A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

PSCAD Power System Studies: Four Real-World Case Studies

Calendar icon. D

May 5, 2025 | Blog

Person looking at two computer monitors displaying technical diagrams and graphs.

PSCAD (Power Systems Computer Aided Design) is the industry standard for high-fidelity electromagnetic transient (EMT) and dynamic studies. At Keentel Engineering, our PSCAD modeling services help utilities, renewable developers, and independent power producers validate grid interconnection performance, ensure ride-through compliance, and optimize protection schemes. Below are four detailed case studies showcasing how our PSCAD-driven power system studies delivered actionable insights and millions in cost savings.


Case Study 1
Transient Stability Analysis for a 345 kV Renewable Interconnection

Client: Confidential Renewable Energy Developer (Midwest, USA)
Scope: 600 MW combined wind + BESS interconnection at a 345 kV POI adjacent to a weak grid.
Challenge: Verify ride-through capability, critical clearing times, and voltage recovery under fault conditions per NERC PRC-024-2.

Keentel Solution

  • Developed detailed PSCAD models for wind turbines, BESS converters, collector system, and substation.
  • Simulated three-phase, single-line-to-ground, and double-line-to-ground faults.
  • Determined breaker critical clearing times and evaluated dynamic reactive support needs.

Results

  • Demonstrated full compliance without adding reactive support equipment.
  • Saved the client $2 million in avoided hardware upgrades.

Case Study 2
EMT Simulation of Inverter-Based Resources in a Weak 115 kV Grid

Client: Confidential Utility Company (Southwest, USA)
Scope: 200 MW solar PV plant interconnection to a low-SCR 115 kV network.
Challenge: Identify sub-synchronous oscillations and high-frequency instabilities that RMS tools couldn’t capture.

Keentel Solution

  • Built a full EMT PSCAD model of PV inverters, plant controller, and grid-tie transformer.
  • Conducted VSC interaction and high-frequency stability analyses.
  • Developed mitigation strategies: PLL tuning and passive damping filters.

Results

  • Detected and neutralized damaging resonances early.
  • Kept the project on schedule without costly reactive power over-design.

Case Study 3
PSCAD Lightning Surge Study for a 500 kV Transmission Line

Client: Confidential Transmission Owner (Southeast, USA)
Scope: Validate insulation coordination for new 500 kV line and associated substations under direct lightning and back-flashover.
Challenge: Ultra-high voltage levels required precise energy-absorption modeling beyond standard arrester sizing.

Keentel Solution

  • Created a PSCAD model including tower geometry, insulator strings, and ground wire.
  • Simulated lightning strikes and storm variations across different soil resistivities.
  • Optimized surge arrester ratings and insulation levels.

Results

  • Reduced equipment capital cost by 8% while improving surge protection margins.
  • Minimized outage risk from lightning events.

Case Study 4
Controlled-Switching & TRV Analysis for 345 kV Circuit Breakers

Client: Confidential IPP (Texas, USA)
Scope: Evaluate transformer inrush, transient recovery voltage (TRV), and restrike risk at a new 345 kV/138 kV switching station.
Challenge: Insurance underwriter required proof that controlled switching would mitigate high inrush currents and TRV stresses.

Keentel Solution

  • Modeled station transformers, reactors, and breakers in PSCAD.
  • Ran point-on-wave switching simulations per IEEE C37.011 and IEC 62271-100.
  • Tuned controlled-switching device parameters and specified mitigation hardware.

Results

  • Achieved a 40% reduction in inrush current and guaranteed TRV compliance.
  • Secured favorable insurance terms and avoided costly breaker upgrades.

Our Service

Learn more about our full PSCAD Modeling Services and how we can tailor dynamic, EMT, and transient analyses to your project’s needs.


Next Steps

Ready to leverage PSCAD for your next interconnection or protection study?



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Leave a Comment

Related Posts

Florida large load grid requirements under SB 484 for data centers and 50 MW projects
By SANDIP R PATEL August 10, 2026
Learn Florida SB 484 large-load requirements, utility tariffs, 50 MW+ thresholds, interconnection costs, FERC reforms, and developer compliance steps.
Utility-scale solar plant performance and capacity testing
By SANDIP R PATEL August 10, 2026
Learn how utility-scale solar plant performance testing uses ASTM E2848/E2939 capacity tests and IEC 61724-1 performance ratio verification.
Owner’s Engineer reviewing energy project design
By SANDIP R PATEL August 9, 2026
Learn what an Owner’s Engineer does, key responsibilities, project benefits, and how independent oversight protects design, construction, and commissioning.
Substation reactor bank for voltage control and fault current limiting
By SANDIP R PATEL August 8, 2026
Complete guide to shunt, series & neutral reactors in substations — how they control voltage, limit fault current, and stabilize the grid.
ACB LSIG protection settings and trip-unit configuration
By SANDIP R PATEL August 8, 2026
Learn ACB protection settings for LSIG trip units, including Ir, Tr, Isd, Tsd, Ii, Ig, Tg, selectivity, coordination, and commissioning best practices.
Transformer protection systems
By SANDIP R PATEL August 8, 2026
Learn how transformer protection systems use CTs, relays, differential protection, REF, and testing to protect critical substation assets and grid reliability.
nerc
By SANDIP R PATEL August 7, 2026
Understand NERC PRC-029-1 ride-through requirements for IBRs in the CAISO region — voltage/frequency curves, key dates, EMT modeling, and compliance steps.
Substation grounding design with IEEE Std 80 earthing grid schematic.
By SANDIP R PATEL July 31, 2026
Learn substation grounding design using IEEE Std 80, CDEGS, soil resistivity modeling, touch and step voltage analysis, GPR, and earthing best practices.
Capacitor Banks & Power Factor Correction Design Guide
By SANDIP R PATEL July 29, 2026
Learn capacitor bank sizing, power factor correction, NEC Article 460 requirements, harmonic mitigation, protection, and installation for industrial power systems.