preferred POI partner for future PJM projects

Case Study 2: ERCOT 345 kV POI Support for 300 MW Wind Expansion

Client: Confidential Wind Developer
Scope: POI interconnection of a 300 MW wind farm expansion into the ERCOT 345 kV network under the ERCOT Resource Interconnection Handbook (RIN).

Services Provided:

  • PSSE model creation & TSAT dynamic-model validation to ERCOT DWG requirements
  • Steady-state, dynamic stability & short-circuit data packages
  • RFI responses and coordination with ERCOT Planning & TSP
  • Protection package design per ERCOT Nodal Operating Guide Sec. 2
  • ICCP point-mapping for telemetry compliance

Key Challenges:

  • ERCOT’s fast-frequency-response (FFR) validation under evolving grid conditions
  • Integrating legacy and new turbine models in a unified hybrid-code base

Results:

  • Zero RFI follow-ups after initial package review—a rare achievement
  • Dynamic-model certification granted ahead of schedule
  • Client entered ERCOT market on time, with no penalties or delays

Case Study 3: WECC 230 kV POI for 150 MW PV + 75 MW/300 MWh BESS Hybrid

Client: Confidential Renewable Developer
Scope: POI interconnection engineering for a 225 MW hybrid solar + BESS project into WECC’s 230 kV transmission.

Services Provided:

  • Dynamic models (PSSE & PSCAD) per WECC Modeling & Validation Subcommittee (MVWG) standards
  • Harmonic analysis & Sub-Synchronous Resonance (SSR) risk assessment
  • Electromagnetic transient (EMT) studies on inverter switching impacts
  • SCADA/RTU signal list development & point-to-point testing support

Key Challenges:

  • WECC’s rigorous review of IBR models and fast-transient behavior
  • SSR studies necessity due to series-compensated transmission lines

Results:

  • EMT modeling report approved without major comments
  • Achieved full PRC-024, PRC-019 & PRC-027 compliance
  • Preemptive modeling saved client millions in potential cost overruns

Case Study 4: NYISO 138 kV POI Interconnection for 120 MW Wind Farm

Client: Confidential Wind Developer
Scope: End-to-end POI interconnection for a 120 MW wind farm tying into 138 kV NYISO system under the NYISO Generator Interconnection Process (GIP).

Services Provided:

  • PSSE steady-state & dynamic models per NYISO submission requirements
  • Technical appendices for FERC LGIA (Appendix C – Facilities Study)
  • Protection coordination plan aligned with NYISO & TO philosophies
  • Short-circuit contribution review & relay coordination studies

Key Challenges:

  • NYISO’s stringent voltage & frequency ride-through criteria
  • Complex stakeholder coordination among the developer, NYISO, and TO

Results:

  • First-round acceptance of full model submittal—no resubmissions required
  • Finalized Interconnection Agreement terms without material changes
  • Substation build-out and energization completed on original timeline
  • Client engaged Keentel for ongoing O&M engineering support

Ready to Accelerate Your POI Connection?

Contact Keentel Engineering today for end-to-end Point-of-Interconnection support—feasibility studies, dynamic modeling, protection design, and final energization.
📞 813-389-7871
📧 contact@keentelengineering.com
🌐 Schedule a Consultation

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.