A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.
Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime
The three operating regions you have to design to
| Device | Output vs voltage | Response | Best suited to | Main limitations |
|---|---|---|---|---|
| Mechanically switched capacitor or reactor | Proportional to voltage squared | Seconds; discrete steps; limited switching operations per day | Steady-state reactive supply, voltage profile, loss reduction | No dynamic capability; step voltage change on switching; capability collapses when most needed |
| Static var compensator | Capacitive branches proportional to voltage squared | A few cycles; continuously controllable | Continuous control where cost matters and deep voltage support is not the driver | Square-law capability loss; harmonic filters are part of the plant and interact with the network |
| STATCOM | Approximately proportional to voltage — constant current capability | One to two cycles closed loop; converter response faster still | Voltage stability margin, weak interconnections, fast disturbance recovery, flicker and unbalance compensation | Higher capital cost; converter losses; adds a converter and its control dynamics to the network |
| Synchronous condenser | Governed by machine capability and excitation | Excitation response in the hundreds of milliseconds; inherent inertial response instantaneous | System strength and inertia, short-circuit contribution, black start support | Rotating plant with maintenance and losses; slower controlled response than a converter |
| STATCOM with energy storage | Reactive as a STATCOM, plus real power within the storage rating | As STATCOM for reactive; real power limited by storage | Where a real power deficiency is part of the problem | Cost and complexity of the storage; different failure and maintenance profile |
| Service area | What we do for SST campuses | Typical deliverables |
|---|---|---|
| Grid interconnection | Site screening, large-load applications, independent studies, utility and RTO coordination in ERCOT, NYISO, PJM and other markets | Screening reports, application data packages, load flow, contingency and stability studies, study review memos |
| EMT modeling | Model requirements, vendor model review, campus aggregation, ride-through, weak-grid, control interaction and load-oscillation studies | EMT model specifications, model acceptance reports, PSCAD study reports, SCR screening |
| MV/MVDC system studies | AC and DC short-circuit, DC protection philosophy, AC protection, arc flash, grounding, insulation coordination | Study reports, protection philosophy documents, settings files, arc flash labels, interface control documents |
| Power quality | Emission requirements, frequency scans, IEEE 519-2022 compliance, filter sizing, flicker assessment | Harmonic study reports, filter specifications, monitoring plans |
| Substation and transmission design | HV/EHV substations, MV collectors, transmission lines, utility interface protection | Physical and electrical drawing packages, specifications, bills of material, protection and control design |
| NERC compliance | Registration and applicability, ride-through requirements, model validation, monitoring, compliance programs | Applicability assessments, compliance programs, evidence packages, model validation reports |
| Owner's engineer and QA/QC | SST, storage and substation specifications, design reviews, FAT and SAT plans and witnessing, multi-unit QA | Specifications, review comments, test plans, witness reports, due diligence reports |
| Onsite generation and BESS | Role definition and sizing, DC bus control architecture, fire and code compliance coordination, performance testing | Sizing studies, control architecture documents, specifications, test procedures |
Storage and generation
| Term | Meaning |
|---|---|
| AFE | Active front end. The actively switched AC/DC stage of an SST that connects to the MV grid and sets its grid behavior. |
| Aggregated model | A model in which many converters are represented by a smaller number of equivalent converters to make campus-scale simulation practical. |
| Arc flash | The release of energy from an electric arc fault, assessed as incident energy at a working distance to set PPE and safe work practices. |
| BESS | Battery energy storage system. |
| Blocking | Turning off all converter switches so the converter stops feeding current, used to limit DC faults. |
| Composite load model | A positive-sequence load model that combines several load types, such as motors, electronics and static loads. |
| DAB | Dual active bridge. An isolated DC/DC converter topology with active bridges on both sides of a high-frequency transformer. |
| DC-link | The internal DC capacitor bank between converter stages. |
| EMT | Electromagnetic transient simulation. Time-domain simulation with microsecond time steps, used to study fast converter and network behavior. |
| FAT | Factory acceptance test. |
| Grid-forming | A converter control mode that sets its own voltage and frequency reference rather than following the grid's, providing support to weak grids. |
| HIL | Hardware-in-the-loop testing, in which a real controller is tested against a real-time simulation. |
| IBR | Inverter-based resource. Generation or storage connected to the grid through power electronics. |
| Insulation coordination | Matching the insulation strength of equipment to the voltage stresses the system produces, with surge protection where needed. |
| ISC/IL | The ratio of available short-circuit current to maximum demand load current at the point of common coupling, used to set IEEE 519 limits. |
| ISOP | Input-series, output-parallel. A modular converter arrangement that shares a high input voltage across cells in series and combines their outputs in parallel. |
| Large load | A load large enough to affect transmission system reliability. Definitions vary, for example 75 MW and above under Texas SB 6, or loads above 20 MW in the federal rulemaking proposal. |
| LVDC | Low-voltage DC, such as 800 VDC or ±400 VDC rack distribution. |
| MFT | Medium-frequency transformer. The compact isolation transformer inside an SST, operating at kilohertz frequencies. |
| MMC | Modular multilevel converter. A converter built from many submodules with their own capacitors, producing a stepped multilevel waveform. |
| MVDC | Medium-voltage DC distribution, roughly 1 kV to 35 kV DC in common usage. |
| OE | Owner's engineer. An independent engineer representing the owner's technical interests. |
| PCC / POI | Point of common coupling / point of interconnection, where the campus connects to the utility system and where compliance is usually assessed. |
| PLL | Phase-locked loop. The control element that tracks grid voltage phase and frequency. |
| Positive-sequence model | A fundamental-frequency, balanced dynamic model used in PSS®E, PSLF and similar tools. |
| Ride-through | The ability to stay connected and keep operating during and after a grid disturbance within defined limits. |
| SAT | Site acceptance test. |
| SCR | Short-circuit ratio. Available short-circuit power divided by converter rating, a measure of grid strength. |
| SiC | Silicon carbide, a wide-bandgap semiconductor material that allows higher voltage, higher frequency switching. |
| SST | Solid-state transformer. A power electronic converter with a high-frequency isolation stage that replaces a 60 Hz transformer and rectifier chain. |
| Supraharmonics | Emissions in the 2 kHz to 150 kHz range, above the range covered by most harmonic limits. |
| TDD | Total demand distortion. Harmonic current distortion relative to maximum demand current, used in IEEE 519. |
| WSCR | Weighted short-circuit ratio. An SCR screen that accounts for several inverter-based plants sharing a network area. |
Links were current at publication (November 2026). Large-load rules, NERC actions and standards editions are changing quickly, so confirm current versions before relying on them.
Large-load reliability and NERC
- NERC Publishes Incident Review and Guidance on Voltage-Sensitive Large Load Integration, NERC
- Reliability Insights: Large Computational Load Risks Due to Voltage Sensitivity, NERC, September 2026
- NERC Seeks to Address Reliability Impacts from Large Load Integration, NERC presentation to FERC, April 2025
- NERC issues Level 3 Alert to address immediate risks data center loads pose to the grid, Renewable Energy World, May 2026
- NERC Voltage-Sensitive Loads, Keentel Engineering
Federal and state large-load rules
- FERC Docket RM26-4, Interconnection of Large Loads, FERC
- FERC Establishes Proceeding to Consider DOE Directive on Large Load Transmission Interconnection Rulemaking, McGuireWoods, October 2025
- Texas Senate Bill 6 Ushers in Major Overhaul of Large Load Interconnection and Grid Access Rules, Bracewell, July 2025
- Public Utility Commission of Texas Issues Proposed Rules for Large Load Interconnections, Foley & Lardner, March 2026
Solid-state transformers and DC data center power
- Solid State Transformer project, Open Compute Project
- Novel Solid-State Transformer Supports 800-V DC Power in AI Data Centers, Electronic Design
- How SSTs are Reshaping Data Center Infrastructure, Microchip Technology
Standards referenced (consult the publisher for the current edition)
Step 5 — options. Replacing or retrofitting the drives with active-front-end or 18-pulse units at about 5% THDi gives a TDD of about 1.5%. An active harmonic filter sized for the 5th and 7th could achieve a similar result at the facility level. A passive 5th-harmonic tuned filter would also work but must be checked for resonance with the utility system and with any future capacitors.
What this means for you.
The same drives can be compliant on a strong system and non-compliant on a weak one. Ask your utility for the maximum short-circuit current at the PCC early in design. If the ratio is below 50, plan for low-harmonic drives or filtering from the start; it is much cheaper than retrofitting.
9. Inverter-based resources: solar, storage and wind
Solar PV, battery energy storage and full-converter wind turbines use pulse-width-modulated inverters with output filters. They are generally low-distortion sources. IEEE Std 1547-2018 (distribution-connected resources) and IEEE Std 2800-2022 (transmission-connected resources) limit their current distortion — total rated-current distortion (TRD) of 5% with individual limits by order, measured against rated current rather than present output. In practice, quality inverters measure 1–3% at rated output.
Three cautions apply:
- Percentages rise at low output. At 10% of rated output a 2% distortion (of rated current) looks like 20% THD. Limits referenced to rated current, like TDD, avoid this trap.
- Inverters change the system's impedance. Plant collector cables, inverter output filters and capacitor banks add capacitance. They can create resonances near the 5th to 13th harmonics on the 34.5 kV collector or at a 138 kV, 230 kV or 345 kV point of interconnection, amplifying background distortion that the plant did not create.
- Background distortion matters. Inverters can absorb or amplify existing voltage distortion depending on their control design. Utilities increasingly require harmonic impedance studies for new plants, sometimes using electromagnetic transient (EMT) simulation.
Keentel's articles on harmonic resonance and on
weak-grid inverter stability cover these interactions in depth.
10. Data centers and other electronic facilities
Data centers are a special case because almost all their load is electronic. Points to check:
- UPS rectifiers. Double-conversion UPS units with IGBT rectifiers typically draw less than 5% THDi at rated load, rising at low load. Older six-pulse or 12-pulse thyristor UPS rectifiers may need input filters.
- Server and network power supplies. Modern units with active power factor correction have low 3rd harmonic. Legacy equipment does not. Measure a representative panel rather than assuming.
- 208Y/120 V and 415Y/240 V distribution. Check neutral current and transformer K-factor as in Sections 4 and 7.
- Generator operation. Test UPS and generator compatibility at the actual load level. Generator THDv can be three to four times the utility THDv for the same load.
- Cooling plant. Chiller, pump, fan and cooling distribution unit drives often contribute more low-order harmonics than the IT load. Specify low-harmonic drives where the facility is large relative to the utility source.
- Large-load interconnection. Utilities and grid operators now treat large data centers as high-impact loads. Harmonic studies and power quality monitoring are increasingly part of interconnection requirements, alongside ride-through and dynamic studies.
11. How a harmonic study is done
A harmonic study answers four questions: How much harmonic current will the facility inject? What voltage distortion will it cause? Will any resonance amplify it? What is the cheapest reliable fix? Keentel's typical workflow:
- Gather data. Single-line diagram; utility short-circuit data (maximum and minimum) at the PCC; utility background distortion if known; transformer impedances; cable lengths; capacitor banks and filters; drive, UPS and inverter data sheets with harmonic spectra.
- Measure existing conditions. For existing facilities, install class-compliant power quality meters at the PCC and key buses for at least one week, capturing 10-minute and 3-second data up to the 50th harmonic.
- Build the model. Represent sources as harmonic current injections and the network as frequency-dependent impedances, including transformer phase shifts that can cancel 5th and 7th harmonics between delta-delta and delta-wye units.
- Run a frequency scan. Plot driving-point impedance versus frequency at each important bus to find resonances, for all credible system configurations (tie breakers open/closed, capacitor steps in/out, generator versus utility).
- Run harmonic load flow. Calculate harmonic currents and voltages and compare them with IEEE 519 at the PCC and with equipment limits (IEEE 18 for capacitors, C57.110 for transformers) inside the facility.
- Design mitigation. Compare options for performance, cost, losses, footprint and future flexibility.
- Verify. Measure again after installation and document compliance with the statistical criteria.
12. Fixing harmonics: options compared

PLECS and Ansys for Solid-State Transformer Engineering: An In-Depth Technical Guide
November 26, 2026 | Blog
Introduction: two tools, one engineering problem
A medium-voltage solid-state transformer (SST) program lives or dies on two questions asked over and over: does the converter do what it must electrically, and can it get the heat out? PLECS answers the first. Ansys answers the second. Used together, with losses flowing one way and temperatures flowing back, they form the core analysis toolchain for most serious SST and MV power-electronics programs today.
This guide is written for engineers and engineering managers who are setting up that toolchain for the first time, or who have inherited models and need to know whether to trust them. It explains what each tool is good at, where each one stops, how to build models of an SST at the right level of fidelity, how to couple electrical and thermal results, and how to buy the licenses. It ends with thirty frequently asked questions and answers.
Why SSTs push simulation harder than other converters
An MV SST for an AI data center or a grid application is unusual in four ways, and each one shapes the modeling approach.
- Scale and repetition. A single 10 MW unit can contain dozens of identical cells in series, each with several H-bridges, an isolation stage and a medium-frequency transformer. A campus can contain hundreds of units. Simulating every switch in every cell at full detail is neither possible nor useful, so models must be layered.
- Multiple time scales. Switching events happen in nanoseconds, the isolation stage runs at tens of kilohertz, the grid at 60 Hz, thermal time constants run from milliseconds in a SiC die to minutes in a cold plate, and AI training load cycles repeat over seconds. No single model covers all of these efficiently.
- Soft switching and new devices. Isolation stages such as dual and multi-active bridges rely on zero-voltage switching. Datasheet loss figures assume hard switching, so the loss model has to be built differently, and ideally verified by measurement.
- Insulation and heat in the same space. Medium-frequency transformers need thick insulation for tens of kilovolts, but insulation is also a thermal barrier and it raises leakage inductance. Electrical, magnetic, thermal and insulation design are tightly coupled.
What this guide covers
The sections that follow cover PLECS fundamentals for MV work, a step-by-step approach to modeling an SST in PLECS, loss and thermal modeling, control design and real-time testing, Ansys Icepak and Mechanical for thermal design, a step-by-step Icepak cell model, coupling the two tools, related Ansys products, engineering discipline and model management, and what to ask for when buying licenses.
The examples use generic, illustrative values. They do not describe any client design.
At a glance: the toolchain

SST simulation toolchain · PLECS, Ansys, RT Box, prototype
PLECS sends losses to Icepak and gets thermal networks back. Maxwell supplies transformer inductances and loss maps. PLECS code runs on the RT Box to drive prototypes, and measured temperatures close the loop.
PLECS fundamentals for medium-voltage converter work
PLECS, from Plexim, is a system-level simulator built specifically for power electronics. Its central idea is the ideal switch: semiconductors are modeled as instantaneous on/off elements, and the circuit is solved as a piecewise-linear state-space system that changes topology at each switching event. That makes it fast and numerically robust for circuits with hundreds of switches, which is exactly what an SST cell string looks like.
Standalone or Blockset
PLECS comes in two editions.
| Edition | What it is | When to choose it |
|---|---|---|
| PLECS Standalone | A complete simulation environment with its own schematic editor, solvers, control library and scripting | Most SST work; no MATLAB license needed; required for the RT Box workflow in its simplest form |
| PLECS Blockset | A circuit engine that runs inside MATLAB/Simulink | Teams whose control design, test benches or code generation already live in Simulink |
The circuit models are largely interchangeable between the two, so a team can start in Standalone and move to Blockset, or the reverse, without rebuilding the power stage.
What the ideal-switch approach gives you, and what it does not
Because switches are ideal, PLECS captures everything that depends on the circuit topology and the switching pattern: currents and voltages in every branch, ripple, harmonics, resonance, control dynamics, soft-switching conditions, power flow and the energy exchanged at each switching instant. It runs in seconds or minutes where a SPICE model would run for hours.
It does not resolve the switching transition itself. The dv/dt and di/dt of a SiC MOSFET turning off, the ringing of the commutation loop, gate-driver behavior and device physics are outside its scope. Losses are therefore computed from lookup tables of switching energy and conduction voltage, not from a device model. When a question depends on the nanosecond-scale transition, such as overshoot, EMI or insulation stress from fast edges, it belongs in a SPICE-type or field-solver tool with extracted parasitics.
The libraries that matter for SST work
- Electrical. Ideal and non-ideal switches, diodes, MOSFETs and IGBTs with loss descriptions, passive components, transformers, sources and meters.
- Magnetic. A permeance-based domain in which cores, air gaps and windings are modeled as a magnetic circuit. This lets you represent leakage paths and multi-winding transformers explicitly, rather than as a fixed equivalent circuit.
- Thermal. Heat sinks, thermal resistances and capacitances, Foster and Cauer networks, and the coupling that turns electrical losses into heat flows.
- Control. Continuous and discrete blocks, PWM modulators, PLLs, filters, transformations, plus C-Script blocks for custom code and a state-machine block for supervisory logic.
Solvers and simulation speed
PLECS offers variable-step solvers for offline studies and a fixed-step discrete solver for code generation and real-time use. For offline SST studies, variable-step is normally the right choice: the solver steps exactly to each switching instant, so accuracy does not depend on a small fixed step. Speed is driven mainly by the number of switching events per simulated second, which is why a full-switching model of a 45-cell unit runs much slower than a cell model, and why averaged models matter at unit and system level.
Analysis tools
PLECS includes steady-state analysis, which finds the periodic operating point directly instead of simulating until transients die out, and frequency-domain tools: AC sweep, impulse response analysis and loop-gain analysis. For an SST these answer practical questions quickly, including the converter input and output impedance used in stability checks, control loop margins, and the frequency response of the isolation stage.
Scripting and automation
Simulation scripts and an external RPC interface allow parameter sweeps, Monte Carlo runs and batch scenario catalogs to be driven from a script, including from Python. For an SST program this is not optional: a scenario catalog of start-up, load steps, faults, cell bypass and thermal derating, multiplied by design options and parameter bands, quickly reaches hundreds of runs.
How to model an SST in PLECS, step by step
The single most important decision is fidelity. Build the model in layers, each checked against the layer below, so that every question is answered by the simplest model that can answer it correctly.
| Level | What is in it | Typical questions it answers | Relative speed |
|---|---|---|---|
| Cell, full switching | Every switch, the isolation stage, the medium-frequency transformer with leakage and magnetizing branches, loss tables, thermal network | Losses, soft-switching range, inductance budget, ripple, junction temperature, control margins | Slowest |
| String, hybrid | Switched front-end bridges, averaged isolation stages, series DC stack, bypass logic | Voltage balancing, ripple distribution, bypass transients, fault blocking | Medium |
| Unit, averaged | Cells as controlled sources with averaged losses, unit controls, filters | Start-up, load steps, ride-through, current sharing | Fast |
| System, averaged | Several units, DC bus, cables, sources and loads, protection logic | Bus stability, sharing between units, faults, black start, generator interaction | Fastest |
Step 1: Start with a low-fidelity sanity model
Before building anything detailed, build a model in a day or two with averaged cells and ideal transformers. Use it to confirm your understanding of the architecture: power flow direction, voltage levels at every interface, cell count, modulation index and the operating envelope. Errors in understanding caught here cost hours; caught later they cost weeks.
Step 2: Put every parameter in one place
Define all parameters in a single initialization script or parameter file: voltages, cell counts, capacitances, inductances, switching frequency, device part numbers, loss tables, thermal data and control gains. Give the file a revision number tied to the design baseline it represents. Every result should record which parameter revision produced it. When the hardware team changes a value, you change one line and re-run.
Step 3: Build the cell at full detail
A typical SST cell has an AC-side or high-voltage-side bridge, a DC link, an isolation stage and a low-voltage or DC-end bridge.
- Front-end bridge. Model the H-bridge or bridges with switch models that carry loss tables. Use the actual modulation: phase-shifted carriers in a cascaded H-bridge, with each cell's carrier offset so that the string's effective switching frequency is multiplied.
- Isolation stage. For a dual active bridge (DAB), model both bridges, the series inductance and the transformer. For multi-port stages such as a triple active bridge (TAB), model each winding with its own leakage and place the magnetizing branch where the hardware actually has it. Power exchanged between each pair of ports depends on the equivalent inductance between them, which is not the same as any single branch leakage.
- Transformer. Use either an equivalent circuit (leakage per winding, magnetizing inductance, turns ratio) or the magnetic domain for a more physical representation. Include winding capacitance once it is known, because it affects soft switching at light load and the high-frequency behavior of the isolation stage.
- DC links and filters. Include capacitor ESR if you need ripple heating, and the actual capacitance values, including tolerance bands.
Step 4: Check the cell against hand calculations
Before trusting a cell model, check it against first principles. For a DAB with single phase-shift control, the transferred power is:
P = \frac{n V_1 V_2 \, \varphi (\pi - |\varphi|)}{2 \pi^2 f_s L}
where n is the turns ratio, V1 and V2 the bridge DC voltages, φ the phase shift in radians, fs the switching frequency and L the series inductance referred to one side. If the simulated power at a given phase shift does not match this within a few percent, something in the model is wrong.
Also check soft switching. For zero-voltage turn-on, the current in each bridge must have the right sign and enough magnitude at the switching instant to charge and discharge the device output capacitances within the dead time. PLECS shows the switch current at each transition directly; plotting it across the load range gives the soft-switching boundary.
Step 5: Build the string
Connect cells in series on the high-voltage side and in series or parallel on the other, as the architecture requires. At string level the questions change to balancing and ripple:
- Each cell's DC-link voltage must stay within its share, through transients and with one cell bypassed.
- In single-phase cells, power pulses at twice line frequency. That ripple has to go somewhere: into link capacitors, into DC-end voltage swing, or cancelled across phases at a series output. The string model is where you see which.
- Cell bypass and its transient, including the switch from N to N−1 active cells.
To keep the string fast, replace the isolation stage in each cell with an averaged model that conserves power and reproduces the DC-link dynamics, after checking that it matches the full-switching cell.
Step 6: Build the unit and the system
At unit and system level, cells become controlled voltage or current sources with averaged losses. Add the unit controls, input filters, protection logic, DC-bus capacitance and cables. This is the level for the scenario catalog: start-up, load steps, generator voltage sags, loss of a cell, loss of a unit, AC- and DC-side faults and black start. Variable-step solvers make these runs quick, often faster than real time.
Step 7: Automate the scenario catalog
Define each scenario as a script entry with its parameters, stimulus and pass criteria. Run the full catalog after every significant model change and archive the results with the model and parameter revisions. This turns the model from a one-off study into a regression-tested engineering asset.
Common modeling mistakes
- Using datasheet hard-switching losses for a soft-switched isolation stage.
- Representing a multi-winding transformer as separate two-winding transformers.
- Forgetting dead time, which changes both soft switching and output voltage at light load.
- Running a fixed-step solver offline with a step too large to resolve switching.
- Averaged models that were never checked against the switching model they replace.
- Parameters scattered across subsystems, so nobody knows which values produced a given result.
Loss and thermal modeling in PLECS
Efficiency, junction temperature and lifetime all come from the loss model, so it deserves as much care as the circuit. PLECS computes semiconductor losses from lookup tables attached to each switch, and passes the resulting heat into a thermal network that can feed temperature back into the loss tables.
How PLECS computes semiconductor losses
- Conduction losses come from an on-state characteristic: voltage drop as a function of current and junction temperature. For a SiC MOSFET this is close to a resistance that rises with temperature; for an IGBT or diode it is a knee voltage plus a slope.
- Switching losses come from energy tables: turn-on and turn-off energy as functions of blocking voltage, current at the instant of switching and junction temperature. At each switching event PLECS reads the voltage and current from the circuit, looks up the energy and injects it as heat.
- Reverse conduction matters for SiC MOSFETs, which conduct in the third quadrant through the channel when gated on and through the body diode during dead time. Both paths need loss data.
Many device manufacturers publish PLECS-format thermal descriptions for their modules. They are a good starting point, but check the conditions they were measured under: gate resistance, gate voltage, stray inductance and temperature.
The soft-switching problem
Datasheet switching energies are measured in a double-pulse test under hard switching. In a soft-switched isolation stage, they are badly wrong.
- Turn-on under zero-voltage switching is nearly lossless, because the output capacitance has already been discharged by the load current during the dead time. Using the datasheet turn-on energy overstates losses substantially.
- Turn-off still has losses, but at a lower level and with a different dependence on current, because the device turns off into its own output capacitance. The datasheet turn-off energy also includes energy that is stored in the output capacitance and later recovered.
- Incomplete soft switching at light load, when there is not enough current to complete the transition in the dead time, puts some of the hard-switching loss back.
A practical approach is to build separate tables for the isolation stage:
- Set the turn-on energy to zero where the switch current at turn-on has the sign that indicates zero-voltage switching, and to the hard-switching value otherwise.
- Replace the turn-off energy with soft-switching turn-off data, ideally measured on the actual module and gate driver by calorimetric or carefully de-embedded double-pulse methods.
- Mark the results with an error band until measured data is available, and tighten it once board-level tests come in.
Magnetics and passive losses
Transformer and inductor losses are often a large share of the total in a medium-frequency isolation stage. PLECS can estimate core loss using Steinmetz-type models with the actual non-sinusoidal flux waveform, and winding loss from RMS current with a frequency-dependent resistance. For a design-grade answer, especially with litz wire and thick insulation, take core and winding loss from finite-element tools such as Ansys Maxwell or from vendor measurements, and feed them in as tables. Capacitor losses follow from ripple current and ESR.
Thermal networks: Foster versus Cauer
PLECS models heat flow with thermal impedance networks.
| Network | What it is | Use it for | Limitation |
|---|---|---|---|
| Foster | A curve fit to a measured transient thermal impedance, as R-C pairs in series | Junction-to-case behavior straight from a datasheet Zth curve | The internal nodes have no physical meaning, so a Foster network cannot be correctly cascaded with a heat sink model |
| Cauer | A ladder of R and C to ground that follows the physical layers | Cascading junction, case, thermal interface, cold plate and coolant | Needs a conversion from Foster or extraction from a 3D thermal model |
For an SST cell, the usual pattern is a Foster or Cauer junction-to-case model from the module data, connected to a heat sink or cold plate model whose behavior comes from Ansys. Section 9 describes that coupling.
Temperature feedback
SiC on-resistance rises with temperature, which raises losses, which raises temperature. PLECS closes that loop automatically when loss tables include temperature dependence. Run steady-state analysis at each operating point to get the converged junction temperature without simulating the full thermal settling time.
Mission profiles and lifetime
AI training loads are cyclic. Each load cycle produces a junction temperature swing, and repeated swings wear out die attach and bond wires. The workflow is:
- Run a representative load profile through the averaged unit model with thermal networks to get junction temperature versus time.
- Count the temperature cycles with a rainflow algorithm, recording swing amplitude, mean temperature and duration.
- Apply a power-cycling lifetime model from the module manufacturer or the literature to estimate consumed life.
- Feed the result into the FMEA as a wear-out failure mode with its supporting evidence.
Control design, real-time simulation and HIL with PLECS
An SST is as much a control problem as a power-stage problem. PLECS lets the same model carry the control from first concept to a running prototype, which removes most of the translation errors that creep in when control is redesigned in a different tool for each stage.
Designing the control in the model
A typical SST control architecture has three layers, and each maps to PLECS features.
| Layer | Typical functions | How it is modeled |
|---|---|---|
| Cell | DC-link voltage regulation, isolation-stage phase-shift control, soft-switching modes, local balancing, bypass and blocking | Discrete control blocks and C-Script running at the cell controller rate |
| String and unit | Grid current control with a phase-locked loop, power or voltage control, droop, ripple handling, balancing across cells | Discrete blocks at the unit controller rate, with realistic sampling and delays |
| Supervisory | Start-up, precharge, normal operation, fault response, bypass sequencing, shutdown | State-machine block, with each state and transition explicit |
Model the control as discrete-time from the start, with the real sampling rates, computation delays and PWM update timing. A continuous-time controller that looks stable in simulation can go unstable once a one-sample delay is added.
The state machine deserves particular attention. Start-up sequences, such as precharging DC links before closing an input breaker, and ordered shutdown are where prototypes are most often damaged. A state flowchart that runs in the model, with every transition tested in the scenario catalog, is far cheaper than discovering a missing interlock at the bench.
Checking loops in the frequency domain
Use PLECS loop-gain and AC sweep analysis to measure phase and gain margins on the switching model, not just the averaged one. For DC-bus systems, sweep the output impedance of sources and the input impedance of loads. A constant-power load presents a negative incremental input impedance at low frequency, and stability requires the source impedance to stay well below the load impedance across frequency. Active damping in the load converters' control can reshape their input impedance, and the sweep shows whether it does.
From model to real time: RCP and HIL
Plexim's RT Box hardware runs PLECS models in real time, with code generated by the PLECS Coder. It supports two uses that matter on an SST program.
- Rapid control prototyping (RCP). The control model runs on the RT Box, which drives the real power hardware through its digital and analog I/O. Engineers can energize a prototype cell or string before production firmware exists. Protection functions should stay in the gate-driver hardware, not in the prototyping controller.
- Hardware-in-the-loop (HIL). The power stage model runs on the RT Box in real time, and the real controller is connected to it as if it were the hardware. This tests the controller against faults, weak sources and abnormal conditions that are unsafe or impossible to create in a lab.
Because the same PLECS model is used offline, for RCP and for HIL, there is no model translation step between design, prototype and test.
Real-time constraints for SST models
Real-time simulation runs with a fixed time step of a few microseconds or less. That is a hard limit on model size: a full-switching model of a long cell string will not fit on one unit. Practical approaches:
- Run one or two cells at full switching detail and the rest of the string as averaged cells.
- Split the model across several linked real-time units.
- Use switching-function or averaged models for the isolation stage when the controller under test runs at the unit level.
Design the real-time model alongside the offline model, not afterward, so the partitioning matches the controller architecture.
Alternatives
If a team already owns dSPACE, Speedgoat or OPAL-RT hardware, the control can be built in Simulink and deployed there, with PLECS Blockset providing the power stage. The trade-off is a more complex toolchain in exchange for reusing existing equipment.
Ansys for power electronics thermal design: Icepak or Mechanical
PLECS tells you how much heat each device and component produces. Ansys tells you where that heat goes, how hot everything gets, and whether the cooling design can remove it. Ansys, now part of Synopsys, offers several thermal tools. For SST work the choice is usually between Icepak and Mechanical, sometimes with Fluent alongside.
The three options
| Tool | Method | Strengths for SST work | Limits |
|---|---|---|---|
| Ansys Icepak | Computational fluid dynamics (CFD) tailored to electronics cooling: conduction, convection and radiation in one model | Cold plates and liquid flow, air-cooled enclosures, fans and heat sinks, power module and PCB import, compact package models, reduced-order thermal models | Less suited to detailed mechanical stress |
| Ansys Mechanical | Finite element analysis (FEA) of heat conduction, steady-state and transient, with convection applied as boundary conditions | Detailed temperature fields in solids, insulation and transformer structures; thermal stress and fatigue in the same environment | Convection must be supplied as heat-transfer coefficients, from correlations or a CFD run |
| Ansys Fluent | General-purpose CFD | Complex coolant manifolds, two-phase cooling, detailed flow distribution | More setup effort; usually not needed for a cell-level study |
Which one to buy first
For most SST programs, Icepak is the better first license.
- SST cells are typically liquid-cooled, with power modules on cold plates. Icepak solves the coolant flow and the solid conduction together, so the heat-transfer coefficient on each wetted surface comes out of the model instead of being guessed.
- Icepak handles the electronics details efficiently: module baseplates, thermal interface materials, PCB copper, compact package models and power maps.
- It can generate reduced-order thermal models that go straight back into PLECS.
Choose Mechanical first if the main questions are temperature distribution inside solid structures, such as a cast-resin medium-frequency transformer, and thermal stress, and if convection can be represented reliably by heat-transfer coefficients. Many teams end up with both: Icepak for the cell and cold plate, Mechanical for the transformer insulation and for power-cycling stress.
Questions each tool answers on an SST cell
- What is the junction temperature of every die at rated load and at the worst ambient and coolant temperature?
- How evenly is coolant shared between cold plates, and what is the pressure drop?
- What is the hot-spot temperature in the transformer windings and insulation, and how steep is the gradient across the insulation? Insulation under DC stress is sensitive to temperature gradients, because conductivity depends on temperature.
- How much margin is there between the hottest component and its rating, and how does it change with altitude, fouling or a failed pump?
- What thermal impedance does each device see from junction to coolant, for use back in PLECS?
- What thermal cycling does each solder layer see, and how many cycles will it survive?
How to model a converter cell in Ansys Icepak, step by step
The steps below describe a cell-level thermal model for a liquid-cooled SST cell with power modules on cold plates and a medium-frequency transformer. The same pattern applies to stage 2 cells and source converters.
Step 1: Define the questions and the inputs before opening the tool
Write down what the model must answer, such as peak junction temperature at rated load and worst coolant temperature, and list the inputs you need. Issue that list to the mechanical and cooling team on day one. Typical inputs:
- Cooling concept: coolant type, inlet temperature range, flow rate per cell, allowed pressure drop
- Ambient air temperature range, altitude and enclosure ventilation
- Mechanical layout: module positions, cold plate geometry and channel design, busbars, capacitors, transformer location
- Material data: thermal conductivity of baseplates, thermal interface materials, insulation, potting and resin
- Losses per component at each operating point, from PLECS
Where inputs are not yet fixed, agree first values with stated uncertainty and run the model at the band limits.
Step 2: Prepare and simplify the geometry
Import the mechanical model (typically through SpaceClaim or a neutral CAD format) and simplify it before meshing. Remove fasteners, small fillets, labels and features that do not affect heat flow. Keep everything that does: the thermal interface layers, the cold plate channels, the module baseplate and the main conduction paths. Simplification is where most Icepak time is saved or lost.
Step 3: Represent the power modules
There are three levels of detail for a module:
| Representation | Content | When to use |
|---|---|---|
| Block with a power | A solid block with total module loss | Early layout studies only |
| Compact model | Two-resistor or multi-node network from the manufacturer | System and enclosure studies |
| Detailed | Individual dies, solder, DBC substrate, baseplate, with a loss per die | Junction temperature per die, hot-spot location, Zth extraction |
For SiC modules with several dies per switch, the detailed representation is worth it. Die-to-die temperature differences can be significant, and the hottest die sets the derating.
Step 4: Model the cold plate and coolant
Draw the coolant channels explicitly and define the inlet flow and temperature and the outlet pressure. Icepak solves the flow and the convective heat transfer together. If the cell has two cold plates at different electrical potentials, model both, and include the insulating flow path between them, since its thermal resistance matters too.
Step 5: Model the transformer and passives
Represent the transformer core, windings and insulation as separate bodies with their own losses. The insulation is both a thermal barrier and the component most sensitive to temperature, so resolve it with enough mesh across its thickness to capture the gradient. Add DC-link capacitors with their ripple losses, and busbars with their resistive losses.
Step 6: Apply the losses
Apply losses from PLECS per component and per operating point: rated load, overload, light load and the worst thermal case. For a transient study, apply time-varying loss profiles from the mission profile. For transformers, use spatial loss distributions from Ansys Maxwell when the losses are concentrated in specific regions.
Step 7: Mesh and check convergence
Use a fine mesh in the dies, thermal interfaces, channel walls and insulation, and a coarser mesh elsewhere. Check that the solution has converged: residuals reduced, energy balance closed (heat in equals heat out within a small percentage), and monitored temperatures stable. Then refine the mesh once and confirm that the key temperatures change by only a small amount. A thermal result without a mesh-independence check should not go into a design review.
Step 8: Validate and report
Compare the result with a hand calculation of the main thermal path, and later with measured temperatures from prototype tests. Report junction temperatures per die, hot-spot temperatures in the transformer, coolant temperature rise and pressure drop, and the margin to each limit. State the assumptions and the input uncertainty alongside the numbers.
Step 9: Extract thermal models for PLECS
Run step-change transient cases, with a step of power in one source at a time, and record the temperature response at each junction. Fit those responses with Foster or Cauer networks, including the coupling between neighboring devices if it is significant. Alternatively, use Ansys reduced-order model tools to export a compact model. These become the thermal networks in PLECS.
Closing the loop: coupling PLECS losses and Ansys thermal results
Neither tool alone gives a trustworthy junction temperature. PLECS needs thermal impedances to know how hot the devices get, and Ansys needs losses to know how much heat to remove. The coupling is iterative, and it should be planned, not improvised.
The workflow
- First losses. Run the PLECS cell model at each operating point with an assumed junction temperature, typically near the design limit, and export losses per die and per component.
- First thermal run. Apply those losses in Icepak and solve for temperatures.
- Extract thermal impedance. From transient step runs, extract Foster or Cauer networks from each junction to the coolant, including mutual heating between neighboring devices.
- Coupled electrical-thermal model. Put the extracted networks into PLECS. Temperature-dependent loss tables now converge to a consistent junction temperature at each operating point.
- Second thermal run. Apply the converged losses in Icepak to confirm the temperature field, the transformer hot spot and the coolant temperature rise.
- Iterate on design changes. When the cooling, layout or devices change, update the networks and repeat. Keep the networks versioned with the Icepak model that produced them.
One iteration is usually enough at early design stages. Two are normal before a design review. Converge when temperatures change by less than about a degree between passes.
What crosses the interface
| From PLECS to Ansys | From Ansys to PLECS |
|---|---|
| Losses per die and per switch, per operating point | Thermal networks from each junction to coolant |
| Transformer core and winding losses, or their split by region | Coupling terms between neighboring devices |
| Capacitor and busbar losses | Coolant and heat-sink temperature rise with flow |
| Time-varying loss profiles for mission-profile runs | Hot-spot temperatures for derating rules |
Keep the interface honest
- Agree units, sign conventions and naming for every device before the first exchange. A loss assigned to the wrong die is a common and expensive error.
- Check the energy balance: total losses exported from PLECS must equal total heat in the Icepak model.
- Record which PLECS model revision and which Icepak model revision were used for every coupled result.
- When measured temperatures become available, correct whichever model disagrees, and document the change.
Related Ansys tools: Maxwell, Q3D Extractor and Twin Builder
PLECS and Icepak cover most of the system and thermal work. Three other Ansys products fill specific gaps on an SST program. They are not needed on day one, but it helps to know where they fit before buying.
| Tool | What it does | SST use | When to add it |
|---|---|---|---|
| Ansys Maxwell | Low-frequency electromagnetic finite-element analysis | Medium-frequency transformer design: leakage and magnetizing inductance, core and winding loss distribution, electric field in the insulation | When the transformer is being designed or verified in-house, rather than by a vendor |
| Ansys Q3D Extractor | Parasitic extraction of resistance, inductance and capacitance from 3D geometry | Commutation loop inductance of busbars and module connections; winding-to-winding capacitance | When overshoot, ringing or soft-switching depend on layout parasitics |
| Ansys Twin Builder | System simulation and reduced-order model creation | Turning detailed thermal or electromagnetic models into compact models for system simulation | When many coupled runs or digital-twin use make full models too slow |
Why the transformer usually needs Maxwell
The medium-frequency transformer is where electrical, magnetic, thermal and insulation design meet. Thick insulation for tens of kilovolts pushes the windings apart, which raises leakage inductance, which sets how much power the isolation stage can transfer at a given phase shift. Maxwell answers three questions that a circuit simulator cannot: what leakage the physical design actually produces, where the losses are concentrated, and how the electric field is distributed in the insulation. The loss distribution goes into Icepak; the leakage values go into PLECS.
Insulation and partial discharge
MV insulation under DC stress with fast switching edges is a known risk area. Electric-field simulation identifies high-stress regions at conductor edges and interfaces, and coupled thermal results show where temperature gradients redistribute DC field through temperature-dependent conductivity. Simulation guides the design, but partial-discharge freedom has to be demonstrated by test on prototypes and coupons. Treat field plots as a reason to test, not a substitute for it.
Engineering discipline: validation, model management and review
A model is only as useful as the confidence people can place in it. On a fast-moving SST program, where the hardware design changes weekly and gate reviews depend on simulation evidence, model management is as important as model building.
Validate in stages
| Stage | Validate against | Typical tolerance target |
|---|---|---|
| Model build | Hand calculations: power transfer, ripple, thermal resistance chain | A few percent |
| Averaged model | The full-switching model it replaces, over the scenario catalog | Close agreement on averages and dynamics |
| Loss model | Board-level measurements of switching and conduction loss | Within the measurement uncertainty |
| Thermal model | Thermocouple or thermal-camera measurements on prototypes | A few degrees at key points |
| Full model | Prototype cell and string tests: efficiency, ripple, transients, temperatures | Agreed with the program before testing starts |
Agree the correlation tolerances before testing, not after. Otherwise the temptation is to declare agreement with whatever the test showed.
Manage models like software
- Keep models, parameter files and scripts under version control, with a change log.
- Tie every parameter file to a design baseline revision, and every result to the model and parameter revisions that produced it.
- Freeze a model revision for each gate review, and archive the results package with it.
- Use the same naming for devices, nodes and signals in PLECS and Ansys.
- Deliver models as runnable source files with a short user note: what the model represents, its assumptions and limits, how to run the scenarios and what the outputs mean.
Report uncertainty honestly
Early results rest on preliminary data: datasheet losses, estimated transformer parameters, assumed thermal boundary conditions. Report them as bands, state which inputs drive the band, and show how the band narrows as measured data arrives. A gate review that sees bands understands the risk. One that sees single numbers assumes certainty that is not there.
Review checklist before any result goes into a gate package
- Parameters match the current design baseline revision.
- Hand-calculation checks are recorded and pass.
- Averaged models have been checked against switching models for this case.
- Loss tables match the switching mode: soft-switched where soft switching is achieved.
- Thermal mesh independence and energy balance have been checked.
- PLECS and Icepak losses balance.
- Assumptions, exclusions and uncertainty bands are stated.
- A second engineer has reviewed the setup and the conclusion.
Buying the licenses: what to ask for in the quotes
Neither vendor publishes list prices for commercial licenses, so every purchase starts with a quote. Asking for the right configuration avoids paying for modules you will not use, or discovering mid-project that a needed feature is missing.
| Software | Vendor | What it is for on an SST program | What to ask for in the quote |
|---|---|---|---|
| PLECS | Plexim (plexim.com) | Converter simulation of cells, strings, units and systems; loss and thermal coupling; control models; code generation for real-time hardware | PLECS Standalone (or Blockset if the team works in Simulink), one or two seats, term matching the program phase. Confirm the thermal library, the magnetic library, the analysis tools and RT Box / PLECS Coder support are included, and whether a node-locked or floating license suits your team. |
| Ansys | Ansys, part of Synopsys (ansys.com) | Thermal analysis of cells, strings, cold plates and transformers | Ansys Icepak for electronics cooling with liquid cold plates, or Ansys Mechanical for steady-state and transient conduction and thermal stress. One seat, lease term matching the program. Confirm the solver core limit (HPC licensing), CAD import and reduced-order model export. |
| PLECS RT Box (optional) | Plexim | Rapid control prototyping and hardware-in-the-loop testing | Number of units needed for the cell or string model, I/O count and type, and lead time. Usually bought by whoever owns the lab. |
Questions to put to each vendor
- Term and start date. Can the license start on a specific date and run for the exact program duration? Is a short-term lease available?
- Seat type. Node-locked to one computer or floating across a team? Floating costs more but suits shared work.
- Commercial use. Is the quote for a commercial license? Academic and startup programs carry restrictions.
- Included modules. For PLECS, the thermal and magnetic libraries, analysis tools and code generation. For Ansys, the solver, meshing, CAD import and any HPC cores for parallel solving.
- Support and training. Is technical support included? Is there onboarding or a starter model?
- Transfer. Can the license be transferred to another user or company? This matters if a client is paying for the seat.
- Lead time. How quickly can a license key be issued after purchase order? Allow a few days for installation and checks.
Budgeting notes
- Ansys thermal seats generally cost significantly more than PLECS seats. Get both quotes before committing to a project budget.
- HPC (parallel processing) licenses can make a large difference to Icepak run time on detailed models. Decide whether you need them based on model size.
- If a client is reimbursing license costs, agree in writing whether the license is reimbursed at cost, who owns it afterwards, and whether the vendor allows it to be assigned.
How Keentel Engineering can help
Keentel Engineering supports SST, MVDC and data center power programs from the system side, with the modeling discipline this guide describes. We work as added engineering capacity under the client's direction, through our engineering team and qualified partners.
| Service | What we deliver |
|---|---|
| Requirements and modeling plans | KPI tables, requirements decomposition, model fidelity plans and scenario catalogs tied to the client's design baseline |
| Converter and system simulation | Cell, string, unit and system models, averaged and switching, with parameter management and automated scenario runs |
| Loss and thermal coupling | Loss models, including soft-switching corrections, coupled with thermal analysis and extracted thermal networks |
| Control scheme development | Control architecture, state machines and control models for rapid prototyping and HIL test rigs |
| MVDC bus and protection | DC bus specification, fault blocking, feeder reactor sizing, stability with constant-power loads |
| FMEA and test planning | DFMEA and PFMEA, test plans, HIL rig specifications and MV safety cases |
| Model review and validation | Independent review of existing models, correlation plans and gate-review evidence |
| Grid-side engineering | Interconnection, EMT studies, power quality, substations and NERC compliance, from 4 kV to 765 kV |
Keentel Engineering · Florida engineering firm registration No. 36853 · Texas engineering firm registration No. F-29821 · (813) 389-7871 · contact@keentelengineering.com · keentelengineering.com
Frequently asked questions
PLECS
1. What is PLECS, in one sentence?
A system-level power electronics simulator from Plexim that models switches as ideal elements, so circuits with hundreds of switches run fast enough for system studies, loss and thermal analysis and control design.
2. PLECS Standalone or PLECS Blockset?
Standalone is a complete environment and needs no MATLAB. Blockset runs inside Simulink. Choose Standalone unless your control design or test infrastructure already lives in Simulink; the circuit models move between them with little rework.
3. Why not use SPICE for SST work?
SPICE models device physics and switching transitions, which is too slow for a string of dozens of cells over many line cycles. Use PLECS for system behavior, losses and control, and SPICE or a field solver for nanosecond-scale questions such as overshoot, ringing and gate-drive behavior.
4. Can PLECS show dv/dt and switching ringing?
No. Switches are ideal, so the transition itself is not resolved. Switching losses come from energy tables. Questions about edge rates, EMI and insulation stress from fast edges belong in a parasitic-aware transient tool.
5. How accurate are PLECS losses?
As accurate as the loss tables. With measured data for the actual module, gate driver and switching mode, conduction and switching losses can be close to measurement. With datasheet hard-switching data applied to a soft-switched stage, they can be significantly overstated.
6. How do I model soft-switching losses?
Set turn-on energy to zero where the current at turn-on indicates zero-voltage switching, use measured soft-switching turn-off data, and fall back to hard-switching values where soft switching is lost at light load. Report results with an error band until board-level measurements confirm them.
7. How do I model a multi-winding transformer?
Use a single transformer model with a leakage inductance per winding and the magnetizing branch where the physical design puts it, or build it in the magnetic domain. Do not represent it as separate two-winding transformers; power flow between ports depends on the coupling through the shared core.
8. How big a model can PLECS handle?
There is no fixed limit, but speed falls with the number of switching events per second. A full-switching cell runs quickly; a full-switching string of dozens of cells is slow. Use averaged cells above cell level, after checking them against the switching model.
9. Which solver should I use?
Variable-step for offline studies, because it steps exactly to switching instants. Fixed-step discrete for code generation and real-time hardware.
10. How do I check stability of a DC bus with constant-power loads?
Use AC sweep or impedance analysis to get the source output impedance and the load input impedance, and check that the source impedance stays well below the load impedance across frequency. Confirm with time-domain load steps.
11. Can PLECS generate code for a controller?
Yes. The PLECS Coder generates C code from the model, for Plexim's RT Box and for supported embedded targets. Treat generated prototyping code as a development tool, not as certified production firmware.
12. What is the RT Box used for?
Two things: rapid control prototyping, where it runs the controller and drives real power hardware, and hardware-in-the-loop, where it simulates the power stage in real time and a real controller is tested against it.
13. Can a whole SST string run in real time?
Usually not at full switching detail on one unit. Run one or two cells in detail and the rest averaged, or split the model across several linked real-time units.
14. Do device manufacturers provide PLECS models?
Many publish PLECS thermal descriptions for their modules. Check the test conditions, especially gate resistance, gate voltage, stray inductance and temperature, against your design.
Ansys
15. Icepak or Mechanical: which first?
Icepak for liquid-cooled cells with power modules on cold plates, because it solves coolant flow and conduction together. Mechanical first if the main questions are temperature and stress inside solid structures and convection can be represented by heat-transfer coefficients.
16. Do I need Fluent?
Rarely for cell-level work. Fluent is for complex manifolds, two-phase cooling or detailed flow distribution across many cold plates.
17. How detailed should power modules be in Icepak?
Use a simple block only for early layout. Use compact network models for enclosure studies. Model individual dies, solder layers and substrate when you need junction temperatures per die or thermal impedances for PLECS.
18. How do I know an Icepak result is right?
Check convergence, energy balance and mesh independence, compare against a hand calculation of the main thermal path, and correlate with measured temperatures once prototypes exist.
19. Where do the losses for Icepak come from?
From PLECS for semiconductors, capacitors and busbars, and from Ansys Maxwell or vendor data for transformer core and winding losses. Check that the total heat in Icepak equals the total losses exported.
20. How do I get thermal models back into PLECS?
Run transient step-power cases in Icepak, record each junction's response, and fit Foster or Cauer networks, including coupling between neighboring devices. Ansys reduced-order model tools can also export compact models.
21. Foster or Cauer?
Foster networks fit datasheet curves easily but cannot be correctly cascaded with other stages. Cauer networks follow the physical layers and can be cascaded from junction to coolant.
22. When do I need Ansys Maxwell?
When the medium-frequency transformer is designed or verified in-house: to get leakage and magnetizing inductance, loss distribution and the electric field in the insulation.
23. When do I need Q3D Extractor?
When layout parasitics matter: commutation loop inductance of busbars and modules, and winding capacitance that affects soft switching and high-frequency behavior.
24. Why does the thermal model matter for insulation?
Insulation under DC stress conducts more where it is hotter, so temperature gradients redistribute the electric field. Hot spots and steep gradients in transformer insulation are a reliability risk that thermal and field models should flag for testing.
Workflow, buying and teams
25. How many PLECS-Ansys iterations are needed?
Usually one for early design and two before a design review. Stop when junction temperatures change by less than about a degree between iterations.
26. How do I predict lifetime under AI load cycles?
Run the load profile through the averaged model with thermal networks, rainflow-count the junction temperature cycles, and apply a power-cycling lifetime model from the module manufacturer or the literature. Feed the result into the FMEA.
27. What licenses does a typical SST team need?
One or two PLECS seats, one Ansys thermal seat (usually Icepak), and RT Box hardware for the lab. Maxwell and Q3D are added if transformer and layout design are done in-house.
28. What should I ask vendors when buying?
Term and start date, node-locked or floating, commercial use, included modules, support and training, transferability, and how quickly the license key can be issued.
29. How long does it take to get productive?
An engineer experienced in power electronics can build useful PLECS models within days. Icepak takes longer, because geometry preparation, meshing and validation need practice. Plan a starter model and vendor onboarding at the start of a program.
30. What is the most common mistake on SST simulation programs?
Trusting a single number from an unvalidated model. Layer the models, check each against the one below and against hand calculations, report uncertainty as bands, manage parameters and revisions carefully, and correlate with measurements as soon as hardware exists.
References and further reading
Product capabilities, editions and licensing change between releases. Confirm details with the vendors before purchasing. Links were current at publication.
Vendors
- Plexim: PLECS, PLECS Coder and RT Box
- Ansys: Icepak, Mechanical, Fluent, Maxwell, Q3D Extractor and Twin Builder
Standards and practice referenced
| Subject | Reference |
|---|---|
| MV DC transformers (system reference) | IEEE 2892 |
| Power electronic converter safety | IEC 62477-1, IEC 62477-2, IEC 61800-5-1 |
| Dry-type transformer practice and partial discharge | IEEE C57.12.01, IEEE C57.12.91, IEEE C57.124, IEC 60270 |
| Partial discharge under repetitive impulse voltage | IEC TS 61934 |
| Arc flash and electrical safety for MV testing | NFPA 70E |
Disclaimer
General information only. This article is published for general technical and educational purposes. It is not engineering advice for any specific project, design, product or site, is not issued for construction, manufacturing, procurement or certification, and carries no professional engineering seal. Decisions about a specific design require a site- and product-specific engagement, independent review and testing.
No warranty. The methods, figures, workflows and recommendations here are illustrative and are provided as is, without warranty of any kind, express or implied, including accuracy, completeness, fitness for a particular purpose or results. Simulation results depend on the models, data and assumptions used, and must be verified by measurement before they are relied on.
Limitation of liability. To the fullest extent permitted by law, Keentel Engineering (KEENTEL LLC) accepts no liability for any loss, damage, cost or claim arising from use of or reliance on this article, including indirect or consequential loss.
Software and vendors. Product descriptions are based on publicly available information and general industry practice at the time of writing. Features, editions, licensing and pricing are set by the vendors and change between releases. Confirm all details with the vendors before purchasing.
Illustrative examples. Examples and values are generic and illustrative. They do not describe any client's design, and no client information is disclosed. Keentel does not disclose past or current client names or project details, which are protected by confidentiality obligations to those clients.
Trademarks and non-affiliation. PLECS, PLECS Coder and RT Box are trademarks of Plexim GmbH. Ansys, Icepak, Mechanical, Fluent, Maxwell, Q3D Extractor, Twin Builder and SpaceClaim are trademarks of Ansys, Inc. or its affiliates. MATLAB, Simulink and Simscape are trademarks of The MathWorks, Inc. dSPACE, Speedgoat and OPAL-RT are trademarks of their respective owners. Their mention implies no affiliation with, endorsement of, or endorsement by Keentel Engineering.
State of Florida — Registry No. 36853 · Texas Firm Registration No. F-29821 · KEENTEL LLC, DBA: KEENTEL ENGINEERING. Copyright 1995-2026 Keentel Engineering. All Rights Reserved.
| Office | Address | Phone |
|---|---|---|
| Head Office — Tampa | 400 N Ashley Dr STE #2600, Tampa FL 33602 | (813) 389-7871 |
| Austin | 5900 Balcones Drive STE 100, Austin TX 78731 | (512) 591-0752 |
| Sacramento | 1401 21st St Ste R, Sacramento CA 95811 | (916) 913-4524 |
| Baltimore | 306 W Redwood St STE 200, Baltimore MD 21201 | (410) 225-2181 |

About the Author:
Sandip "Sonny" R. Patel, P.E.
IEEE Senior Member · Founder & CEO, Keentel Engineering
In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.
For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.
His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.
Services

Let's Discuss Your Project
Let's book a call to discuss your electrical engineering project that we can help you with.

About the Author:
Sandip "Sonny" R. Patel, P.E.
IEEE Senior Member · Founder & CEO, Keentel Engineering
In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.
For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.
Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.
His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.
Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.
Leave a Comment
We will get back to you as soon as possible.
Please try again later.
















