A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime

The three operating regions you have to design to

Device Output vs voltage Response Best suited to Main limitations
Mechanically switched capacitor or reactor Proportional to voltage squared Seconds; discrete steps; limited switching operations per day Steady-state reactive supply, voltage profile, loss reduction No dynamic capability; step voltage change on switching; capability collapses when most needed
Static var compensator Capacitive branches proportional to voltage squared A few cycles; continuously controllable Continuous control where cost matters and deep voltage support is not the driver Square-law capability loss; harmonic filters are part of the plant and interact with the network
STATCOM Approximately proportional to voltage — constant current capability One to two cycles closed loop; converter response faster still Voltage stability margin, weak interconnections, fast disturbance recovery, flicker and unbalance compensation Higher capital cost; converter losses; adds a converter and its control dynamics to the network
Synchronous condenser Governed by machine capability and excitation Excitation response in the hundreds of milliseconds; inherent inertial response instantaneous System strength and inertia, short-circuit contribution, black start support Rotating plant with maintenance and losses; slower controlled response than a converter
STATCOM with energy storage Reactive as a STATCOM, plus real power within the storage rating As STATCOM for reactive; real power limited by storage Where a real power deficiency is part of the problem Cost and complexity of the storage; different failure and maintenance profile
Stage Keentel scope Outcome
Screening Series-compensation proximity, radial contingency review, UIF and short-circuit ratio screening, frequency scans Early identification of which SSO types apply
Detailed studies PSCAD/EMTDC EMT studies with vendor real-code models, impedance-based and frequency-scan analysis Clear evidence of stability margins or risk
Model quality EMT model review, benchmarking against positive-sequence models, model acceptance support Models that system operators accept
Mitigation Control retuning recommendations with vendors, SSDC and bypass logic requirements, protection and monitoring specifications Practical, coordinated solutions
Interconnection support SSR and SSO study reports for ISO and utility requirements, response to reviewer comments Fewer delays in the interconnection process

Resilience: designing CDUs to the facility Tier objective


Liquid cooling makes heat removal more critical, not less. Cold plates hold only seconds of thermal buffer. If TCS flow stops, processors throttle or shut down very quickly. Resilience design must therefore cover:


  • Pump redundancy: N+1 pumps at minimum, with automatic changeover.
  • CDU redundancy: N+1 CDUs on a common TCS header, or 2N CDUs serving A and B manifolds for fault-tolerant designs.
  • Power to CDUs: dual-corded CDUs fed from A and B sources, with pumps and controls on UPS power so coolant keeps flowing through a utility failure and generator start. This is the liquid-cooling equivalent of continuous cooling.
  • Facility water continuity: chilled water or condenser water must also continue, through thermal storage, UPS-backed pumps or a high enough FWS temperature that the TCS can coast on stored thermal mass for the transfer period.
  • Concurrent maintainability: isolation valves so any CDU, pump, filter or manifold section can be serviced without stopping the others.
  • Leak management: leak detection, drip trays, automatic isolation valves and procedures for fluid spills.


Electrical engineering considerations


CDUs and liquid-cooling plants are electrical loads with their own design requirements:


  • Pump motors and VFDs. Large CDUs use variable-frequency drives on their pump motors. These introduce harmonic current that must be included in the facility's harmonic study and IEEE 519 evaluation.
  • Critical mechanical load on UPS. Putting CDU pumps on UPS increases UPS and battery sizing. The mechanical UPS load must be included in redundancy and ride-through calculations.
  • Feeder and protection design. Dual feeds, automatic transfer, selective coordination and arc-flash labelling apply to CDU power distribution just as they do to IT power.
  • Generator transient response. CDU pumps restarting together after a transfer create motor inrush on the generators. Staged restarts and soft acceleration reduce the step load.
  • Load dynamics. AI training loads can swing rapidly between high and low power. Cooling controls must track those swings without temperature overshoot, and electrical systems must handle both the IT and the cooling load changes.


Commissioning a liquid-cooled data hall


  1. Flush and clean the TCS piping and manifolds to the specified cleanliness, using high-purity flush water.
  2. Fill and vent with the specified coolant, verifying glycol concentration and chemistry.
  3. Pressure test for leaks at design and test pressures, including quick-disconnect fittings.
  4. Verify sensors and controls: flow meters, temperature sensors, pressure transmitters, leak detection and BMS points.
  5. Load test with heat load banks connected through the cold-plate interfaces or rack manifolds, across the operating range.
  6. Prove the heat balance on both loops at several load steps, and the approach temperature against the design.
  7. Test failure scenarios: pump failure, CDU failure, power transfer to generator, valve failure and loss of facility water, confirming temperatures stay within the IT vendor's limits.


How Keentel Engineering helps


Keentel Engineering supports data center owners, developers and EPCs with the electrical engineering that liquid-cooled facilities depend on, and coordinates with the mechanical engineer of record and cooling vendors on the integrated design.


How Do AI Data Center Loads Compare to Electric Arc Furnaces on the Power Grid?

AI Data Center Loads vs Electric Arc Furnaces: Grid Impact
Calendar icon. D

November 30, 2026 | Blog

Part A — AI Loads and Arc Furnaces at a Glance

Utilities are being asked to connect something they say they have never seen: data center campuses of several hundred megawatts whose demand jumps, dips and pulses as artificial intelligence (AI) training jobs start, synchronize, pause and restart. Interconnection engineers describe the challenge in new language — "large electronic loads," "computational loads," "power swings from synchronized GPU clusters" — and regulators have responded with alerts, task forces and new ride-through requirements.

Yet the grid has met a load like this before. For seventy years, steelmakers have connected electric arc furnaces (EAFs) to transmission systems. An arc furnace draws tens to hundreds of megavolt-amperes through electrodes that strike an arc directly on scrap steel. The arc is violently unstable during melting, so the furnace swings its reactive and active power many times a second, flickers lights across a region, injects harmonics and interharmonics, and in some places has excited torsional vibration in nearby turbine-generator shafts. Utilities, furnace builders and equipment makers solved those problems with a toolbox that is still in service: synchronous condensers, static var compensators, STATCOMs, energy storage, series reactors, power-electronic furnace supplies, planning levels for flicker and contractual rules for who may cause how much disturbance at a point of common coupling (PCC).

This guide is Keentel Engineering's technical treatment of that parallel. It explains what an AI training load does to the grid, what an arc furnace does, where the physics is the same and where it is not, and how the arc-furnace playbook should be rescaled and re-weighted — not copied — for AI campuses. Every example uses US voltage classes (13.8, 34.5, 138, 230 and 345 kV) at 60 Hz, and every number is worked through in Keentel's own calculation files.

Keentel's position. Keentel Engineering is an independent power engineering firm. We perform interconnection, power quality, flicker, harmonic, oscillation, ride-through and EMT studies for data centers, steel mills, utilities and renewable plants from 4 kV to 765 kV. We do not sell compensators, batteries, GPUs or software. Our interest is that large loads are connected safely and that the evidence supports the decision.

Who this guide is for

  • Data center developers and owners planning AI training campuses of 100 MW to multiple gigawatts.
  • Utility and transmission planners writing or applying large-load interconnection requirements.
  • Power quality engineers who know arc-furnace flicker and need to apply that experience to computational loads.
  • Steel mill and industrial owners who will share substations and transmission corridors with new data centers.
  • Electrical and MEP designers of data center substations, UPS systems and medium-voltage distribution.
  • Compliance and reliability staff following NERC's large-load work and regional ride-through rules.
  • Key facts at a glance

    Item

    Electric arc furnace

    AI training campus

    Typical size per load

    Tens of MVA to a few hundred MVA per furnace

    Hundreds of MW to several GW per campus

    Dominant swing

    Reactive power (Mvar), with active power

    Active power (MW) at near-unity power factor

    Character

    Stochastic, broadband, worst during bore-in and melting

    Structured, periodic steps set by training iterations, checkpoints and job starts

    Main grid symptom historically

    Lamp flicker (Pst, Plt), harmonics, interharmonics

    MW oscillation, load steps, sudden load loss on voltage dips

    Classic mitigation

    Synchronous condenser, SVC, STATCOM, series reactor, DC furnace

    Power smoothing in the load, storage, STATCOM for voltage, ride-through settings

    Governing US references

    IEEE 1453 (flicker), IEEE 519 (harmonics)

    IEEE 1453 and IEEE 519 still apply; large-load requirements from NERC and regions are evolving

    Notable US event

    Decades of flicker complaints and torsional studies

    About 1,500 MW of data center load dropped offline in Northern Virginia in July 2024 (NERC incident review)

    The core ideas in one table

    Idea

    What it means in practice

    Same PCC physics

    Any large load that changes its current quickly changes voltage, frequency and generator torque near it. The equations do not care whether the load melts steel or trains a model.

    Different dominant quantity

    Arc furnaces mainly swing Mvar, which moves voltage. AI campuses mainly swing MW, which moves voltage less but pushes on generators, frequency and electromechanical modes.

    Different spectrum

    Furnace energy is spread broadly across frequencies. AI training energy is concentrated in narrow lines set by the job's iteration rhythm. A narrow line on top of a lightly damped grid mode is the real risk.

    Different scale

    A large furnace is a few hundred MVA. A training campus can be several gigawatts — comparable to the largest generating units, whose loss the grid is designed to survive.

    Self-disconnection

    Data center protection and UPS logic can remove the whole load during a grid fault, by design. A furnace does not do that.

    Software is the new electrode

    The disturbance source is now programmable. Ramp limits, power floors, staggered checkpoints and synthetic load can tame the fluctuation before it ever reaches the grid.

    Keep the philosophy, change the metric

    The arc-furnace philosophy — planning levels at the PCC and a fair allocation of emission among users — still fits. The lamp-weighted flicker metric does not. MW-oscillation limits by frequency band are a better fit.

    Fact check: what common summaries get right, and what needs care

    Short descriptions of the arc-furnace parallel circulate widely. Their core message is sound. Several points need qualification for US engineering practice.

    Common statement

    Keentel's engineering check

    "The grid met this load before with arc furnaces."

    Largely true for the physics and the toolbox. Arc furnaces produced fast, large, irregular load swings, harmonics and occasional torsional interaction, and the industry developed proven mitigations. The scale and spectrum of AI campuses differ enough that the playbook must be rescaled, not copied.

    "Furnace flicker comes chiefly from reactive power swings."

    Correct. At a typical transmission PCC with X/R near 10, reactive swings move voltage roughly ten times more than equal active swings. That is why SVCs and STATCOMs worked so well on furnaces (worked example 3).

    "AI swings are mostly MW, so a STATCOM can hold voltage but cannot cancel them."

    Correct and important, but it needs one refinement. A STATCOM can hold the PCC voltage almost completely for a modest rating — about 34 Mvar for a 227 MW step in Keentel's example. What it cannot do is stop the MW swing from reaching generators, frequency and electromechanical modes. Only stored energy, generation or load-side shaping can do that.

    "Synchronized training concentrates energy at specific frequencies."

    Correct. Keentel's synthetic profile puts most of the swing energy in a line at the iteration frequency and its harmonics (worked example 1). Whether that matters depends on how the line lines up with the grid's own lightly damped modes.

    "A furnace is rated in tens or low hundreds of MVA; an AI campus can reach several gigawatts."

    Correct. One training campus can exceed the largest single contingency some regions plan for.

    "Customer-side protection removed about 1,500 MW in July 2024."

    Correct per NERC's incident review of the July 2024 event in the Eastern Interconnection. Since then a larger event in Northern Virginia in July 2026 was reported at roughly 3–4 GW, and NERC issued a Level 3 alert on large loads in 2026.

    "Use Pst screening, IEC 61000-3-7 and IEEE 1453."

    Correct for flicker. In US practice IEEE 1453 is the governing guide; IEC 61000-3-7 is the international method it draws on. Flicker screening alone will badly understate the risk from AI loads, because the lamp-weighted metric barely responds to slow MW pulses (worked example 14).

    "Utilities already specify oscillation limits over a band of roughly 0.1 to 20 Hz."

    Several large-load requirements and industry reports describe oscillation and fluctuation limits over sub-synchronous bands of that order. Exact bands, metrics and limits vary by region and are still being written; confirm the current requirement with the transmission provider.

    Eight findings for decision makers

  • The arc-furnace experience is directly useful. Planning levels, emission allocation, compensator design and torsional screening all transfer to AI loads.
  • The metric must change. Lamp-weighted flicker is the wrong yardstick for slow, large MW pulses. Limits on MW oscillation amplitude by frequency band, and weighted toward the system's natural oscillation modes, fit better.
  • Voltage is the easy part. For an AI campus at a strong transmission PCC, holding voltage takes a modest compensator. The hard part is the MW swing that reaches generators.
  • Coherence multiplies the problem. Twelve thousand servers stepping together produce a swing about a hundred times larger than the same servers stepping at random (worked example 2).
  • Resonance multiplies it again. A forcing line that lands on a grid mode with 5% damping is amplified about ten times (worked example 5).
  • Load loss is the largest single risk. A campus that drops off the grid for a normally cleared fault is a multi-hundred-megawatt contingency. Ride-through design is not optional.
  • The cheapest fix is often in software. Ramp limits, power floors and staggered checkpoints cut the 0.5 Hz swing line by 59–84% in Keentel's example at a cost of about 1.4% extra energy (worked example 11).
  • Storage is sized by power, not energy. Absorbing a ±50 MW swing at 0.5 Hz takes under 9 kWh per half cycle; the battery or supercapacitor must be sized for power and cycle life (worked example 7).
  • Key terms

  • Electric arc furnace (EAF): a furnace that melts scrap steel with an electric arc between graphite electrodes and the charge. AC furnaces are three-phase; DC furnaces use a rectifier supply.
  • Flicker (Pst, Plt): perceptible fluctuation of lamp light caused by voltage fluctuation. Pst is the short-term (10-minute) severity index; Plt is the long-term (2-hour) index. A value of 1.0 is the threshold of irritability for the reference lamp.
  • PCC: point of common coupling — the point on the utility system nearest the customer where other customers are or could be served.
  • Short-circuit power (Ssc): the three-phase fault level at a bus, a measure of grid strength.
  • SVC / STATCOM: static var compensator (thyristor-controlled reactors and switched capacitors) and static synchronous compensator (voltage-source converter). Both control reactive power.
  • E-STATCOM: a STATCOM with energy storage on its DC side, able to exchange active as well as reactive power.
  • Forced oscillation: a sustained oscillation in the power system caused by a periodic external input, as opposed to a poorly damped natural mode.
  • Inter-area mode: an electromechanical oscillation in which groups of generators in different areas swing against each other, typically at 0.1–1 Hz.
  • Torsional mode: a mechanical vibration mode of a turbine-generator shaft, typically from about 5 Hz to roughly 45 Hz for the lower modes, depending on the machine.
  • Training iteration: one step of a training job — compute, then synchronize results across the cluster. Thousands of accelerators do this together, so their power rises and falls together.
  • Checkpoint: a pause during training to save the model state. Power drops sharply during the pause and returns when training resumes.
  • Ride-through: the ability of a facility to stay connected and keep consuming power through a grid voltage or frequency disturbance.
  • Part B — The Engineering in Depth

    1. What an AI training load actually does

    An AI training job runs the same mathematical step over and over. Each step, or iteration, has two broad phases. In the compute phase, every accelerator in the cluster works through its share of the model and its share of the data. In the communication phase, the accelerators exchange and combine their results so that every copy of the model stays identical. Compute draws high power. Communication draws less, because many accelerators are waiting on the network. Because the job is synchronized across the whole cluster, thousands of servers move between the two phases at nearly the same instant.

    The result, seen from the substation, is a power trace with a strong rhythm. Iteration periods for large models typically range from a fraction of a second to several seconds, depending on model size, batch size, parallelism strategy and network speed. On top of that rhythm sit slower events:

  • Job start. The cluster moves from idle to full training power over seconds, often after a data-loading phase.
  • Checkpoints. Every few minutes to every hour, the job pauses to write the model state to storage. Power falls toward idle during the pause and returns when training resumes.
  • Evaluation and restarts. Periodic evaluation steps, failed-node restarts and job swaps create further steps.
  • Job end or crash. A job that finishes or fails drops the whole cluster to idle at once unless software prevents it.
  • Cooling, power conversion and building loads add a slower, smoother layer. Chilled-water plants and fans respond over tens of seconds to minutes, so they do not follow the iteration rhythm, but they do follow the larger steps.

    Worked example 1 — a synthetic per-server training profile

    Keentel built a simple, openly described model so that every later example can be traced. It represents one accelerator server (node) with:

    Parameter

    Value used

    Idle power

    4.6 kW

    Compute-phase power

    8.6 kW

    Communication-phase power

    8.0 kW

    Iteration period

    2.0 s (0.5 Hz)

    Fraction of the period in compute (duty)

    70%

    Start-up idle

    0–12 s

    Checkpoint pause

    140–152 s

    The average training power per node is:

    AI load and arc furnace engineering figure

    The swing within an iteration is only 0.6 kW peak to peak, about 7% of training power. A rectangular wave of height ΔP and duty d has a fundamental component of amplitude:

    AI load and arc furnace engineering figure

    A Fourier transform of the simulated training segment, sampled at 60 samples per second, finds the strongest lines at 0.5 Hz (0.306 kW), 1.0 Hz (0.183 kW), 2.5 Hz (0.076 kW) and 2.0 Hz (0.051 kW) per node. The energy sits in a few narrow lines, not spread across the spectrum. The checkpoint pause is a different kind of event: a step of 8.42 − 4.6 = 3.82 kW per node, more than six times the iteration swing.

    These values are illustrative. Real profiles vary by model, framework, accelerator generation and power-management settings, and some measured clusters show iteration swings of tens of percent rather than 7%. The method, not the number, is what transfers to a project.

    Worked example 2 — why synchronization matters

    If N nodes swing independently, with random phases, their combined amplitude grows only as the square root of N. If they swing together, it grows in direct proportion to N.

    AI load and arc furnace engineering figure

    Campus size

    Nodes (at 8.42 kW)

    Coherent 0.5 Hz amplitude

    Incoherent amplitude

    Checkpoint step

    100 MW

    11,876

    3.7 MW

    34 kW

    45 MW

    500 MW

    59,382

    18.4 MW

    75 kW

    227 MW

    For a 100 MW campus, coherence turns a 34 kW ripple into a 3.7 MW oscillation — a factor of about 109, which is √11,876. That is the core reason training loads behave differently from conventional data center loads. Thousands of independent web requests average out. One synchronized training job does not.

    Two points follow. First, a campus running many small, unrelated jobs behaves more like the incoherent case; a campus dedicated to one very large job behaves like the coherent case. Second, the checkpoint step, not the iteration ripple, is the largest single MW event in normal operation — 227 MW in seconds for a 500 MW campus in this model.

    AI load and arc furnace engineering figure

    Figure 1. Synthetic profiles from Keentel's illustrative models: a 100 MVA AC arc furnace over several heats (top) and a 500 MW synchronized training campus with and without a per-node ramp limit (bottom). The furnace trace is stochastic; the training trace is structured.

    How Keentel Engineering helps here. Keentel builds a load profile for each campus from the owner's planned workloads, accelerator power data and measured traces where they exist. We separate the iteration rhythm, checkpoint steps, job starts and job ends, and we state which are coherent across the campus. That profile becomes the input to every later study, and it is written so the transmission provider can audit it.

    2. What an arc furnace does

    An electric arc furnace melts steel scrap with three graphite electrodes (AC furnace) or one electrode and a bottom return (DC furnace). A furnace transformer, typically fed from a 34.5, 69, 138 or 230 kV supply in US practice, steps down to a secondary voltage of several hundred to over a thousand volts. Secondary currents reach tens of kiloamperes.

    A heat — one batch of steel — follows a sequence:

  • Bore-in. The electrodes strike arcs on cold scrap and bore down into it. Arcs are short, unstable and constantly broken and re-struck as scrap falls. This is the worst phase for flicker.
  • Melting. A molten pool forms; arcs lengthen and stabilize somewhat. Fluctuations continue but are smaller.
  • Refining (flat bath). The arc burns over liquid steel, often shielded by foamy slag. Power is relatively steady.
  • Tapping and charging. Power is off while steel is tapped and the next scrap bucket is charged.
  • From the grid's view, the furnace is a highly variable, low power factor load. During bore-in, the arc can move from near short circuit (electrode touching scrap) to open circuit (arc extinguished) many times per second. The furnace's reactive power swings far more than its active power, because the furnace circuit is dominated by the reactance of the furnace transformer, flexible cables and electrode arms.

    The arc's voltage–current characteristic is also strongly nonlinear. It produces harmonics of all orders — even and odd — and interharmonics, especially in the early melting phase. Unbalance between phases is common because each electrode sees a different arc.

    Worked example 16 — a synthetic furnace trace

    Keentel's synthetic furnace model in Figure 1 draws random power during four "power-on" windows, with a mean of 69.8 MW and a standard deviation of 17.6 MW, clipped between zero and 110 MW. It is not a physical arc model; it is a simple way to show the statistical character of a furnace beside the structured character of a training campus. A real flicker study uses measured furnace data or a validated arc model.

    Why the furnace became a reference case

    Arc furnaces became the reference case for disturbing loads because they combine every difficult property at once: size, speed, randomness, nonlinearity and unbalance. The flicker meter itself — the instrument that weights voltage fluctuation by how annoying it is to a person watching an incandescent lamp — was developed largely to measure arc-furnace disturbance. Planning levels for flicker, the idea of an emission allocation for each customer at a shared point of common coupling, and the practice of requiring a disturbing customer to pay for its own compensation all grew out of arc-furnace connections.

    How Keentel Engineering helps here. For steel mills, Keentel performs flicker, harmonic and unbalance studies using measured furnace data where available, sizes and specifies compensation, and verifies compliance after energization with IEEE 1453 measurements at the PCC.

    3. Seventy years of arc-furnace experience: a short history

    The parallel between AI loads and arc furnaces is not a loose analogy. Utilities in the United States connected large arc furnaces to transmission systems from the 1950s onward, and the technical literature from that period describes the same symptoms that large-load task forces describe today: rapid load swings, voltage dips felt by other customers, interaction with nearby generators and the need for fast compensation.

    The 1950s: synchronous condensers and the first studies

    Mid-century papers in the American Institute of Electrical Engineers (AIEE) transactions, including work by C. Concordia and colleagues, examined voltage dips and the response of synchronous machines and synchronous condensers to arc-furnace load swings. The tools of the day were rotating machines. A synchronous condenser raised the short-circuit level at the furnace bus, which reduced the voltage change for a given load swing, and it supplied some reactive power on demand through its excitation system. Its response was limited by machine time constants, so it could not follow the fastest arc fluctuations.

    The 1960s and 1970s: the static var compensator

    The thyristor made the static var compensator (SVC) possible. A thyristor-controlled reactor in parallel with fixed or switched capacitor banks could change its reactive output within one or two cycles. Some of the earliest industrial SVCs were installed specifically to compensate arc furnaces. Fixed capacitors, usually arranged as harmonic filters tuned near the 2nd, 3rd, 4th or 5th harmonics, supplied steady reactive power and absorbed harmonic currents; the reactor branch varied to cancel the furnace's reactive swings. SVCs typically reduced flicker severity by a factor of about 1.5 to 2, limited by their response time and by the half-cycle granularity of thyristor control.

    The 1990s: voltage-source converters arrive

    The STATCOM, built from voltage-source converters with turn-off semiconductors, responds faster than an SVC and can control current within a fraction of a cycle. In 1999 a STATCOM was commissioned at a steel plant in Hagfors, Sweden, to compensate an arc furnace; it is widely cited as the first application of the technology to flicker mitigation. Reported flicker reduction factors for STATCOMs on furnaces are in the range of about 3 to 5 or more, depending on control design and the furnace.

    Energy storage on the compensator's DC side

    Engineers recognized early that a compensator which could exchange active power as well as reactive power would handle the active component of a furnace swing too. Superconducting magnetic energy storage (SMES), battery-backed STATCOMs and supercapacitor-backed compensators were proposed and, in some cases, demonstrated for furnaces and other pulsed industrial loads from the late 1980s through the 2000s. These are the ancestors of today's battery and supercapacitor E-STATCOMs for data centers.

    Changing the furnace itself

    The other line of development changed the source:

  • DC arc furnaces, supplied through thyristor rectifiers, became common from the 1980s. They produce less flicker than an equivalent AC furnace — a severity coefficient around two-thirds of the AC value is a common planning assumption — but bring characteristic rectifier harmonics.
  • Series reactors and saturable reactors in the furnace supply stabilize the arc and reduce current swings.
  • Electrode regulation, foamy-slag practice, scrap preparation and hot-heel operation all reduce the time the furnace spends in the most violent phase.
  • Converter-fed AC furnaces, in which a power-electronic converter decouples the arc from the grid, appeared in the 2010s. The grid sees a controlled, near-constant load; the converter absorbs the arc's fluctuations.
  • Active-power stabilizers and "watt compensators"

    Some installations went further and controlled the furnace's active power swing directly. Thyristor-controlled series reactors acting as active-power stabilizers, and static watt compensators that switch a resistive load bank to fill dips in furnace demand, were used where the active swing disturbed generators or tie-line flows. The principle — burn power deliberately when the process power drops, so the grid sees a steadier load — is exactly what AI campuses now do in software when they hold accelerators at a power floor during communication phases or checkpoints.

    Keentel Study Spotlight — learning from the furnace record. Before a large-load study begins, Keentel reviews the disturbance history of the transmission area: existing furnaces, other large industrial loads, compensators already in service and any past flicker or oscillation complaints. Old furnace studies often contain the best available data on local grid damping, resonance and planning levels, and they show which mitigation the utility already trusts.

    4. The physics at the PCC: why Mvar and MW behave differently

    For a load connected at a bus with Thevenin impedance R + jX behind it, a change in active power ΔP and reactive power ΔQ changes the bus voltage by approximately:

    AI load and arc furnace engineering figure

    In per unit on a common base this becomes ΔV ≈ R·ΔP + X·ΔQ. On transmission systems X is much larger than R; X/R ratios of 8 to 15 are typical at 138–345 kV. So a megavar moves voltage roughly X/R times as much as a megawatt does.

    Worked example 3 — same PCC, two loads

    Consider a 230 kV PCC with a three-phase short-circuit level of 5,000 MVA and X/R = 10. On a 100 MVA base:

    AI load and arc furnace engineering figure

    Load event

    ΔP

    ΔQ

    ΔV from ΔP

    ΔV from ΔQ

    Total ΔV

    Arc furnace swing

    30 MW

    60 Mvar

    0.06%

    1.19%

    1.25%

    AI campus checkpoint step

    227 MW

    11 Mvar

    0.45%

    0.22%

    0.67%

    The furnace swing is much smaller in MW yet causes almost twice the voltage change, because it is reactive. The AI step is seven times larger in MW but mostly active, so its voltage effect is smaller — and two-thirds of it comes from the MW component.

    The reactive power a compensator must inject to cancel the voltage change completely is:

    AI load and arc furnace engineering figure

    For the furnace, that is −63 Mvar — more than the furnace's own reactive swing, because the compensator must also offset the small active part. For the AI step, it is only −33.7 Mvar: 22.7 Mvar to offset the active part (227/10) plus 11 Mvar for the reactive part. A STATCOM of a few tens of Mvar can hold the PCC voltage nearly flat during a 227 MW step.

    That is the encouraging half of the story. The other half is that the STATCOM has done nothing about the 227 MW itself. The generators still see the step. Their rotor angles and speeds still respond. If the step repeats at a frequency near a grid mode, they still oscillate. Voltage support is necessary for AI loads but it is not sufficient.

    AI load and arc furnace engineering figure

    Figure 2. Voltage change at the same 230 kV PCC for an arc-furnace swing and an AI campus step, split into the part caused by active power and the part caused by reactive power (Keentel worked example 3).

    How Keentel Engineering helps here. Keentel computes the PCC impedance for normal and credible outage conditions, separates the active and reactive parts of the load's disturbance, and sizes voltage support only for what voltage support can fix. The active-power part is carried into the oscillation and frequency studies described below, where it belongs.

    5. Flicker screening — and why it is the wrong yardstick for AI loads

    Flicker is the human perception of light fluctuation caused by voltage fluctuation. The IEC flickermeter, adopted in the United States through IEEE 1453, weights voltage fluctuation by a lamp-and-eye response that peaks near 8.8 Hz and falls steeply below about 1 Hz and above about 25 Hz. Its outputs are the short-term severity Pst (10 minutes) and long-term severity Plt (2 hours). Pst = 1.0 corresponds to the level at which half of observers find the flicker irritating.

    The classic arc-furnace screen

    For arc furnaces, planners use a simple screening relationship:

    AI load and arc furnace engineering figure

    where SscF is the furnace's short-circuit power (the apparent power the furnace draws with its electrodes short-circuited) and Ssc is the short-circuit power at the PCC. Kst is an empirical coefficient, commonly taken in the range 48–85 for AC furnaces, with values around 60 often used for screening. For DC furnaces, a value around two-thirds of the AC value is a common planning assumption.

    Worked example 4 — screening a furnace

    A furnace with SscF = 200 MVA and Kst = 60:

    PCC short-circuit level

    Uncompensated Pst

    2,000 MVA

    6.0

    5,000 MVA

    2.4

    To meet an illustrative transmission planning level of Pst = 0.8 without compensation would require 60 × 200 / 0.8 = 15,000 MVA at the PCC — rarely available. So the furnace needs mitigation:

    Mitigation at 2,000 MVA

    Assumed reduction factor

    Resulting Pst

    None

    1

    6.0

    100 MVA synchronous condenser (X″ = 0.15 pu) adds about 667 MVA

    —

    4.5

    SVC

    about 2

    3.0

    STATCOM

    about 4

    1.5

    The table shows why steel mills moved from synchronous condensers to SVCs and then to STATCOMs, and why even a STATCOM may not be enough at a weak bus. It also shows why many furnace connections were made at 230 kV or above. The reduction factors are illustrative; actual performance depends on the furnace, the control design and the network.

    Worked example 15 — a DC furnace

    Using Kst = 40 for a DC furnace of the same short-circuit power at the 2,000 MVA bus gives Pst = 40 × 200 / 2,000 = 4.0, a third lower than the AC furnace but still far above planning levels without compensation.

    Worked example 14 — why flicker misses AI loads

    Now apply flicker logic to an AI campus. For a 100 MW campus, the coherent 0.5 Hz amplitude in worked example 2 is 3.67 MW, or 7.34 MW peak to peak. At the 230 kV, 5,000 MVA, X/R = 10 bus:

    AI load and arc furnace engineering figure

    At a weaker 138 kV bus with 1,500 MVA and X/R = 6, the same swing gives about 0.080%. Both values are tiny compared with the fluctuation needed to register flicker at 0.5 Hz, where the flickermeter is very insensitive. A flicker study would report the campus as harmless.

    But the same 3.67 MW oscillation, if it lands on an inter-area mode with 5% damping, is amplified about tenfold in a single-oscillator approximation — on the order of 37 MW of forced oscillation shared among the generators taking part in that mode (worked example 5). The flicker metric was designed to protect people from lamp flicker. It was never designed to protect generators and power system modes from slow MW forcing. That is the central reason the arc-furnace yardstick must change even where the arc-furnace philosophy still applies.

    IEEE 1453 planning levels

    IEEE 1453-2022 provides indicative planning levels for flicker at medium, high and extra-high voltage. Values often quoted for high voltage are around Pst 0.8 and Plt 0.6, with medium voltage around Pst 0.9 and Plt 0.7. Utilities set their own planning levels and allocate emission limits to individual customers. Always use the transmission provider's current values. IEC 61000-3-7 describes the international approach to emission allocation for fluctuating loads at MV, HV and EHV, and IEEE 1453 draws on it.

    How Keentel Engineering helps here. For AI campuses, Keentel still runs the flicker screen — it is required in many interconnection agreements and it protects neighbors with sensitive lighting and equipment — but we report it beside an MW-oscillation assessment, so no one mistakes a low Pst for a clean bill of health.

    6. Spectrum and resonance: when a small swing becomes a large one

    Figure 3 compares the spectra of Keentel's synthetic furnace and training campus. The furnace spreads its energy across the whole range from a fraction of a hertz to tens of hertz, with no dominant line. The training campus puts almost all its swing energy into a handful of narrow lines at the iteration frequency and its harmonics.

    AI load and arc furnace engineering figure

    Figure 3. Where the MW swing energy sits in Keentel's synthetic models, compared with typical power system mode ranges. Shaded bands are indicative; actual mode frequencies are system-specific.

    A broadband source excites every mode a little. A narrowband source excites the modes near its lines a lot and the rest hardly at all. Whether a training campus is a problem therefore depends on alignment: does any of its lines fall near a lightly damped mode of the power system?

    Worked example 5 — resonance gain

    For a lightly damped mode with natural frequency fn and damping ratio ζ, a sinusoidal forcing at frequency f is amplified by approximately:

    AI load and arc furnace engineering figure

    At resonance (r = 1), G = 1/(2ζ).

    Damping ratio ζ

    Gain at resonance

    2%

    25

    5%

    10

    10%

    5

    Forcing frequency (ζ = 5%)

    Gain

    At the mode (r = 1.0)

    10.0

    10% below the mode (r = 0.9)

    4.8

    Half the mode frequency (r = 0.5)

    1.3

    Many utilities treat 3–5% damping as the minimum acceptable for electromechanical modes. A campus line sitting on a mode at that damping is amplified five to ten times. Move the line 10% away and the gain halves; move it to half the mode frequency and resonance hardly matters.

    This simple model treats the power system as a single oscillator. Real systems have many modes, and the response at a given generator depends on its participation in each mode and its electrical distance from the campus. The point stands: a narrowband forcing source is dangerous only near a weakly damped mode, and the danger is multiplied by the inverse of the damping.

    Forced oscillation is not instability

    A forced oscillation is different from an unstable mode. The power system can be perfectly stable — every mode damped — and still oscillate continuously because something keeps pushing it. The fix is to remove or reduce the push, or to move it away from the mode, not to retune generator stabilizers. Forced oscillations from malfunctioning plant controllers, steam valves and wind turbine controls have been recorded across the US interconnections, sometimes travelling across hundreds of miles. A synchronized training campus is a forcing source by design.

    How Keentel Engineering helps here. Keentel identifies the electromechanical modes near a proposed campus from small-signal studies, from synchrophasor ringdown analysis where the transmission provider shares data, and from earlier oscillation events. We map the campus's expected forcing lines against those modes and their damping, and we report the gain at each line — so the owner knows which workloads matter and which do not.

    7. Torsional interaction with turbine-generators

    Large steam and combustion turbine-generators have shafts that can twist at mechanical natural frequencies, typically from about 5 Hz to roughly 45 Hz for the lower modes, with very light mechanical damping — often a fraction of a percent. Any electrical disturbance that pushes on the generator's air-gap torque at a torsional frequency can excite these modes. Series capacitors, HVDC converters, poorly tuned power electronics and, historically, arc furnaces have all been examined for torsional interaction.

    Arc furnaces became a concern because their broadband swings contain energy at torsional frequencies, and because a few US steel mills sat electrically close to large thermal units. Studies from the arc-furnace era established the practice of screening torsional exposure whenever a large fluctuating load connects near a thermal plant.

    Worked example 6 — torsional gain and the forcing available

    With the same resonance formula, a torsional mode with 0.1% damping has a gain at resonance of 1/(2 × 0.001) = 500; with 0.5% damping, 100. That is why even small forcing near a torsional mode can matter over long periods, through shaft fatigue rather than immediate failure.

    How much forcing does a training campus produce at a torsional frequency? In Keentel's idealized rectangular profile, the 32nd harmonic of the 0.5 Hz iteration rhythm falls at 16 Hz with an amplitude of about 0.011 kW per node. For a 500 MW campus of 59,382 coherent nodes that is about 0.68 MW. Real power-supply and accelerator electronics round the edges of the steps, so real high-frequency content is usually lower than the idealized wave suggests — but faster iteration rhythms, sharper power-management transitions or interaction with converter controls can push it higher. The only reliable answer comes from measured power at high time resolution and a torsional screening study with the actual generator data.

    What to screen
  • Electrical distance. Torsional exposure falls quickly with distance. Screen thermal units within a few buses of the campus, and any unit on a radial or weakly meshed path.
  • Modal frequencies and damping. Obtain them from the generator owner or manufacturer data where possible.
  • Campus spectrum. Use measured or vendor-provided high-resolution power traces for the actual accelerators and power supplies, at the actual iteration rhythms planned.
  • Converter interaction. Check whether campus power electronics, including UPS rectifiers and any grid-connected storage, have control bandwidth that could interact with torsional modes, as is done for HVDC and series-compensated lines.
  • How Keentel Engineering helps here. Keentel performs torsional interaction screening for large loads near thermal plants: unit interaction factor screening, frequency scans and, where needed, detailed EMT studies with multi-mass shaft models. We coordinate with generator owners so that data stays confidential and results are actionable on both sides.

    8. Load loss: the risk arc furnaces never posed

    An arc furnace that sees a voltage dip keeps drawing current; at worst its arcs extinguish briefly and re-strike. It does not deliberately disconnect itself from the grid. A data center does exactly that. Its uninterruptible power supply (UPS) systems are designed to protect the servers from any grid disturbance outside a tolerance window. When the grid voltage dips below the UPS threshold, the UPS transfers the critical load to batteries, and in many designs the facility also starts its standby generators and opens its utility breakers. From the grid's point of view, the load vanishes in a few cycles.

    The 2024 Eastern Interconnection event

    In July 2024, a fault on a 230 kV transmission line in Northern Virginia was cleared normally, but a sequence of automatic reclosing attempts produced repeated voltage dips. Data center facilities in the area responded by transferring to backup power, and roughly 1,500 MW of load disconnected from the grid. NERC's incident review documented the event and identified the main issues: the load-loss behavior was not represented in planning models, the facilities did not return to grid power promptly or in a coordinated way, and the grid operator had to manage the resulting overfrequency and high voltage. No customer lost service; the data centers ran on their own backup.

    Reports in 2026 described a larger event in Northern Virginia in July 2026 with roughly 3–4 GW of data center load lost during a transmission disturbance. NERC issued a Level 2 alert on large loads in 2025 and a Level 3 alert, with essential actions, in May 2026. Treat event magnitudes for the 2026 event as reported values pending NERC's final analysis.

    Worked example 8 — frequency after a large load loss

    When load disappears, generation briefly exceeds demand and frequency rises. Two first-order quantities describe the event:

    AI load and arc furnace engineering figure

    where β is the interconnection's frequency response (MW per 0.1 Hz), H the aggregate inertia constant and S the online generation rating.

    Illustrative case

    Load lost

    β (MW/0.1 Hz)

    H (s)

    S (GVA)

    Settling frequency rise

    Initial RoCoF

    Large eastern interconnection

    1,500 MW

    2,500

    4.0

    700

    0.060 Hz

    0.016 Hz/s

    Smaller interconnection

    3,000 MW

    900

    4.5

    90

    0.333 Hz

    0.222 Hz/s

    In a very large interconnection, 1,500 MW is manageable for frequency; the bigger local issues are overvoltage as lightly loaded lines release reactive power and the operational burden of reconnecting the load. In a smaller interconnection, 3,000 MW of sudden load loss is comparable to the largest generation contingencies the system is designed for, but in the opposite direction, and it can drive frequency high enough to trip generation protection if unchecked. All values are illustrative; actual frequency response varies by season, hour and dispatch.

    Worked example 9 — how often the trigger happens

    Load loss is triggered by voltage dips, and voltage dips are triggered mostly by transmission faults. A rough exposure estimate:

    Item

    Value

    Fault rate (illustrative, all fault types)

    1.5 per 100 mi-yr

    Line-miles electrically close enough to cause a deep dip

    300 mi

    Expected faults per year

    4.5

    Clearing time

    Duration at 60 Hz

    5 cycles (fast primary protection)

    83 ms

    15 cycles (slower primary or zone 2)

    250 ms

    30 cycles (breaker failure, remote backup)

    500 ms

    So a campus in a meshed transmission area can expect several deep dips each year, most cleared within about 100 ms. If the facility's ride-through settings trip on any dip deeper than, say, 30% for longer than two cycles, the campus will drop off the grid several times a year. A furnace operator might not even notice those dips.

    Keentel Study Spotlight — load-loss and ride-through study. Keentel models the campus as the grid sees it: UPS transfer thresholds and timers, protective relay settings at the substation, standby generator starts, mechanical load response and the reconnection sequence. We simulate the faults the transmission provider requires, report how much load is lost and when it returns, and recommend settings that keep the campus connected for normally cleared faults while still protecting the critical load.

    9. Ride-through design for AI campuses

    The arc-furnace era never needed a ride-through standard for loads. Large-load requirements now being written by US transmission providers and reliability organizations do. Common elements include:

  • Voltage ride-through. Stay connected and keep drawing power (or return to pre-disturbance power within a stated time) for voltage dips within a defined voltage–time envelope.
  • Frequency ride-through. Stay connected across a defined frequency range.
  • No sudden large power changes. Limits on ramp rates when returning from backup power, and coordination with the transmission operator before large planned transfers.
  • Oscillation and fluctuation limits. Limits on periodic power fluctuation in defined frequency bands.
  • Modeling and data. Validated models of the facility's dynamic behavior, including protection and UPS logic, for planning and operations.
  • Where load loss comes from inside the facility

    Element

    Why it trips

    What to change

    UPS input voltage window

    Narrow tolerance window protects downstream equipment

    Widen the window to what the rectifier and batteries can actually tolerate; add time delay

    UPS transfer and retransfer logic

    Transfer on any disturbance; slow or uncoordinated return

    Ride through short dips on the input; coordinate retransfer with the utility; ramp the return

    Medium-voltage protection

    Undervoltage relays set tight for equipment protection

    Coordinate pickup and delay with transmission clearing times

    Automatic transfer schemes

    Transfer to generators on first dip

    Add delay and require sustained loss before transfer

    Mechanical systems

    Chillers, pumps and fans trip on dips and restart slowly

    Use ride-through-capable drives and staggered restarts

    Power supplies in servers

    Hold-up time of a few cycles

    Rely on UPS for longer events; confirm hold-up in specifications

    The ITIC (CBEMA) curve, which describes the voltage tolerance expected of information technology equipment, remains a useful reference for the downstream equipment, but it says nothing about how the facility should behave toward the grid. The facility's grid-facing ride-through is now a design requirement in its own right.

    Ride-through has to match protection clearing

    Worked example 9 shows that normal clearing times range from about 83 ms to 250 ms, with backup clearing up to 500 ms. A ride-through envelope that holds through 150 ms at 0% retained voltage, and longer at partial voltage, covers most normally cleared faults. Reclosing sequences — the trigger in the 2024 event — need special attention: each reclose onto a persistent fault creates a new dip, so the facility logic must tolerate repeated dips within seconds.

    How Keentel Engineering helps here. Keentel reviews every element in the chain from the transmission relay to the server power supply, finds the settings that cause unnecessary load loss and recommends changes that meet the transmission provider's ride-through requirement while protecting the facility. We document the result in a form the utility can use in its planning models.

    10. Harmonics: one place where the load improved

    Arc furnaces are notorious harmonic sources: even and odd harmonics, interharmonics and unbalance, worst during bore-in. Early data centers with six-pulse UPS rectifiers were significant harmonic sources too. Modern large data centers are usually much cleaner, because UPS systems and server power supplies use active front ends with power-factor correction.

    IEEE 519-2022 sets current distortion limits at the PCC in terms of total demand distortion (TDD), scaled by the ratio of short-circuit current to maximum demand current, and voltage distortion limits by voltage level.

    Worked example 10 — TDD by front-end type

    Using illustrative harmonic current spectra at full load:

    Front end

    Main harmonic currents (% of rated)

    TDD

    6-pulse rectifier

    5th 20, 7th 14, 11th 9, 13th 7, 17th 5, 19th 4

    27.7%

    12-pulse rectifier

    11th 9, 13th 7, 23rd 4, 25th 3.5

    12.6%

    Active front end

    5th 1.5, 7th 1.0, 11th 0.8, 13th 0.6, high-frequency 1.5

    2.5%

    AI load and arc furnace engineering figure

    At transmission voltages, IEEE 519 TDD limits are typically a few percent, depending on the short-circuit ratio. A modern campus with active front ends usually meets them comfortably at the fundamental level, but three cautions apply:

  • Aggregation and cancellation. Thousands of active front ends switching at different frequencies usually cancel well, but common control or synchronized switching can reduce cancellation.
  • Supraharmonics. Active front ends move distortion to the kilohertz range, which IEEE 519 does not fully address and which can interact with capacitors and filters.
  • Resonance. Large cable networks and capacitor banks inside the campus create parallel resonances that can amplify background harmonics from the grid. That is a design issue, not an emission issue.
  • Interharmonics are worth a note. AI training's power fluctuation at a fraction of a hertz modulates the fundamental current and produces sidebands very close to 60 Hz — sub-synchronous and super-synchronous components. Those are the same quantities that oscillation-band limits address, seen from the harmonic side.

    How Keentel Engineering helps here. Keentel performs IEEE 519 harmonic studies, frequency scans and filter designs for data centers and industrial plants, including supraharmonic assessment and resonance checks on large campus cable networks.

    11. The toolbox, translated

    Every major arc-furnace mitigation has an AI-campus equivalent. Some transfer almost unchanged; others change role because the dominant quantity has moved from Mvar to MW.

    AI load and arc furnace engineering figure

    Figure 4. Keentel's map from arc-furnace era tools to their AI-campus equivalents.

    Arc-furnace tool

    What it did for furnaces

    AI-campus equivalent

    Role change

    Synchronous condenser

    Raised fault level, supplied Mvar, added inertia

    Synchronous condenser at the campus or nearby

    Now valued more for inertia and fault level than for Mvar

    SVC

    Cancelled Mvar swings within cycles

    SVC or STATCOM for voltage control

    Still needed, but sized for a smaller ΔQ

    STATCOM

    Faster Mvar cancellation, higher flicker reduction

    STATCOM with power oscillation control

    Voltage role continues; cannot address MW

    SMES, battery or supercap compensator

    Active and reactive compensation

    E-STATCOM, BESS, supercapacitor buffer

    Becomes the main hardware answer to MW swings

    DC furnace, converter-fed furnace

    Decoupled the arc from the grid

    Rectifier front ends, MV-UPS, DC distribution

    Converter can buffer and shape power if designed to

    Series reactor, active-power stabilizer

    Limited current and active swings

    Power smoothing, ramp limits in the load

    Moves into software and power management

    Static watt compensator

    Filled dips with resistive load

    Synthetic load, accelerator power floor

    Same principle, software implementation

    Electrode regulation, slag practice

    Reduced the violent phase

    Workload scheduling, staggered checkpoints

    The process itself becomes the control

    Pst planning levels and allocation

    Fair share of flicker headroom

    MW oscillation limits by frequency band

    Same philosophy, different metric

    Interruptible tariffs

    Curtailed furnaces at peak

    Flexible or curtailable service

    Larger scale, faster response possible

    The most important change is in the last four rows. For furnaces, the process was largely fixed and the grid or a compensator absorbed its variability. For AI campuses, the process is software. The cheapest and most effective controls often live in the scheduler, the training framework and the accelerator power-management firmware.

    How Keentel Engineering helps here. Keentel compares mitigation options on equal terms — software shaping, storage, compensators, condensers and network reinforcement — with cost, performance and verification for each, so owners do not buy hardware for a problem software can solve, or rely on software for a problem only hardware can solve.

    12. Shaping the load at its source

    Because the disturbance comes from software, it can be shaped in software. The main techniques are:

  • Ramp-rate limits. Limit how fast each accelerator or server can change power. A slower edge removes high-frequency content and reduces the iteration line.
  • Power floors. Keep accelerators at a minimum power during communication phases and short pauses, so the dip is smaller. This burns some extra energy.
  • Synthetic load (power burn). Run dummy work during checkpoints or after a job ends, then ramp down slowly.
  • Staggering. Offset checkpoints and job starts across independent jobs or cluster partitions, so their steps do not coincide.
  • Frequency avoidance. Where possible, avoid iteration rhythms that land on known grid modes, for example by changing batch size or parallelism.
  • Worked example 11 — ramp limits and a power floor

    Keentel applied a per-node ramp limit to the synthetic profile and measured the 0.5 Hz line again:

    Ramp limit per node

    0.5 Hz line

    Reduction from 0.306 kW

    2.0 kW/s

    0.283 kW

    8%

    0.5 kW/s

    0.125 kW

    59%

    0.2 kW/s

    0.050 kW

    84%

    A ramp limit works by preventing the node from completing its swing within each phase. At 0.5 kW/s, the node cannot fully rise from 8.0 to 8.6 kW during the 0.6 s communication phase, so the swing shrinks. Ramp limiting also softens the checkpoint step: at 0.5 kW/s per node, the 3.82 kW checkpoint drop takes about 7.6 s instead of a fraction of a second.

    A power floor works differently. Raising the communication-phase power from 8.0 to 8.4 kW cuts the swing to 0.2 kW and the 0.5 Hz line to 0.102 kW — a two-thirds reduction — at the cost of 1.43% more energy for the node. For a 500 MW campus, that is about 7 MW of continuous extra consumption, so floors are a tool to apply when and where the oscillation risk justifies the cost.

    There is a performance trade-off. Ramp limits that slow accelerators during compute phases can lengthen each iteration. Whether that matters depends on how close to power-limited the accelerators are. The owner's compute team, not the electrical engineer, has to confirm the trade-off — which is why load shaping must be agreed early, not imposed after a problem appears.

    Who controls the shaping?

    Load shaping is only useful if it is reliable. A transmission provider cannot plan around a setting that the next software release might change. Good practice is to:

  • Define the shaping requirement in electrical terms (MW per second, MW amplitude by band) at the PCC.
  • Implement it in a layer the facility controls — power management firmware or a site controller — not only in individual training jobs.
  • Monitor compliance continuously at the PCC and report exceptions.
  • Fall back to hardware (storage or burn) when software shaping is disabled or fails.
  • Keentel Study Spotlight — load-shaping specification. Keentel translates the transmission provider's oscillation and ramp requirements into a load-shaping specification the owner's compute and facilities teams can implement: limits per node and per hall, checkpoint staggering rules, burn sequences on job end, and the monitoring that proves the limits are met.

    13. Storage and E-STATCOMs: sized for power, not energy

    The arc-furnace era showed that active-power compensation needs stored energy. AI campuses confirm it: the MW swing must come from somewhere, and if not from the generators it must come from a buffer.

    Worked example 7 — how much energy does a swing need?

    To absorb a sinusoidal swing of amplitude ΔP at frequency f, the buffer charges for one half cycle and discharges for the next. The energy moved in one half cycle is:

    AI load and arc furnace engineering figure

    For ΔP = 50 MW at 0.5 Hz:

    Quantity

    Value

    Energy per half cycle

    31.8 MJ = 8.84 kWh

    Half cycles per day

    86,400

    Full cycles per day

    43,200

    Depth of discharge per half cycle on a 50 MW / 12.5 MWh battery

    0.071%

    The energy is small; the power and the cycle count are large. A battery sized for 50 MW will handle the swing with tiny depth of discharge, but tens of thousands of shallow cycles per day must be checked against the cell chemistry's cycle-life data and thermal limits. Supercapacitors and flywheels handle very high cycle counts well and are often a better fit for the fastest swings.

    Checkpoints are a bigger energy problem. Bridging a 227 MW checkpoint pause of 12 s takes 227 × 12 / 3,600 = 0.757 MWh. Ramping the campus back over 30 s, with the buffer covering the difference, takes 0.946 MWh. Both are within the range of a modest battery, but they require hundreds of megawatts of power capability — almost as much as the campus itself. That is why staggering and ramp limits, which shrink the step in software, are usually combined with storage rather than replaced by it.

    E-STATCOM versus separate BESS and STATCOM

    An E-STATCOM shares one converter between voltage control and active-power buffering. A separate battery and STATCOM can be optimized independently. The choice depends on rating, footprint, redundancy and the interconnection requirement. Either way, the converter controls must be studied for interaction with the grid, with campus UPS converters and with nearby inverter-based resources.

    UPS batteries as a buffer

    Data centers already contain large amounts of stored energy in their UPS batteries. Medium-voltage UPS designs and grid-interactive UPS controls can, in principle, use that energy to smooth campus power. Doing so must not reduce the backup time below what the critical load requires, and battery life must be checked for the added cycling. This is the data center equivalent of using the furnace's own converter to buffer its arc.

    How Keentel Engineering helps here. Keentel sizes storage and E-STATCOMs for power, energy and cycle life together, using the campus load profile and the required reduction in each oscillation band. We perform the EMT studies that show the buffer's controls are stable alongside UPS converters and the grid.

    14. Series devices, active-power stabilizers and grid reinforcement

    Some arc-furnace installations used thyristor-controlled series reactors to stabilize furnace active power, typically achieving a reduction in the swing of around 3:1.

    Worked example 13 — a 3:1 stabilizer

    Applying a 3:1 reduction to the 227 MW checkpoint step leaves 227 / 3 ≈ 76 MW. That is a meaningful improvement, but series devices carry the full campus current continuously, add losses and need careful protection. For AI campuses, the same reduction is usually cheaper to achieve through load shaping and storage.

    Network reinforcement is the other traditional lever. Raising the short-circuit level at the PCC reduces voltage effects in proportion. It does nothing for the MW swing reaching generators — the generators still supply the same MW — but it can increase the damping of local modes and reduce the electrical distance to the generators that absorb the swing. Synchronous condensers add inertia and fault level, which slows RoCoF after load loss and stiffens the local voltage.

    How Keentel Engineering helps here. Keentel evaluates network reinforcement, synchronous condensers and series devices alongside storage and load shaping, using short-circuit, dynamic and EMT studies, and reports the cost per MW of oscillation reduction for each option.

    15. Flexibility: the interruptible furnace becomes the flexible campus

    Utilities have long offered steel mills interruptible or curtailable tariffs: lower rates in exchange for the right to curtail the furnace at system peaks. AI campuses can offer the same, and in some cases more, because training jobs can pause and resume, and workloads can sometimes move between sites.

    Worked example 12 — the value of flexibility

    A 300 MW campus that can reliably curtail 20% (60 MW) on request, valued at an illustrative $150 per MW-day of capacity, earns:

    AI load and arc furnace engineering figure

    The actual value depends entirely on the market and the tariff; capacity prices vary widely by region and year. More important than revenue, flexible service is increasingly a path to faster interconnection: transmission providers can connect a campus before network upgrades are complete if the campus agrees to curtail under defined conditions.

    Flexibility and oscillation control interact. A campus that curtails by stopping jobs abruptly creates exactly the step the grid least wants. Curtailment must be ramped, and the ramp must be coordinated with the transmission operator.

    How Keentel Engineering helps here. Keentel models flexible-service arrangements in planning studies, defines the curtailment ramps and conditions that keep the grid secure, and supports owners in negotiating terms the facility can actually meet.

    16. The US requirements landscape

    Requirements for large loads in the United States are developing quickly. The following summary reflects public documents available in late 2026; confirm the current status of each before relying on it.

    Body

    Item

    What it addresses

    NERC

    Large Loads Task Force (LLTF)

    Characteristics, risks, modeling and possible standards for large loads

    NERC

    White paper: Characteristics and Risks of Emerging Large Loads (2025)

    Load behavior, ride-through, oscillation, modeling gaps

    NERC

    Incident Review: Large Load Loss (2024 event)

    About 1,500 MW of data center load lost after a 230 kV fault and reclosing

    NERC

    Level 2 alert on large loads (2025)

    Recommendations on modeling, ride-through and data

    NERC

    Level 3 alert on large loads (May 2026)

    Essential actions for registered entities on large-load risks

    ERCOT

    NOGRR 282

    Ride-through requirements for large electronic loads

    ERCOT

    Large-load interconnection process and Q&A

    Study process and data requirements

    ERCOT

    Board update on interconnection and grid analysis (September 2026)

    Discussion of rapid load fluctuations

    MISO

    Large Load Working Group materials (April 2026)

    Proposed large-load interconnection reliability requirements

    ESIG

    Large loads performance requirements report (2026)

    Recommended performance requirements and metrics

    GridLab

    Large loads interim report (2025)

    Policy and technical options for large loads

    IEEE

    IEEE 1453-2022

    Flicker measurement and limits

    IEEE

    IEEE 519-2022

    Harmonic limits

    Common themes across these documents:

  • Ride-through for voltage and frequency disturbances, with defined envelopes.
  • Ramp-rate and step limits on load changes, including return from backup power.
  • Oscillation limits on periodic power fluctuation in sub-synchronous frequency bands.
  • Models — positive-sequence dynamic models and, increasingly, EMT models — validated against tests or measurements.
  • Monitoring with high-resolution recording at the PCC.
  • Coordination with the transmission operator before large planned changes.
  • Utilities and regions differ on thresholds (the size above which a load is "large"), on band definitions and on how strictly requirements apply to existing facilities. Several also distinguish between computational loads and other large loads such as cryptocurrency mining, hydrogen electrolysis and industrial process loads.

    How Keentel Engineering helps here. Keentel tracks NERC and regional large-load requirements and maps each requirement to the facility design element that meets it, so owners know which settings, equipment and documents each transmission provider will expect.

    17. A better yardstick: MW oscillation limits by frequency band

    If the lamp-weighted flicker metric is the wrong yardstick for AI campuses, what replaces it? Keentel's view is that the arc-furnace framework survives intact and only the weighting changes:

  • Planning level. The transmission provider defines an acceptable level of forced oscillation at the PCC or at critical generators, by frequency band.
  • Allocation. That headroom is allocated among large loads in the area, as flicker headroom was allocated among furnaces.
  • Emission limit. Each campus receives a limit on MW oscillation amplitude in each band, measured at its PCC.
  • Weighting. The weighting function reflects the grid's sensitivity — higher in bands containing lightly damped modes, lower elsewhere — rather than the eye's sensitivity.
  • Verification. High-resolution monitoring at the PCC confirms compliance.
  • Illustrative band structure

    Band

    Typical concern

    Example limit form

    Below 0.1 Hz

    Governor response, area control error, tie-line flows

    Ramp rate in MW/min

    0.1–1 Hz

    Inter-area and plant control modes

    MW amplitude limit, tighter near known modes

    1–3 Hz

    Local electromechanical modes

    MW amplitude limit

    3–20 Hz or wider

    Control interaction, torsional exposure near thermal units

    Amplitude limit or screening requirement

    These bands are illustrative. Transmission providers are still defining them, and several published requirements use different splits and metrics, such as limits expressed as a percentage of facility rating.

    Worked example 14, revisited

    The 100 MW campus's 3.67 MW line at 0.5 Hz is 3.7% of its rating. If the provider sets a limit of 1% of rating in the 0.1–1 Hz band, the campus needs a reduction of about 73%. The ramp limit of 0.5 kW/s per node (59%) is not enough alone; the 0.2 kW/s limit (84%) or a combination of a moderate ramp limit with a power floor would meet it. That is the kind of calculation that turns a requirement into a design.

    How Keentel Engineering helps here. Keentel helps transmission providers develop practical band limits and allocation methods from their own mode data, and helps owners demonstrate compliance with them.

    18. The study workflow for an AI campus

    The arc-furnace study sequence — screen, model, mitigate, verify — carries over with additions:

    1. Data collection. Campus size, phasing, workloads, accelerator generations, UPS and protection design, planned interconnection point and the transmission provider's requirements.

    2. Load characterization. Build the campus profile (section 1): iteration lines, checkpoint steps, job starts and ends, coherence assumptions and cooling response.

    3. Steady-state and short-circuit studies. Load flow, contingency analysis, short-circuit levels at the PCC under normal and outage conditions.

    4. Voltage and flicker screening. ΔV for steps, flicker screening per IEEE 1453 and the transmission provider's planning levels.

    5. Mode survey. Identify electromechanical modes, their frequencies, damping and participation near the campus.

    6. Forced-oscillation assessment. Map campus lines to modes, compute response at key generators and lines, compare with limits.

    7. Torsional screening. Where thermal units are electrically close.

    8. Ride-through and load-loss studies. Dynamic simulation of required faults with UPS, protection and generator logic.

    9. Harmonic studies. IEEE 519 compliance, resonance and supraharmonics.

    10. EMT studies. Where converter controls, weak grids or nearby inverter-based resources make phasor studies insufficient.

    11. Mitigation design. Load shaping, storage, compensators, reinforcement; repeat affected studies.

    12. Commissioning and verification. Tests and monitoring that prove the campus behaves as modeled.

    Keentel Study Spotlight — large-load interconnection study package. Keentel delivers the full sequence above as a single, consistent package, with one campus model used across steady-state, dynamic, EMT and harmonic studies, and a mitigation report that shows how each requirement is met.

    19. Modeling large computational loads

    Planning models traditionally represent load as a static or composite load model at a bus. That cannot represent a data center's UPS transfer logic, protection, cooling plant response or programmed power shaping. Better practice is to:

  • Represent the facility explicitly with a dynamic model that includes UPS behavior (ride-through thresholds, transfer to battery, retransfer and ramp), protection and backup generation.
  • Include the power profile where oscillation matters, either as a time-series input or as a parameterized source with defined lines.
  • Provide EMT models where converter interactions matter, with the actual control settings.
  • Validate against factory tests, site tests and recorded disturbances.
  • Several model structures for computational loads have been proposed by industry groups and vendors. Whatever structure is used, the important thing is that the parameters come from the actual facility design and are updated when settings change.

    How Keentel Engineering helps here. Keentel builds facility dynamic models from UPS, protection and cooling design data, tunes them against test results, and delivers them in the formats transmission providers require, with documentation that survives audit.

    20. Monitoring and verification

    Arc-furnace compliance was verified with flickermeters at the PCC. AI-campus compliance needs more:

  • High-resolution power recording at the PCC — enough to resolve oscillation lines up to at least several hertz, and ideally waveform capture for faults.
  • Synchrophasor measurement to correlate campus behavior with grid modes.
  • Event recording of UPS transfers, protection operations and job-level power events.
  • Spectral reporting of MW oscillation by band, trended over time.
  • Change control that triggers review when workloads, firmware or settings change.
  • How Keentel Engineering helps here. Keentel specifies monitoring systems, develops commissioning test plans, and analyzes recorded data to confirm compliance and update models.

    21. Sharing a PCC: steel mills and data centers together

    Some data center campuses are being sited near existing steel mills, attracted by the same strong transmission infrastructure. Two disturbing loads at one PCC raise new questions:

  • Flicker headroom. The mill may already use most of the flicker allocation; the campus must stay within what remains.
  • Combined voltage swings. Furnace ΔQ and campus ΔP add at the PCC.
  • Compensator sharing. A furnace SVC or STATCOM tuned for flicker may not be suitable for the campus's needs.
  • Harmonic interaction. Furnace harmonics and interharmonics may interact with campus filters and cable capacitance.
  • Ride-through sensitivity. Furnace-induced voltage fluctuations could trip campus UPS systems with tight input windows.
  • How Keentel Engineering helps here. Keentel studies combined loads at shared PCCs, allocates headroom fairly, and designs compensation and settings that keep both facilities compliant.

    22. Inside the facility: where the power swing is born and where it can be stopped

    It helps to follow the power path from the accelerator back to the PCC, because every stage is a place where the swing can be passed through, amplified, filtered or absorbed.

    Stage

    Typical US arrangement

    Effect on the swing

    Opportunity

    Accelerator and board power

    Point-of-load converters on the server board

    Generates the swing; edges set by power-management firmware

    Ramp limits, power floors, frequency avoidance

    Server power supply

    AC-DC or DC-DC supply in each server or rack shelf

    Small hold-up capacitance; passes the swing almost unchanged

    Little; hold-up covers only a few cycles

    Rack and row distribution

    Busway, 415/240 V AC or DC distribution at rack level

    Passes the swing

    Rack-level energy storage in some designs

    UPS

    Low-voltage or medium-voltage double-conversion or line-interactive UPS

    Passes the swing in normal mode unless controlled to smooth it

    Grid-interactive UPS control; battery buffering within backup limits

    Medium-voltage distribution

    13.8 kV or 34.5 kV switchgear and cables

    Passes the swing; cable capacitance affects harmonics

    Location for STATCOM or BESS connection

    Main power transformers

    230/34.5 kV or 345/34.5 kV

    Passes the swing; adds reactive losses that grow with load

    Little

    Campus-level storage or compensator

    BESS, E-STATCOM, supercapacitor bank at 34.5 kV or the high-voltage bus

    Absorbs MW swings, controls voltage

    The main hardware option

    PCC

    138, 230 or 345 kV

    Where limits are measured

    Monitoring and verification

    Two observations come from this table. First, nothing between the accelerator and the PCC naturally smooths the swing. Unlike a furnace, whose flexible cables and furnace transformer at least add impedance to the arc circuit, a data center's power path is designed to deliver clean, stiff power to the servers. Every element passes the server's demand straight to the grid. Second, there are only three places to stop it: at the source (in firmware), in the UPS (with grid-interactive control) or with dedicated storage at the campus bus. A robust design usually uses at least two of them, so that the campus still meets its limits when one is unavailable.

    Cooling: the slow layer

    Cooling systems — chillers, cooling towers, pumps, computer-room air handlers and, increasingly, liquid-cooling distribution units — add a slower layer to the profile. They follow the IT load with delays of tens of seconds to minutes, governed by thermal inertia and control loops. For oscillation in the 0.1–3 Hz bands, cooling is effectively constant. For checkpoint steps and job ends, cooling lags: when the IT load drops, cooling continues at high power for a while, then ramps down, which slightly softens the step seen by the grid. For ride-through, cooling is often the weak point, as case study 3 shows, because drives and compressors may trip on dips and restart slowly.

    How Keentel Engineering helps here. Keentel reviews the full power path inside the facility, from accelerator power management to the main transformers, and identifies where the swing can be shaped most cheaply and reliably — and where a second layer of control is needed as a backstop.

    23. Lessons from the arc-furnace era that still apply

    Seventy years of furnace connections left behind lessons that are not written in any single standard but are part of utility practice. Most apply directly to AI campuses.

  • The disturber pays. Utilities generally required furnace owners to fund the compensation needed to meet emission limits. The same principle is appearing in large-load requirements: the campus funds storage, compensators or shaping needed to meet oscillation and ride-through limits.
  • Measure before and after. Good furnace projects recorded background flicker and harmonics at the PCC before the furnace was connected, so that later complaints could be attributed fairly. AI campuses need the same baseline for MW oscillation and voltage fluctuation.
  • Leave headroom for the next customer. Allocation methods for flicker reserve part of the planning level for future connections. A first AI campus should not be allowed to use the entire oscillation headroom in an area.
  • Know the weak configuration. Furnace studies were always run at the minimum credible short-circuit level, not just the normal one. AI campus studies should be run with the critical outages and the lowest-damping dispatch.
  • Compensators need maintenance plans. Furnace SVCs taken out of service for maintenance caused flicker excursions (case study 2). For AI campuses, the plan must state what happens when storage or a compensator is out: reduced operation, stricter shaping or curtailment.
  • Process changes are often the cheapest fix. Foamy slag and scrap preparation reduced furnace flicker at little cost. Workload scheduling and firmware limits play the same role for AI campuses.
  • Expect the load to grow and change. Furnaces were upgraded, and so will AI campuses be, with every hardware generation and every new training method. Requirements and studies should include a trigger for review when the load changes materially.
  • Keentel Study Spotlight — baseline and attribution survey. Before a large load connects, Keentel installs or reviews high-resolution monitoring at the proposed PCC and nearby buses to record background voltage fluctuation, harmonics and MW oscillation. The baseline makes later compliance assessment fair to the new customer and to everyone already connected.

    24. The economics of mitigation

    Engineering decisions about large-load mitigation are ultimately economic decisions under technical constraints. The relative cost of each option is a useful first guide, though actual costs vary widely by project and market.

    Option

    Typical cost driver

    Strength

    Limitation

    Firmware load shaping

    Engineering effort; small throughput or energy penalty

    Cheapest per MW of oscillation reduction; acts at the source

    Depends on software discipline; needs monitoring and a backstop

    Power floor or synthetic load

    Continuous energy cost (about 1.4% of energy in worked example 11)

    Simple and effective for the iteration line

    Ongoing operating cost; increases cooling load

    Grid-interactive UPS control

    Controls engineering; battery cycling

    Uses equipment already installed

    Must not reduce backup time; battery life impact

    Campus BESS or E-STATCOM

    Converter rating (MW) more than energy (MWh)

    Handles all bands and checkpoint steps; independent of software

    Capital cost; cycle-life and thermal checks; control interaction studies

    STATCOM

    Mvar rating

    Solves voltage problems cheaply

    Does nothing for MW swings

    Synchronous condenser

    MVA rating, civil works, maintenance

    Adds inertia and fault level

    Does not absorb sustained MW swings

    Network reinforcement

    Lines, transformers, substations

    Raises short-circuit level; may improve damping

    Long lead times; may not fix forced oscillation

    Flexible service

    Revenue or rate effect; operational constraints

    Can speed interconnection

    Requires reliable, ramped curtailment

    The pattern in Keentel's studies is consistent: software shaping first, storage second, voltage support as required, reinforcement where the network needs it anyway. The order mirrors the furnace experience — process improvement, then fast compensation, then reinforcement — with the important difference that the AI campus's process improvement can be implemented in weeks rather than years.

    A simple cost-per-reduction comparison

    For a 300 MW campus with a 10 MW line at 0.5 Hz and a limit of 3 MW:

  • Firmware shaping that removes 70% of the line meets the limit on its own. Its cost is mostly engineering and a small loss of throughput.
  • A power floor alone removes about two-thirds of the line, slightly short of the limit, at an energy cost of about 1.4% of campus consumption — roughly 4 MW continuous.
  • A BESS or E-STATCOM sized to absorb 7 MW of oscillation amplitude meets the limit with margin but costs far more per MW of reduction than shaping.
  • The combination of shaping and a modest buffer is usually the least-cost design that also stays compliant when one layer is unavailable — which is what case study 1 found.

    How Keentel Engineering helps here. Keentel presents mitigation options with technical performance and a cost basis side by side, so owners and transmission providers can agree on the least-cost design that meets the requirement and survives equipment outages.

    25. Questions to ask at each project stage

    Stage

    Questions for the owner

    Questions for the transmission provider

    Site selection

    How large will the campus grow? Will it run one large job or many small ones?

    What is the short-circuit level under outages? Are there known lightly damped modes or thermal units nearby?

    Interconnection request

    What load profile, ride-through settings and models can we provide now?

    Which large-load requirements apply, and which version?

    System impact study

    Is the profile realistic for the hardware we will buy?

    Which bands and limits will be enforced? Is a combined study needed with other large loads?

    Facility design

    Where will shaping live? Which UPS and protection settings meet ride-through?

    Will the provider accept firmware shaping as a compliance measure? What monitoring is required?

    Procurement

    Can the UPS, drives and storage meet the ride-through envelope and cycle life?

    What model formats and test evidence are needed?

    Commissioning

    Which tests will prove shaping, ride-through and storage response?

    What data must be submitted and when?

    Operation

    What changes in workload, firmware or hardware trigger a review?

    How will exceptions be reported and handled?

    How Keentel Engineering helps here. Keentel supports owners and transmission providers at every stage, from site screening to operational compliance, so that each question is answered before it becomes a delay.

    26. Operating the grid with large computational loads

    Planning studies decide whether a campus can connect. Operations decide whether it runs safely day to day. The arc-furnace era offers a template here too: large furnaces were often scheduled in coordination with the utility, especially during system emergencies or when compensators were out of service. AI campuses need a similar but faster operating relationship.

    Information the transmission operator needs
  • Real-time campus demand and the amount of load that could be lost on a voltage dip.
  • Planned large changes — job starts, scheduled checkpoints on very large jobs, maintenance transfers to backup generation — with notice.
  • Status of mitigation equipment — storage, compensators and shaping functions — and any reduction in capability.
  • Status of backup power — whether the campus is on grid supply, on generators or in transition — and the planned return.
  • Coordinated return from backup power

    One of the clearest lessons of the 2024 event is that reconnection matters as much as disconnection. A campus that returns hundreds of megawatts to the grid in one step after a disturbance creates a second disturbance. Good practice is an automatic, ramped return — for example over several minutes — that the transmission operator can pause or delay, with staggered return of halls or buildings.

    Operating limits during outages

    When a critical transmission element is out, or when a mitigation device is unavailable, the campus may need to operate within reduced limits: stricter ramp rates, staggered jobs, a lower maximum demand or a commitment not to start new large jobs. These limits should be agreed in advance and written into operating procedures, so that they can be applied quickly without negotiation.

    Event analysis

    Every large-load event — a transfer to backup, an oscillation alarm, a ride-through failure — should be analyzed jointly by the owner and the transmission operator, using recorded data from both sides. The findings feed model updates and setting changes. This is the same cycle that steel mills and utilities followed for furnace flicker complaints, carried out at a larger scale and higher speed.

    Worked example 8, revisited — reserves for load loss

    If a transmission operator must carry a load-loss contingency for a campus that might drop off on a fault, it must keep generation able to reduce output quickly by that amount, or accept the resulting overfrequency. For a 500 MW campus, that is a 500 MW downward-reserve obligation in the area, with associated cost and operating constraints. When ride-through settings remove the load-loss risk for normally cleared faults, as in case study 3, the contingency can be reduced or removed. Ride-through is not just a reliability improvement; it frees operating margin.

    Keentel Study Spotlight — operating procedures for large loads. Keentel helps owners and transmission operators write the operating procedures that turn study results into daily practice: data exchange, notice of large changes, ramped return from backup, reduced-capability limits and joint event analysis.

    27. Ten common mistakes

    1. Treating an AI campus as a constant load in planning studies.

    2. Relying on flicker screening alone and concluding the campus is benign.

    3. Sizing a STATCOM and assuming it solves the oscillation problem.

    4. Ignoring coherence and estimating swings from random aggregation.

    5. Overlooking checkpoint steps and job-end drops.

    6. Setting UPS input windows tightly without considering transmission fault clearing.

    7. Implementing load shaping only in job-level software that can change without notice.

    8. Sizing storage for energy instead of power and cycle life.

    9. Skipping torsional screening near thermal plants.

    10. Studying the campus without the actual protection and UPS settings.

    28. A checklist for owners and planners

  • Campus profile defined, with coherence assumptions stated.
  • PCC short-circuit levels under normal and outage conditions known.
  • Flicker screening completed and reported beside oscillation assessment.
  • Modes near the campus identified with damping.
  • Forced-oscillation response computed at key generators.
  • Torsional screening done where thermal units are near.
  • Ride-through settings coordinated with protection clearing times.
  • Load-loss study completed for required faults, including reclosing.
  • Harmonic study complete with resonance check.
  • Mitigation selected with verified performance.
  • Load-shaping specification defined in electrical terms and controlled at facility level.
  • Monitoring specified and commissioning tests planned.
  • Models validated and documented.
  • 29. Summary of the worked examples

    No.

    Topic

    Key result

    1

    Per-node training profile

    8.42 kW average; 0.5 Hz line 0.31 kW

    2

    Coherent aggregation

    100 MW: 3.7 MW coherent vs 34 kW incoherent; 500 MW checkpoint step 227 MW

    3

    ΔV at 230 kV PCC

    Furnace 1.25%; AI step 0.67%; STATCOM 34 Mvar holds AI voltage

    4

    Furnace Pst screening

    Pst 6.0 at 2,000 MVA; STATCOM brings it to 1.5

    5

    Resonance gain

    10× at 5% damping

    6

    Torsional gain

    100–500× at 0.1–0.5% damping

    7

    Storage sizing

    8.84 kWh per half cycle for ±50 MW at 0.5 Hz

    8

    Frequency after load loss

    0.06 Hz for 1,500 MW large interconnection; 0.33 Hz for 3,000 MW smaller interconnection

    9

    Fault exposure

    4.5 faults/yr; clearing 83–500 ms

    10

    Harmonic TDD

    27.7% 6-pulse; 2.5% active front end

    11

    Load shaping

    Ramp limits cut 0.5 Hz line 8–84%; floor costs 1.43% energy

    12

    Flexibility value

    $3.29 M/yr for 60 MW

    13

    Active-power stabilizer

    227 MW step reduced to 76 MW

    14

    Flicker blindness

    0.015% ΔV at 230 kV for a 3.7 MW line

    15

    DC furnace

    Pst 4.0

    16

    Synthetic furnace

    Mean 69.8 MW, std 17.6 MW

    Part C — Three Anonymous US Case Studies

    The three cases below are composites built from typical project situations. Names, locations, ratings and numbers have been changed, and no case describes a single real project or client. They show how the arc-furnace playbook was adapted, step by step, in situations Keentel engineers see in practice.

    Case study 1 — A 300 MW training campus in Texas and a 0.5 Hz line that would not go away

    The situation

    A developer planned a 300 MW AI training campus in central Texas, connected at a new 230 kV switching station looped into an existing double-circuit line. The campus would house one very large training cluster in its first phase, running a single job at a time for weeks — the most coherent workload pattern possible. The transmission provider's large-load requirements, written under the regional ride-through and fluctuation rules, asked for a dynamic model, a ride-through demonstration and evidence that periodic power fluctuations would stay within stated limits in sub-synchronous bands.

    The developer's first submission described the campus as a 300 MW constant-power load with a 0.98 power factor, plus a statement that UPS systems would "ride through all grid events." The transmission provider rejected it and asked for a characterized load profile.

    What Keentel found

    Keentel's first task was to build a credible profile. The developer's compute team supplied accelerator power data from a pilot cluster running a 70-billion-parameter open model training run. The pilot traces showed an iteration rhythm of about 1.8–2.2 s, depending on batch size, with a swing of about 9% of training power between compute and communication phases, and checkpoints every 20–30 minutes lasting 10–15 s.

    Scaled to 300 MW with full coherence, the profile gave:

  • A 0.5 Hz line of roughly 10–14 MW amplitude, with harmonics at 1.0, 1.5 and 2.5 Hz.
  • Checkpoint steps of about 130 MW in under a second.
  • Job-start ramps of about 150 MW over 5–10 s after data loading.
  • The short-circuit level at the new switching station was about 4,200 MVA with all lines in service and about 2,600 MVA with one circuit out. Voltage effects were modest: the checkpoint step produced a ΔV of about 0.5% with all lines in service and under 1% with a circuit out. Flicker screening gave Pst well below 0.5. On voltage alone, the campus looked benign.

    The mode survey told a different story. Small-signal analysis of the regional model, cross-checked against ringdown analysis of synchrophasor records from earlier generator trips, identified a local mode near 0.55 Hz involving two combined-cycle plants and a group of wind plants about 60 miles away, with damping estimated between 4% and 7% depending on dispatch. The campus's 0.5 Hz line sat within 10% of it.

    Using the resonance relationship from worked example 5, with r ≈ 0.91 and ζ = 5%, the gain was about five (5.1). A detailed dynamic simulation, injecting the campus profile as a time series, showed sustained MW oscillation of 30–45 MW peak to peak on the combined-cycle units' outputs, and oscillation on a 345 kV tie that exceeded the provider's monitoring alarm threshold. Under the low-damping dispatch, the response was larger still.

    Options considered

    Keentel evaluated four approaches:

    Option

    Effect on 0.5 Hz line

    Cost and trade-offs

    STATCOM, 60 Mvar

    Held voltage; no effect on MW line

    Moderate cost; did not address the problem

    Ramp limit and power floor in facility firmware

    Reduced the line by 65–80%

    Low cost; small throughput penalty; required firmware control at facility level

    Battery E-STATCOM, 60 MW / 15 MWh

    Reduced the line by about 90% with power-oscillation control; bridged checkpoints

    Higher cost; cycle-life analysis required

    Change iteration rhythm away from the mode

    Moved the line away; gain fell to about 1.5

    No hardware cost; constrained the compute team; not guaranteed for future jobs

    The solution

    The final design combined two layers:

  • Load shaping in facility firmware. A per-node ramp limit and a communication-phase power floor, implemented in the accelerator power-management layer controlled by the facility rather than by individual jobs. Checkpoints were staggered across four cluster partitions so that no more than a quarter of the campus paused at once.
  • A 60 MW / 15 MWh E-STATCOM. It provided voltage control, a power-oscillation control loop targeting the 0.3–1.0 Hz band and checkpoint bridging. Its sizing followed worked example 7: the swing energy was small, so the rating was set by power and cycle life rather than energy.
  • The combination reduced the 0.5 Hz line at the PCC by about 92% in simulation, and the combined-cycle units' oscillation fell below 4 MW peak to peak under the worst dispatch. The checkpoint step seen by the grid fell from 130 MW to about 25 MW, ramped over 20 s.

    Keentel also corrected the ride-through design. The original UPS input window would have transferred the campus to batteries for any dip below 85% lasting more than 20 ms. Coordinated with the transmission protection clearing times, the revised settings held the campus on the grid through faults cleared within the provider's required envelope, with a ramped return after longer events.

    Verification

    Commissioning included staged tests: training at partial scale with shaping disabled and enabled, a deliberate checkpoint with and without staggering, and an E-STATCOM response test. High-resolution PCC monitoring confirmed the line reduction within a few percent of the study prediction. The transmission provider accepted the campus model and added it to its planning cases.

    Lessons
  • A campus that passes voltage and flicker screening can still drive a power system mode.
  • The mode survey decided the outcome. Without it, the line near 0.55 Hz would have been missed.
  • Software shaping did most of the work; storage closed the gap and provided a backstop if firmware settings change.
  • Load shaping is enforceable only if it lives at the facility level and is monitored at the PCC.
  • Case study 2 — A Midwest mini-mill and a new data center on one 138 kV substation

    The situation

    A steel company operated a mini-mill in the Midwest with one 120-ton AC arc furnace and a ladle furnace, connected to a 138 kV substation through a dedicated furnace transformer. The mill had an SVC installed in the 1990s, sized for flicker compensation, and a long record of compliance with the utility's flicker allocation. A data center developer purchased land next to the mill and proposed a 150 MW campus, to be served from a new bay on the same 138 kV substation. The campus would host a mix of training and inference workloads.

    The utility's concern was straightforward: two disturbing loads on one bus. It asked for a combined study.

    What Keentel found

    Keentel began with the mill's history. The utility supplied fifteen years of IEEE 1453 measurements at the PCC: with the SVC in service, the 95th percentile Pst during furnace operation was about 0.65, against a planning level of 0.8. With the SVC out of service — which had happened twice for maintenance — Pst exceeded 1.4. The bus short-circuit level was about 2,800 MVA normally, falling to about 1,900 MVA with one 138 kV source out.

    The campus's contribution to flicker was negligible, as worked example 14 predicts. But the study found three real issues:

    1. UPS sensitivity to furnace fluctuation. The campus UPS design specified a rectifier input window of ±10% with a fast transfer to battery. Measured furnace-induced voltage fluctuation on the bus, during bore-in with the SVC in service, reached about 2–3% in short bursts, and during an SVC outage about 5%. Those were within the window, but the combination of furnace fluctuation with a transmission fault on the outage configuration could push the bus outside the window more often than either alone.

    2. Combined voltage swings at the PCC. Furnace ΔQ and campus checkpoint ΔP added at the bus. At 1,900 MVA, a 60 MW campus step coinciding with a furnace bore-in swing produced combined ΔV of about 2%, above the utility's step-change criterion.

    3. Harmonic interaction. The SVC's filter banks, tuned near the 2nd, 3rd and 5th harmonics, interacted with the campus's long medium-voltage cable runs, shifting a parallel resonance closer to the 7th harmonic. Background 7th harmonic voltage on the bus would be amplified.

    The solution

    The solution worked on both sides of the bus:

  • Campus ride-through. The UPS input window and transfer logic were revised to ride through fluctuations and short dips on the input, with transfer reserved for sustained events. That removed the sensitivity to furnace fluctuation.
  • Checkpoint ramping. The campus agreed to ramp checkpoint and job-start steps at no more than about 2 MW per second at the PCC, enforced in facility firmware and backed by a 20 MW battery used for ramp control.
  • Separate voltage control. Rather than retune the mill's SVC, which was optimized for flicker, the campus installed its own 40 Mvar STATCOM in voltage-control mode, coordinated with the SVC through slow reference adjustment to avoid control fighting.
  • Harmonic filter adjustment. A 7th-harmonic filter branch was added on the campus side, and the campus cable network was re-checked for resonance.
  • Headroom allocation. The utility formally reallocated flicker headroom, leaving the mill's existing allocation intact and assigning the campus a small allocation — which it used only marginally.
  • Verification

    After energization, PCC monitoring showed the mill's Pst unchanged, the campus's MW steps within the agreed ramp, and the 7th harmonic voltage on the bus lower than before the campus was built, because of the added filter. During the following year, two transmission faults on the area network caused dips at the bus; the campus rode through both.

    Lessons
  • Shared PCCs need combined studies; each load passing alone is not enough.
  • The furnace's measured flicker record was the best available data on the bus's behavior.
  • Two compensators on one bus must be coordinated or they will fight.
  • The data center's biggest exposure was not its own disturbance but its sensitivity to its neighbor's.
  • Case study 3 — A 500 MW Mid-Atlantic campus and the cost of dropping off

    The situation

    An owner operated a 500 MW data center campus in the Mid-Atlantic region, connected at 230 kV through two transformers and a ring bus. The campus hosted a mix of training and cloud workloads. After the 2024 load-loss event and the large-load alerts that followed, the transmission provider asked large-load customers in its zone to demonstrate ride-through performance and provide validated dynamic models.

    The owner's records showed the campus had transferred to backup power three times in the previous two years, each time following a transmission fault, and each time returning to grid power manually over 30–90 minutes. Each event removed 300–420 MW from the grid within a few cycles.

    What Keentel found

    Keentel's review traced each transfer to specific settings:

  • UPS rectifier input undervoltage. Set to transfer to battery at 80% voltage after 10 ms. All three faults produced dips below 80% for 60–120 ms.
  • Medium-voltage undervoltage relays. Set at 85% with a 0.5 s delay to open the utility main breakers and start the generators. On two of the three events, reclosing produced repeated dips, and the accumulated time exceeded the timer.
  • Chiller and pump drives. Tripped on dips below 70% and restarted only after a 3-minute lockout. Facility thermal management then held the campus on generators while cooling recovered.
  • Retransfer logic. Manual, by design, after the facility operations team confirmed grid stability.
  • A fault exposure estimate, following worked example 9, suggested about four to five faults per year close enough to produce dips below 80% at the campus, consistent with the observed history.

    Keentel built a dynamic model of the campus including UPS logic, relay settings, generator start and the mechanical systems, and validated it against the recorded data from two of the three events. The validated model reproduced the load loss timing within one cycle.

    Options considered

    The study tested settings and equipment changes against the transmission provider's ride-through envelope:

    Change

    Effect

    UPS rectifier input: ride through dips to 0% for 150 ms and to 70% for 2 s, using battery support without transfer

    Eliminated rectifier-driven load loss for normally cleared faults

    MV undervoltage relays: coordinated with clearing times and reclosing intervals; transfer only on sustained loss

    Eliminated relay-driven load loss for reclosing sequences

    Chiller and pump drives: ride-through-capable drive settings, shorter restart lockouts, staggered restarts

    Kept cooling running through short dips

    Automatic ramped return: after a transfer, return to grid over 10 minutes in coordination with the transmission operator

    Removed the manual delay and the large reconnection step

    Synchronous condenser at the campus

    Considered for added fault level and inertia; not selected because ride-through changes solved the problem

    The solution

    The owner implemented the settings changes in stages over six months, with Keentel reviewing each change before it went live and confirming with the equipment manufacturers that the revised windows were within equipment capability. A small number of older UPS modules could not support the wider window and were scheduled for replacement.

    The revised campus model was submitted to the transmission provider and accepted. In the provider's planning cases, the campus now remained connected for all normally cleared faults in the required set, and the load-loss contingency the provider had been carrying for the campus was removed from its operating studies.

    Verification

    In the year after the changes, two transmission faults produced dips at the campus. The campus stayed on grid power through both, with no UPS transfers and no generator starts. Recorded PCC data confirmed the model's prediction of the campus's power during and after the dips.

    Lessons
  • Load loss is a settings problem more often than an equipment problem.
  • A validated model, tested against real events, is what makes the transmission provider confident.
  • Mechanical systems matter: cooling trips can force a facility onto generators even when the electrical systems rode through.
  • Coordinated, ramped return is as important as staying connected.
  • What the three cases have in common

  • Each started with a load described too simply — a constant MW figure and a power factor.
  • Each was solved by understanding the load in the time and frequency domains, not just its size.
  • Arc-furnace methods — headroom allocation, compensator coordination, measured PCC data — were directly useful.
  • The new elements — mode surveys, load-shaping specifications, ride-through coordination — were decisive.
  • Verification at the PCC closed each project and gave the transmission provider confidence.

  • Part D — 30-Question Technical FAQ

    1. Is it true that the grid has handled loads like AI campuses before?

    In important ways, yes. Electric arc furnaces have connected to US transmission systems since the 1950s and produced fast, large, irregular load swings, harmonics and occasional generator interaction. The industry developed planning levels, emission allocation, compensators, storage-backed compensation and furnace supply changes to manage them. What is new is the scale (hundreds of megawatts to gigawatts), the dominance of active power over reactive power, the narrowband spectrum and the ability of data centers to disconnect themselves during faults.

    2. What is the main physical difference between an arc furnace and an AI campus?

    An arc furnace swings mainly reactive power, which moves voltage strongly at a transmission bus. An AI campus swings mainly active power at near-unity power factor. Active power moves voltage less at a high-X/R bus, but it reaches generators directly, affecting rotor angles, frequency and electromechanical modes. Worked example 3 shows a smaller furnace swing causing almost twice the voltage change of a much larger AI step at the same 230 kV bus.

    3. Why do AI training loads swing at all?

    Training alternates between compute phases, when accelerators work at high power, and communication phases, when they exchange results and draw less. Because the whole cluster is synchronized, thousands of servers change power together. Checkpoints, job starts and job ends add larger steps. Inference workloads and conventional cloud workloads are usually less coherent.

    4. How large is the swing in practice?

    It depends on the hardware, software and workload. Keentel's illustrative profile uses a swing of about 7% of training power within each iteration and a checkpoint step of about 45% of training power. Measured clusters have shown larger swings in some cases. The campus profile should be built from the owner's actual hardware and workload data.

    5. Why does synchronization matter so much?

    Independent swings add like random variables: the total grows with the square root of the number of servers. Synchronized swings add directly. For about 12,000 servers, that is a factor of about 109 (worked example 2). A campus dedicated to one large job is close to the synchronized case.

    6. What frequencies do AI campuses produce?

    The main line sits at the iteration frequency — often a fraction of a hertz to a few hertz — with harmonics above it. Checkpoints and job events add very-low-frequency content. Faster electronic transitions add smaller content up to tens of hertz.

    7. Why is a narrowband line more dangerous than broadband noise?

    A narrowband line concentrates its energy at one frequency. If that frequency is near a lightly damped power system mode, the response is amplified by roughly 1/(2ζ) — ten times at 5% damping. Broadband noise excites every mode a little; a narrow line excites one mode a lot.

    8. Can a STATCOM solve AI oscillation problems?

    A STATCOM can hold PCC voltage nearly constant for a modest rating — about 34 Mvar for a 227 MW step in worked example 3. It cannot change the active power the campus draws, so generators still see the MW swing. Solving the MW problem needs stored energy, load shaping or generation.

    9. What is an E-STATCOM?

    An E-STATCOM is a STATCOM with energy storage — usually batteries or supercapacitors — on its DC side. It can exchange active as well as reactive power, so it can buffer MW swings and support voltage with one converter.

    10. How much storage does a training campus need?

    For oscillation, very little energy and a lot of power. A ±50 MW swing at 0.5 Hz needs only about 8.84 kWh per half cycle (worked example 7), but the buffer cycles tens of thousands of times per day. For checkpoint bridging, more energy is needed — about 0.76 MWh for a 227 MW, 12 s pause — and power capability approaching the step size. Size for power, energy and cycle life together.

    11. Is flicker still relevant for AI campuses?

    Yes, as a requirement — many agreements require flicker compliance — and for neighbors with sensitive equipment. But flicker screening will usually show an AI campus as harmless, because the flickermeter is insensitive to slow MW swings. It should be reported beside an oscillation assessment, never instead of one.

    12. What flicker limits apply in the United States?

    IEEE 1453-2022 provides the measurement method and indicative planning levels; utilities set their own planning levels and emission allocations. High-voltage planning levels around Pst 0.8 and Plt 0.6 are commonly cited. Use the transmission provider's current values.

    13. What is Kst and how is it used?

    Kst is an empirical severity coefficient for arc furnaces used in the screening relationship Pst ≈ Kst · SscF / Ssc. Values around 48–85 are used for AC furnaces, commonly 60 for screening; DC furnaces are often taken at about two-thirds of the AC value. It is a screening tool only.

    14. What happened in the 2024 load-loss event?

    NERC's incident review describes a July 2024 event in which a fault on a 230 kV line in Northern Virginia, followed by reclosing attempts, caused repeated voltage dips. Data centers transferred to backup power and about 1,500 MW of load disconnected. The grid remained stable, but the event exposed gaps in modeling, ride-through settings and reconnection coordination.

    15. Have there been larger events since?

    Reports in 2026 described a larger Northern Virginia event in July 2026 with roughly 3–4 GW of data center load lost during a transmission disturbance. NERC issued a Level 3 alert on large loads in May 2026. Treat the 2026 magnitudes as reported values pending NERC's final analysis.

    16. Why do data centers disconnect during faults?

    UPS systems and facility protection are designed to protect the critical load from any grid disturbance outside a tolerance window. When voltage dips, the UPS transfers to batteries and the facility may start generators and open its utility breakers. That protects servers but removes load from the grid.

    17. Can a data center ride through faults without risking its servers?

    Usually yes. The UPS batteries can carry the load through short dips while the rectifier stays connected, so the grid sees a continued load or a quick return. The settings must be coordinated with transmission fault clearing times and reclosing sequences and checked against equipment capability. Case study 3 shows an example.

    18. What ride-through requirements apply?

    They are evolving by region. ERCOT's NOGRR 282 addresses ride-through for large electronic loads; MISO and others have proposed large-load reliability requirements; NERC's alerts recommend ride-through practices. Confirm the transmission provider's current requirements at the start of each project.

    19. How does load loss affect frequency?

    Sudden load loss raises frequency. In a very large interconnection, 1,500 MW might raise settling frequency by about 0.06 Hz; in a smaller one, 3,000 MW might raise it by about 0.33 Hz with an initial RoCoF above 0.2 Hz/s (worked example 8, illustrative). Local overvoltage can be the more immediate concern.

    20. Do AI campuses cause torsional problems?

    They can, if they are electrically close to thermal turbine-generators and their power contains energy near torsional frequencies. Idealized profiles show small but nonzero content in the torsional range (worked example 6). Screening with actual generator data and high-resolution campus power traces is the only reliable answer.

    21. Are AI campuses harmonic problems?

    Modern campuses with active front ends usually meet IEEE 519 limits comfortably (about 2.5% TDD in worked example 10). Watch for supraharmonics in the kilohertz range, resonance with large campus cable networks, and reduced cancellation when converters switch in synchronism.

    22. What is load shaping?

    Load shaping controls the campus's power profile at its source: ramp limits on each server, power floors during communication phases, synthetic load during pauses, staggered checkpoints and avoidance of iteration rhythms near grid modes. In worked example 11, ramp limits cut the 0.5 Hz line by 59–84%, and a power floor cut it by two-thirds at 1.43% extra energy.

    23. Who should control load shaping?

    The facility, not individual jobs. Shaping that lives only in training scripts can change with the next software release. It should be defined in electrical terms, implemented in a facility-controlled layer such as power-management firmware or a site controller, and monitored at the PCC.

    24. Does load shaping cost compute performance?

    Sometimes. Ramp limits during compute phases can lengthen iterations; power floors burn extra energy. The trade-off depends on how power-limited the accelerators are. The compute team must confirm it, which is why shaping should be agreed early in the project.

    25. How should oscillation limits be defined?

    Keentel's view is to keep the arc-furnace framework — planning levels, allocation, emission limits, verification — and change the metric to MW oscillation amplitude by frequency band, weighted by the grid's sensitivity in each band. Transmission providers are still defining bands and limits; several published requirements use different splits.

    26. Can a data center share a substation with a steel mill?

    Yes, with a combined study. Flicker headroom, combined voltage swings, compensator coordination, harmonic interaction and the data center's sensitivity to furnace fluctuation all need checking. Case study 2 shows an example.

    27. Do synchronous condensers help with AI campuses?

    They add fault level and inertia, which stiffen voltage and slow frequency change after load loss. They do not absorb sustained MW swings. They are most useful where the grid is weak or where inertia is low.

    28. What models does a transmission provider need for an AI campus?

    A dynamic model that represents UPS ride-through and transfer logic, protection, backup generation and cooling response; a representation of the power profile where oscillation matters; and, where converter interaction is a concern, an EMT model with actual settings. Models should be validated against tests or recorded events.

    29. What monitoring should an AI campus have?

    High-resolution power recording at the PCC, synchrophasor measurement, event recording of UPS and protection operations, spectral reporting of MW oscillation by band, and change control that triggers review when workloads, firmware or settings change.

    30. How can Keentel help?

    Keentel characterizes campus load profiles, performs short-circuit, flicker, oscillation, torsional, ride-through, harmonic and EMT studies, designs load-shaping specifications and storage or compensator solutions, builds and validates facility models, supports interconnection submittals, and verifies performance at commissioning — for data centers, steel mills and other large loads from 4 kV to 765 kV.


    How Keentel Engineering Helps

    Keentel Engineering supports data center developers and owners, steel and industrial customers, utilities and transmission providers in connecting large, fast-changing loads safely and on schedule.

    Need Keentel service Outcome
    Know the load Campus load characterization from workloads, hardware data and measured traces A defensible profile of iteration lines, steps and coherence that every study can use
    Plan the connection Load flow, contingency and short-circuit studies at the proposed PCC Upgrades, limits and outage conditions identified early
    Check voltage and flicker ΔV, flicker screening and IEEE 1453 assessment Voltage support sized for what it can fix; flicker obligations met
    Find the modes Small-signal analysis and synchrophasor ringdown review The grid modes that matter, with frequency and damping
    Assess oscillation Forced-oscillation studies with the campus profile Response at generators and ties compared with limits
    Protect generators Torsional interaction screening and EMT studies Shaft exposure quantified and managed
    Stay connected Ride-through and load-loss studies with UPS, protection and cooling logic Settings that keep the campus on the grid for normally cleared faults
    Control harmonics IEEE 519 studies, frequency scans, filter design Compliance and resonance-free campus networks
    Shape the load Load-shaping specifications for compute and facilities teams Oscillation and ramp limits met in software, verified at the PCC
    Size the hardware Storage, E-STATCOM, STATCOM and synchronous condenser sizing Equipment rated for power, energy and cycle life
    Share a PCC Combined studies for steel mills and data centers Fair headroom allocation and coordinated compensators
    Model the facility Dynamic and EMT model development and validation Models the transmission provider accepts
    Prove it Commissioning test plans, monitoring specifications, event analysis Evidence that the campus behaves as studied
    Independent oversight Owner's engineer and lender's technical review Study gaps caught before financial close or energization

    Why Clients Choose Keentel


    • Both worlds under one roof. Engineers who know arc-furnace flicker and compensation as well as data center UPS, ride-through and oscillation studies.
    • Independent advice. We do not sell compensators, batteries, accelerators or software; our recommendations serve the owner and the grid.
    • Study depth. Short-circuit, phasor dynamic, EMT, harmonic and torsional studies with one consistent facility model.
    • Field experience. Commissioning, monitoring and event analysis, not only desk studies.
    • Compliance integrated. Study results tied to NERC large-load guidance, regional requirements and IEEE 1453 and IEEE 519.
    • Licensed professional engineering. Florida-registered engineering firm (Firm Registration No. 36853) with offices in Tampa, Austin, Sacramento and Baltimore, supporting projects nationwide from 4 kV to 765 kV.
    • Credentials. NSPE, D-U-N-S registered, IEEE Senior Member leadership, BBB Accredited Business with an A+ rating.


    Talk to Keentel Engineering


    Planning an AI campus, sharing a substation with a steel mill, facing a new large-load ride-through requirement or seeing oscillations you cannot explain? Keentel can scope the right studies and deliver results your transmission provider will accept.


    • Phone: (813) 389-7871
    • Email: contact@keentelengineering.com
    • Book a 15-minute call: calendly.com/keentel-engineering/15min
    • Web: keentelengineering.com


    References


    All links accessed November 2026. Requirements change; confirm current versions with the issuing body.


    NERC reports, alerts and task force


    • NERC, White Paper: Characteristics and Risks of Emerging Large Loads, 2025. https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/3_doc_white-paper-characteristics-and-risks-of-emerging-large-loads.pdf
    • NERC, Incident Review: Considering Simultaneous Voltage-Sensitive Load Reductions (Large Load Loss), 2025, covering the July 2024 event. https://nerc.com/pa/rrm/ea/Documents/Incident_Review_Large_Load_Loss.pdf
    • NERC, Level 2 Alert: Large Loads, 2025. https://www.nerc.com/pa/rrm/bpsa/Alerts%20DL/NERC%20Alert%20Level%202%20%20Large%20Loads.pdf
    • NERC, Large Loads Task Force work plan and resources. https://www.nerc.com/comm/RSTC/LLTF/
    • Utility Dive, coverage of NERC's 2026 Level 3 alert on large-load disruptions. https://www.utilitydive.com/news/data-center-load-disruptions-nerc-alert-recommendations/818036/


    Regional requirements


    • ERCOT, NOGRR 282, ride-through requirements for large electronic loads. https://www.ercot.com/mktrules/issues/NOGRR282
    • ERCOT, Large Load Interconnection Process Q&A, December 2025. https://www.ercot.com/files/docs/2025/12/24/Large-Load-Interconnection-Process-Q-A.pdf
    • ERCOT, Interconnection and Grid Analysis Update, Board item, September 2026. https://www.ercot.com/files/docs/2026/09/17/10-Interconnection-and-Grid-Analysis-Update-REVISED.pdf
    • MISO, Large Load Working Group, Large Load Interconnection Reliability Requirements, April 2026. https://cdn.misoenergy.org/20260420%20LLWG%20Item%2006%20Large%20Load%20Interconnection%20Reliability%20Requirements751448.pdf


    Industry reports and research


    • Energy Systems Integration Group (ESIG), Large Loads Performance Requirements report, 2026. https://www.esig.energy/wp-content/uploads/2026/03/ESIG-Large-Loads-Performance-Requirements-report-2026c.pdf
    • GridLab, Large Loads Interim Report, March 2025. https://gridlab.org/wp-content/uploads/2025/03/GridLab-Report-Large-Loads-Interim-Report.pdf
    • Research preprints on power transients of large AI training workloads and their mitigation, arXiv, 2025–2026. https://arxiv.org/pdf/2508.14318v1 and https://arxiv.org/pdf/2604.15522
    • US Department of Energy Office of Scientific and Technical Information (OSTI), record on static shunt compensation for arc-furnace flicker. https://www.osti.gov/biblio/5274118


    Standards


    • IEEE Std 1453-2022, Recommended Practice for the Analysis of Fluctuating Installations on Power Systems. https://standards.ieee.org/ieee/1453/
    • IEEE Std 519-2022, Standard for Harmonic Control in Electric Power Systems. https://standards.ieee.org/ieee/519/
    • IEC TR 61000-3-7, Assessment of emission limits for the connection of fluctuating installations to MV, HV and EHV power systems (international reference). https://webstore.iec.ch/


    Historical literature


    • C. Concordia and co-authors, AIEE Transactions papers of the 1950s on voltage dips and synchronous machine response to arc-furnace loads (exact title and pages should be confirmed in the IEEE Xplore archive).
    • Industry references describing the 1999 STATCOM installation for arc-furnace flicker compensation at a steel plant in Hagfors, Sweden.
    • P. Kundur, Power System Stability and Control, McGraw-Hill, 1994.


    Related Keentel guides


    • Joint Large-Load and Generation Studies
    • 1 GW Data Center Explained
    • STATCOM V–I Characteristic
    • SVC vs STATCOM
    • Harmonics in Plain English and IEEE 519
    • Frequency Response Stages
    • PPC Interaction and Multi-Plant Oscillation
    • STATCOM POD Tuning and Observability
    • System Strength Metrics
    • Power Swing and PRC-026
    • NERC Compliance Services Guide


    Disclaimer


    This article is provided by Keentel Engineering for general technical education. Worked examples, load profiles, screening coefficients, reduction factors, damping values, fault rates and cost figures are illustrative and simplified; they are not a substitute for project-specific studies with validated models and data. Requirements of NERC, FERC, IEEE, IEC and US transmission providers are summarized at a general level and change over time; consult the current documents and your interconnection agreement. Event magnitudes for 2026 are as reported in public sources and may be revised. Case studies are composites drawn from typical project situations, with names, locations and numbers changed. This article is not legal advice.



    A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

    About the Author:

    Sandip "Sonny" R. Patel, P.E.

    IEEE Senior Member · Founder & CEO, Keentel Engineering

    In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

    For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

    His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

    Four workers in safety vests and helmets stand with arms crossed near wind turbines.

    Let's Discuss Your Project

    Let's book a call to discuss your electrical engineering project that we can help you with.

    Man in a blazer and open shirt, looking at the camera, against a blurred background.

    About the Author:

    Sandip "Sonny" R. Patel, P.E.

    IEEE Senior Member · Founder & CEO, Keentel Engineering

    In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

    For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

    Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

    His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.

    Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

    Leave a Comment

    Related Posts

    Harmonic Resonance in Renewable Energy Power Systems
    By SANDIP R PATEL • November 29, 2026
    Learn how harmonic resonance affects solar, wind and BESS plants. Explore causes, impedance scans, mitigation strategies and IEEE 519 compliance.
    PSS®E vs PSCAD: RMS vs EMT Simulation Explained
    By SANDIP R PATEL • November 29, 2026
    Compare PSS®E vs PSCAD for RMS and EMT simulation. Learn when to use each tool for grid stability, inverter-based resources and interconnection studies.
    Plant controller interactions between solar and storage PPCs sharing a 230 kV grid connection
    By SANDIP R PATEL • November 29, 2026
    Learn how power plant controller interaction causes voltage oscillations in solar, wind and BESS plants, and how droop, delay and PPC tuning help.
    10 Essential BESS Commissioning Tests Before Energization
    By SANDIP R PATEL • November 28, 2026
    Discover 10 essential BESS commissioning tests covering insulation, grounding, PCS, BMS, protection and EMS to ensure safe, reliable grid energization.
    Solid-state transformers for BESS and AI data centers in 2026
    By SANDIP R PATEL • November 27, 2026
    Compare 9 solid-state transformers for BESS and AI data centers in 2026. Explore voltage classes, DC compatibility, efficiency, grounding and grid codes.
    Data Center Cooling Plants: Evaporative vs Hybrid vs Dry
    By SANDIP R PATEL • November 26, 2026
    Compare data center cooling plants by water use, energy efficiency, peak power demand, generator sizing, grid impact and lifecycle costs.
    Ground-Mount Solar Engineering: Complete Design Guide
    By SANDIP R PATEL • November 26, 2026
    Explore ground-mount solar engineering, from site selection and string sizing to collector design, grounding, battery storage and grid interconnection.
    Gas turbine backlog and equipment lead times for power generation projects in 2026.
    By SANDIP R PATEL • November 26, 2026
    Explore the 2026 gas turbine backlog, equipment lead times, GSU supply constraints, interconnection challenges, NERC testing and project delay costs.
    PLECS and Ansys simulation workflow for solid-state transformer engineering.
    By SANDIP R PATEL • November 26, 2026
    Explore how PLECS and Ansys support solid-state transformer simulation, thermal modeling, power loss analysis, control design, and engineering validation.